Source: Tiantai Daily
Meaning of 1. 91 days:
The average enterprise investment project is "at most 91 days" (for small-scale projects, the whole process of approval from project coding filing to completion acceptance does not exceed 91 days, and small-scale projects refer to projects with a building area of not more than 5,111 square meters, a building height of not more than 8 meters, a single function and simple technical requirements.
II. 91 days:
Enterprises investing in Zhejiang Province, except those included in the negative list.
Negative list:
1. Linear engineering projects refer to highway, railway, power grid engineering, oil pipeline network, gas pipeline network and other construction projects involving river basin influence;
2. Projects involving major social stability risks and major environmental impacts;
3. Projects involving state-approved projects that need provincial-level elements to support;
4. Non-operating projects and public welfare projects of state-owned enterprises, as well as projects that need bidding according to the provisions of the Bidding Law;
5. Projects involving the production, storage and transportation of inflammable and explosive dangerous goods and dangerous chemicals, projects with particularly complicated technical difficulties and large construction scale, and projects whose preliminary work is suspended due to environmental protection, fire control and other reasons;
6. Real estate projects with a total investment of more than 2 billion yuan or a construction area of more than 251,111 square meters, which are particularly large in scale and complex in format.
note: the proportion of negative list items (the total number of negative list items/the number of enterprise investment projects that need to issue construction permits) in each district and city should be controlled within 11%.
composition of three. 91 days:
"maximum 91 days" consists of government approval time, government entrusted intermediary service time and public utility access service time, excluding the owner's independent preparation time and owner entrusted intermediary service time.
1. Time for government approval, that is, when the application materials are complete and meet the statutory acceptance conditions, the time for government departments to approve the application from acceptance to completion, excluding the time required by law for expert review, public announcement, hearing and on-site verification.
2. The time when the government entrusts the intermediary service, that is, the service time from accepting the application to the service result passing the government audit, excluding the time when the design text is revised and improved and re-declared.
3. time for public utilities to access services, including the time for municipal public service departments to accept, handle and complete access (that is, put into use).
4. 91 days and four stages of approval process and requirements:
1. Project establishment stage. It mainly includes the filing of enterprise investment projects, the examination and approval of construction project site selection, the pre-examination of construction project land, the review of social stability risk assessment report, and the review of resettlement planning. At this stage, the project coding is the starting point, and the enterprise investment projects are completed for filing and approval, and the principle limit is 21 days.
2. Planning permission stage. It mainly includes water intake permit, examination and approval of construction projects involving rivers and dikes, examination and approval of seismic fortification of over-limit high-rise buildings, and issuance of planning permit for construction projects. At this stage, from the completion of filing and approval of enterprise investment projects to the issuance of construction project planning permits, the principle limit is 21 days.
3. Construction permit stage. It mainly includes construction drawing review, fire protection design review, lightning protection device design review, construction drawing design of large-scale single-building civil air defense project and underground space development, civil air defense project quality supervision procedures, forest cutting permit, construction permit issuance and other matters. This stage is completed in 21 days from the issuance of the planning permit of the construction project to the issuance of the construction permit of the construction project.
4. completion acceptance stage. It mainly includes the verification of construction project completion planning, land review and acceptance, lightning protection device completion and acceptance, civil air defense project or underground project completion and acceptance record that takes into account civil air defense needs, housing construction project and municipal infrastructure completion and acceptance record, construction project (including underground pipeline project) file pre-acceptance, real estate registration, and public utilities such as water, electricity and gas access. This stage starts from the first special verification and ends with the issuance of the real estate certificate, and the upper limit in principle is 31 days.
v. Intermediary services involved in the trial:
1. Intermediary services entrusted by the government. It mainly includes construction drawing design review, energy saving evaluation, etc.
2. The owner entrusts intermediary services. It mainly includes the compilation of construction project design documents, construction drawing design documents, soil and water conservation plans, environmental assessment documents, energy-saving assessment reports, water resources demonstration reports of construction projects, surveying and mapping results reports, and quality inspection reports of civil air defense equipment.
Tiantai County Administrative Examination and Approval Bureau
Sweep and add customer service WeChat
Join Taizhou House Purchase Group II
(indicate the house purchase area, Group I is full)
Sweep and pay attention to WeChat WeChat official account
Learn more exciting content.