Current location - Recipe Complete Network - Catering franchise - About Sichuan Nanchong Construction Project Filing
About Sichuan Nanchong Construction Project Filing
After reading your question, in fact, the setting of this safety organization is to set up a safety team or leading group in accordance with the Safety Equipment Law. I'll show you the specific laws and regulations ... as for the information of civilized construction measures, I'll write it down below, and you can change it yourself.

Measures for the establishment of safety production management institutions and the allocation of full-time safety production management personnel in construction enterprises

Article 1 These Measures are formulated in accordance with the Regulations on the Administration of Work Safety in Construction Projects for the purpose of standardizing the establishment of safety production management institutions for construction enterprises and construction projects and the staffing of full-time safety production management personnel.

Article 2 These Measures shall apply to civil engineering, construction engineering, installation of lines, pipelines and equipment, and activities of new construction, reconstruction, expansion and demolition of decoration engineering.

Article 3 Safety production management institutions refer to construction enterprises and their independent functional departments established in construction projects to be responsible for safety production management.

Branches of large construction enterprises, such as branches and regional companies, shall independently set up safety production management institutions to be responsible for the safety production management of their own enterprises (branches). Construction enterprises and their subsidiaries, regional companies and other large branches must set up safety production management institutions in construction projects.

The responsibilities of the safety production management organization mainly include: implementing the national laws, regulations and standards related to safety production, compiling and updating the safety production management system in time, and organizing activities such as safety education and training for all employees and safety inspection.

Article 4 Full-time safety production management personnel refer to full-time personnel who have passed the safety production assessment by the competent construction department or other relevant departments and obtained the safety production assessment certificate, and are engaged in safety production management in enterprises, including the person in charge of the enterprise safety production management organization and its staff and full-time safety production management personnel at the construction site.

The person in charge of the enterprise safety production management institution shall, according to the actual situation of enterprise safety production, revise the rules and regulations of enterprise safety production in time, deploy safety production management personnel at all levels, supervise, guide and evaluate the safety production management of various departments or branches of the enterprise, and cooperate with relevant departments to investigate and deal with accidents.

The personnel of the enterprise safety production management organization are responsible for the statistics of safety production-related data, the equipment and inspection of safety protection and labor protection articles, and the safety supervision of the construction site.

Full-time safety production management personnel on the construction site are responsible for the patrol inspection of safety production on the construction site and make records. When potential safety hazards are found on site, they should be reported to the enterprise safety production management organization and project manager in time; Should immediately stop illegal command and operation.

Article 5 The full-time safety production management personnel in the safety production management organization of the general construction contracting enterprise shall be fully equipped according to the qualification categories and grades of the enterprise, and the number of full-time safety production management personnel shall be at least:

(1) group company-1 person/10,000 square meters/year (production capacity) or output value per billion buildings/year, and not less than 4 people.

(2) Engineering company (branch company, regional company)-1 employee/1 00000 square meters/year (production capacity) or every1100 million construction output value/year, with no less than 3 employees.

(3) Professional company-1 person/100,000 square meters/year (production capacity) or per1100 million building output value/year, and no less than 3 people.

(4) Labor service companies-1 workers /50 construction workers, and there are no less than 2 workers.

Article 6 A safety production management team headed by the project manager shall be established for a construction project. Team members should include full-time safety production management personnel assigned by the enterprise to the project. The full-time safety production management personnel are configured as follows:

(a) construction projects, decoration projects in accordance with the construction area:

1, 1 ,000 square meters and below have at least 1 person;

2, 10000 ~ 50000 square meters project at least 2 people;

3, more than 50000 square meters of the project at least 3 people, should set up a safety supervisor, according to the civil engineering, mechanical and electrical equipment and other professional set up full-time safety production management personnel.

(2) Total cost of civil works, lines, pipelines and equipment installation:

1 50 million yuan project has at least 1 person;

2, 50 million-65.438+0 billion yuan project at least 2 people;

3, 1 100 million project at least 3 people, should set up a safety supervisor, according to the civil engineering, mechanical and electrical equipment and other professional set up full-time safety production management personnel.

Article 7 Where new technologies, new processes and new materials are adopted in the project or there are many harmful factors and the construction operation is difficult, the full-time safety production management personnel on the construction site shall be increased according to the actual construction situation and the equipment standards stipulated in Article 6.

Article 8 If there are less than 50 construction workers in the construction project of a labor subcontracting enterprise, it shall set up 1 full-time safety production management personnel; 50 -200 people, should set up two full-time safety management personnel; More than 200 people, should according to the actual situation of partial project construction risk, not less than 5‰ of the total number of enterprises.

Article 9 The construction team shall have a part-time safety inspector to supervise and inspect the safety of the construction team's workplace.

Tenth the State Council railway, transportation, water conservancy and other relevant departments and places can

Formulate detailed rules for implementation according to these measures. The relevant departments have provisions, from its provisions.

Eleventh approach by the Ministry of construction is responsible for the interpretation of.

Expert review method for special construction preparation and scheme of dangerous project safety

Article 1 In order to strengthen the safety technical management of construction projects, prevent safety accidents in construction projects and ensure personal and property safety, these Measures are formulated in accordance with the Regulations on the Administration of Work Safety in Construction Projects.

Article 2 These Measures shall apply to civil engineering, construction engineering, installation of lines, pipelines and equipment, and activities of new construction, reconstruction, expansion and demolition of decoration engineering.

Article 3 Projects with greater risks refer to the seven subprojects mentioned in Article 26 of the Regulations on the Administration of Work Safety in Construction Projects, and a special safety construction plan shall be prepared separately before construction.

(1) Foundation pit support and dewatering engineering

Foundation pit supporting engineering refers to the excavation of foundation pit (groove) and the construction of supporting structure with a depth of more than 5m (including 5m); Or the foundation pit is less than 5m, but the geological conditions and surrounding environment are complex, and the groundwater level is above the pit bottom.

(2) Earthwork excavation works

Earthwork excavation refers to the earthwork excavation of foundation pits and troughs with excavation depth exceeding 5m (including 5m).

(3) Formwork engineering

All kinds of tool template engineering, including sliding mode, climbing mode, large template, etc. Formwork support system for horizontal concrete members and formwork engineering for special structures.

(4) Lifting and hoisting works

(5) Scaffolding engineering

1, floor-standing steel pipe scaffold with height over 24m;

2. Attach lifting scaffolding, including integral lifting and sectional lifting;

3. Cantilever scaffolding;

4. Portal scaffolding;

5, hang scaffolding;

6, hanging basket scaffolding;

7. Unload the platform.

(6) Demolition and blasting engineering

Manual, mechanical or blasting demolition projects.

(seven) other dangerous projects.

1, installation and construction of building curtain wall;

2. Tension construction of prestressed structure;

3. Tunnel construction;

4, bridge engineering construction (including bridging);

5, special equipment construction;

6, grid and cable-membrane structure construction;

7, more than 6m slope construction;

8. River diversion and closure construction;

9, port engineering, waterway engineering;

10, the adoption of new technologies, new processes and new materials may have an impact on construction workers.

The quality and safety of the project are recognized by the Administration, and there is no technical standard for construction.

Article 4 Preparation and review of safety special construction scheme

The safety special construction scheme prepared by the professional engineers and technicians of the construction enterprise shall be examined by the professional technicians of the technical department of the construction enterprise and the professional supervision engineer of the supervision unit, and signed by the technical director of the construction enterprise and the chief supervision engineer of the supervision unit.

Article 5 The construction industry shall organize an expert group to demonstrate and review the project.

(1) Deep foundation pit engineering

The excavation depth is more than 5m (including 5m) or the basement is more than 3m (including 3m), or the depth is less than 5m (including 5m), but the geological conditions, surrounding environment and underground pipelines are extremely complicated.

(2) Underground excavation engineering

Underground excavation and tunnel engineering with complicated geology such as karst caves, underground rivers, gas, rockburst, mud gushing and faults.

(3) Tall formwork project

The height of formwork support system for horizontal concrete members exceeds 8m, or the span exceeds 18m, the total construction load exceeds 10kN/m2, or the concentrated line load exceeds15kn/m. ..

(four) 30m and above aerial work projects.

(5) Deep-water operation projects of large rivers.

(6) Demolition blasting of urban houses and other large-scale earthwork blasting projects.

Article 6 Expert argumentation and evaluation

(a) the construction enterprise shall organize an expert group of not less than 5 people to demonstrate and review the prepared safety special construction plan.

(2) The expert group of safety special construction scheme must submit a written demonstration review report, which can be improved by the construction enterprise according to the demonstration review report, and can only be implemented after being signed by the technical director and chief supervision engineer of the construction enterprise.

(3) The written demonstration review report of the expert group is taken as the attachment of the special safety construction scheme. In the process of implementation, the construction enterprise shall organize the construction in strict accordance with the special safety plan.

Seventh the State Council railway, transportation, water conservancy and other relevant departments and localities may formulate detailed rules for implementation according to these measures.

Article 8 The Ministry of Construction shall be responsible for the interpretation of these Measures.

1 The enclosure of the construction site shall be set according to the project location: the height of the main road section and the urban landscape road shall not be less than 2.5m, and it shall be stable, neat and beautiful; The fence height of other sections shall not be lower than 1.8m to ensure stability and beauty; Facade of building and decoration engineering: The enclosure height of enclosure must be greater than 1.5m, which is higher than the working floor to prevent objects from falling.

2 the setting of enterprise characteristic signs on the construction site The setting of the gate, gate and flagpole on the construction site shall be subject to the unified standards of enterprises with different characteristics, and the abbreviation of group and enterprise specifications shall be indicated. Three flagpoles were erected at the construction site to raise the flags of the group and enterprises.

3 The site area distribution is reasonable and orderly, and the site capacity is clean and civilized. The construction area is strictly separated from the living area, the site appearance is neat, tidy and orderly, the civilized and material areas are neatly stacked, and the safety measures are in place.

4. Set up eye-catching safety signs. Set up eye-catching safety warning signs in construction areas and dangerous areas.

5. Set up "seven cards and one map" construction signs. Set up "seven signs and one map" at the main entrance and exit of the construction site: 1. Project introduction marks: project name, construction, design, construction, supervision unit, surrounding scope, area, engineering structure, floor, commencement date and supervision telephone number of the construction site; 2. Nameplate of project leader: including project leader, engineer, safety officer, quality engineer, hygienist, builder, planner and material engineer; 3. Six safety discipline cards. Safety production counting card (days) 5. Ten safety technical measures cards; 6, fire information card 7, health information card (figure); 8, site construction general layout

6. The site must be leveling, smooth drainage, prevent mud, sewage, waste water outflow or blocking sewers and drains.

(3) Provisions on "on-site sanitation"

1 The "Five Owns" facilities in life are complete, and the "Five Owns" facilities on site are complete and reasonable. Eye-catching environmental sanitation publicity signs and contracted maps of responsibility areas should be set up in the living quarters.

2 in addition to the "four pests", drainage, sewage flow, the implementation of various measures to control the four pests. Drainage, sewage flow, conditional should be green layout.

The dormitory should be cleaned. The dormitory uses 36V low-voltage electricity uniformly, and the daily necessities are neatly arranged. On-site offices, changing rooms and toilets should be cleaned frequently and kept clean and tidy.

4 The canteen meets the hygiene requirements of 1, and the erection of the canteen should comply with the regulations and go through the examination and approval procedures; 2, the canteen and the surrounding should be clean and tidy, no water; 3. The container should be marked raw and cooked, veiled, and the canteen with conditions should be sealed; 4. Every year from May to 10, samples (not less than 50g) shall be kept for 24 hours and recorded; 5. Tableware and tea sets should be strictly disinfected, and the use cost should be disinfected every day to prevent cross-contamination. The supply of tea should meet the hygiene requirements; 6. The cook should have an annual physical examination, hold a health certificate and a health post certificate, be diligent, and maintain good personal hygiene habits.

5. Domestic waste management should be put into containers, placed at fixed points, managed by special personnel and cleaned regularly.

6. Health requirements 1, having an infirmary, or conducting on-site medical rounds at least twice a week; 2, do a good job in the publicity and education of workers' health and disease prevention, and introduce the knowledge of disease prevention to workers in the form of blackboard newspaper; 3, medical staff to supervise health, regularly check the place such as canteen hygiene.

Third, the provisions of "civilized construction"

1 On-site publicity requires that eye-catching publicity slogans reflecting the spirit of enterprise and the style of the times be set around the site; Set up propaganda posts and blackboard newspapers at the construction site to reflect the internal and external trends in time.

2 Team building requires strengthening team building. The site should provide necessary activity places for the team, with good class capacity and safety records of three posts and one evaluation, so as to improve the quality of the team.

The comprehensive management of public security requires strengthening the comprehensive management of public security on the construction site, achieving target management, implementing the system, putting the responsibility on people, taking effective public security preventive measures, putting in place preventive facilities for key parts, defining outsourcing teams, establishing file cards, signing public security fire prevention agreements and strengthening legal education.

4. Community service requires cooperation with the region during the construction period, to carry out * * * civilized activities, to think of the people, to reduce the construction noise, to make the construction not a nuisance, and to make the project a caring project and a convenience project.

5 fire safety 1, establish fire safety organization, obligatory fire brigade and fire prevention files; Clarify the fire safety responsibilities of the project leader, management personnel and each operation post; 2, according to the provisions of the configuration of fire equipment, personnel management, the implementation of fire prevention system and measures; 3, according to the construction area, hot work level, hot work must have "two certificates, a device, a guardianship"; 4. Strictly manage inflammable and explosive articles and set up special warehouses for storage.

Four, construction safety, construction civilization and safety civilization construction technology

(1) Creating a civilized construction site means creating a safe construction site, and the civilization of construction will bring construction safety. The purpose of creating a civilized construction site is to establish a civilized image and ensure safe production. In the above civilized construction site standard management regulations, most of them are related to ensuring the safety and health of employees, which almost summarizes the management requirements of all aspects of safety production. Therefore, to create a civilized construction site is to create a safe construction site, and to create construction safety with the civilization of construction.

(2) Safety and civilization are inseparable, and they are * * * one, forming a * * body of safety and civilization. Although the above provisions list safety clauses and civilized clauses respectively, there are civilized requirements in the safety clauses and safety requirements in the civilized clauses. In fact, the two are inseparable, and * * * is integrated into one to create a safe and civilized * * * body. Therefore, we must have such an understanding of security and civilization and their relationship.

(3) The meaning of architectural civilization, human civilization is the embodiment of cultural development level, social civilization is the embodiment of social and cultural development level, and architectural civilization is also the embodiment of architectural cultural development level. The development level of architectural culture is reflected in the development level of staff culture and architectural science and technology.

(4) Safe and civilized construction technology is an important part of construction civilization. Because safe and civilized construction technology is the concentrated expression of building science and technology and an important part of building civilization.

(5) The tasks and contents of safe and civilized construction technology. The task of safe and civilized construction technology is to create a safe and civilized construction production state and standardize the safe and civilized behavior of construction production. The safe and civilized state of building production includes two aspects: creating a safe and civilized construction site and adopting safe and civilized construction technology, and the safe and civilized behavior of building production is to carry out safe and civilized operation and operation. These three aspects of technology and its branches constitute a safe and civilized construction technology system. In view of the close internal relationship between the five components of the construction safety technical guarantee system, and the safe and civilized construction technology is the basic link, its projects will inevitably overlap with other projects to some extent.

Five, the basic requirements of creating a safe and civilized construction site

1, construction site classification

Construction sites can be divided into the following categories according to their scope and architectural characteristics.

(1) Construction area, that is, the construction area designated by large-scale construction projects, including completed area, area under construction, area to be built, enterprise production area and enterprise living area. The relevant planning arrangements shall meet the requirements of maintaining the regional environment, city appearance, traffic conditions, safety and civilization of the city or place.

(2) The construction site, that is, the construction area where the project is under construction, includes the construction and production operation area, the material stacking area and the reservoir area, and the temporary facilities area for management and living.

(3) The construction operation area, that is, the area or lot where the construction operation is under way, includes the following three types:

1) Single operation and normal cooperative operation section, that is, the section with single operation as the main task and other cooperative operations. For example, in the working area of structure and wall construction, the structure and wall are the main ones, and other water, heating, electricity and sanitary pipeline laying operations are carried out in coordination.

2) Cross-operation section, that is, the section where various operations cross and coordinate. In the crossover operation section, there is no obvious dominant single operation (all other operations must obey and cooperate with its construction requirements), so it is necessary to make coordination arrangements among all simultaneous crossover operations to ensure orderly, safe and smooth operation.

3) Special operation and dangerous operation sections, that is, special operations such as electric welding, blasting, prestress, high pressure and underwater, and sections of toxic, harmful and dangerous places.

For different types of construction sites, in addition to observing the general requirements of safe and civilized construction, we should also pay attention to meeting their special requirements.

2. Basic requirements for creating a safe and civilized construction site

(a), the basic requirements of the construction general layout

1 area is divided into construction operation area, auxiliary operation area, material stacking area, construction management and living facilities area according to functions.

2. Regional cross protection: Take protective measures for cross parts with safety problems.

3 tower crane settings meet the requirements of operation coverage and the safety requirements of boom rotation area.

4 Outland enclosure ① Enclosures isolated from the outside world are set around the construction site; (2) In the street or densely populated areas, it is advisable to build guardrails and scaffolding to enclose the outside.

5 Three links, one leveling and one drainage

6 site temporary electricity facilities

7 signs, signage facilities, corporate signs, engineering signs and safety signs are complete.

8 fire control facilities

(2) Basic requirements for three links, one leveling and drainage, dust control and waste control

1 Level the site, remove obstacles and have no potholes.

2. The roadway and sidewalk are solid and flat, with good vision, no water accumulation in rainy season, smooth between entrances and exits, and traffic signs are set up where necessary; At track intersections (tower cranes, etc. ), garage and sidewalk, flat measures should be adopted.

3. Power supply and water supply lines should be erected at the site of Dentsu and Shuitong.

4 drainage and sewage should have a good drainage system, and set up a sewage sedimentation tank to properly handle sewage. Untreated sewage shall not be directly discharged into urban sewers and rivers.

5 Dust Control and Waste Control Control Control the dust, waste gas, waste water and solid waste on the construction site. It is advisable to use sealed air ducts or other dust-proof methods to clean up high-altitude garbage, and regularly clean up garbage. It is forbidden to use garbage soil containing wastes and toxic substances as backfill soil.

(3) Basic requirements for organizing and preventing (fencing) in the operation area

1 The operation area shall be organized with a working site or working surface that meets the requirements, obstacles that affect the operation have been removed, dangerous protrusions have been properly disposed of, materials are neatly stacked, and there is a good safe passage.

2. Clean up the dismantled materials such as templates and scaffolding, as well as construction surplus materials, waste materials and garbage, and remove the nails on the wood in time or take photos (to prevent foot prick).

3 Protection of dangerous operation areas In areas where stones or articles may fall, pop up, splash and other injuries, safety protection measures should be set up to protect the safety of other people on site.

(4) Basic requirements for storing materials, equipment and tools.

1) Materials and articles shall be palletized, and the site shall be leveled and paved; In accordance with the location specified in the layout, neatly stacked and stable, not exceeding the specified height; The material shall be at least 500mm away from the enclosure or temporary building wall, and both ends of the entrance shall be blocked. It is forbidden to pile up materials near the fence or temporary building wall.

2) Scaffolding stacking of materials and articles is easy to roll (slide), and scaffolding stacking of materials and articles with high center of gravity should be stable and reliable. Design when necessary, and set strict design requirements.

3) Storage of flammable and toxic substances Paint, thinner and other flammable substances harmful to employees' health should be classified and stored in a well-ventilated special warehouse, without fireworks and fire-fighting supplies, and asphalt should be placed in a dry and ventilated place to avoid direct sunlight.

(five) the basic requirements and regulations of on-site fire protection

1) General provisions 1, key projects and high-rise buildings should prepare fire prevention technical measures and perform examination and approval procedures, and general projects should have fire prevention technical schemes; 2, according to the provisions of the configuration of fire fighting equipment, facilities and materials, and establish a fire control organization; 3. Clearly define the fire zone and the no-fire zone; 4, hot work must fulfill the examination and approval system, hot work operators hold relevant certificates and have special care; 5, regular fire inspection, eliminate fire hazards in time.

2) Daily management of fire-fighting equipment 1, and the fire-fighting ladder is kept intact; 2. Check the water gun regularly, keep the switch flexible, the nozzle unblocked and the accessories complete without corrosion; 3, hose collection should be rolled up in a single layer, vertical on the shelf; 4, all kinds of pipeline interface should be flexible, elastic moderate, no leakage, shall not fall when using; 5. Fire hydrants should be inspected regularly according to different indoor and outdoor requirements and lubricated in time. Fire hydrants should be cleaned frequently and anti-freezing measures should be taken in winter.

3) 1, fire control measures such as high-pressure water pump with sufficient lift for building construction above 24m; 2, according to the need to add temporary water tank, to ensure that there is enough fire water; 3, set up a full-time fire coordinator patrol inspection; 4, the scene is equipped with alarm device, timely report the fire.

4) the basement construction fire prevention 1, keep the entrance unobstructed; 2. It is forbidden to place oxygen cylinders and acetylene cylinders at the openings and blowholes of doors and windows; 3, are not allowed to be used as dangerous goods warehouse and storage of toxic and flammable items; 4, should have a fire alarm device.

5) Fire fighting in boiler room 1, equipped with suitable fire extinguishers every 25m2 area; 2. Smoke and dust suppression and Mars fire extinguishing devices should be installed on the chimney; 3, it is strictly prohibited to pile up other fuels and burning garbage in the room.

6) forging furnace's operation of fire prevention 1 on site must be checked by the fire safety department and obtain the fire protection approval certificate; 2, when using flammable liquid, should control the temperature, to prevent the liquid spontaneous combustion; 3. forging furnace should be built with refractory materials and equipped with fire fighting equipment.

I hope it helps you.