I. General process
Pre-design-main body demolition-hydropower transformation-carpentry-tiling-wall painting-water heater installation-kitchen ceiling-cabinet installation-range hood installation-wooden door installation-floor installation-wallpaper paving-switch socket installation-lamp installation-hardware sanitary ware installation-curtain rod installation-pioneer cleaning-furniture introduction-household appliances installation-home accessories.
(1) Pre-design
In the preliminary design, the room should be measured in detail, including:
1. Define the area involved in the transformation. Especially: tiles, wall paints, wallpapers, floors and other fields;
2, clear wall size. Especially the size of the wall where furniture needs to be placed. Remind everyone: before starting work, don't forget to go to the property to go through the formalities of starting work and pay the decoration deposit.
(two) the main body is removed or changed.
In the construction stage, the main body demolition and transformation is the primary project, including: wall demolition, wall masonry, wall peeling, plastic steel window replacement and so on. When the main body is demolished and changed, the frame is put up first.
(3) Hydropower transformation
Before the hydropower transformation, the main demolition transformation was basically completed. The first measurement of the cabinet was carried out between the hydropower transformation and the main demolition. Because the wall and floor are not treated, the designer can't give specific design dimensions, but just put forward some suggestions. Mainly includes:
1, whether the lampblack machine socket will affect future installation;
2, the location of the water meter is appropriate;
3. Whether the water inlet is convenient to install the sink.
After the waterway reconstruction, it is best to waterproof the bathroom. The kitchen doesn't usually do this.
(4) Woodworking
Woodworking, bricklayer and oiler are the "three brothers" in construction, and the order is wood-tile-oil. Introductory principle: "Whoever is dirty will go first".
(5) Tiling
The process of working in the "bricklayer's second child" involves the following three links:
1. Installation of lintels and marble windowsills. The threshold is paved with floor tiles.
2. Install the floor drain. Floor drain is the earliest hardware, which is installed with floor tiles. Therefore, when you start to buy building materials, you should buy a floor drain as soon as possible.
After the kitchen wall and floor tiles are pasted, you can make an appointment for the second measurement of the cabinet.
(6) Paint the wall
The "Third Oil Worker" enters the site to finish the basic treatment of the wall and paint the furniture. Students who are going to paste wallpaper only need to let the wall surface be treated at the grassroots level.
(7) Installation of water heater
After the wall and floor decoration is completed, the water heater is delivered for installation. The water heater is installed in front of the ceiling.
(8) Ceiling in kitchen and bathroom
After the water heater is installed, the next step is the ceiling. The kitchen and bathroom ceiling takes the lead. Kitchen and bathroom ceiling, kitchen and bathroom moisture-proof ceiling lamp and exhaust fan to buy. Generally, the ceiling lamp and exhaust fan in kitchen and bathroom are installed at the same time.
(9) Installation of cabinet
After the ceiling is finished, you can install the cabinet on the door. Install sink and gas stove at the same time. It is best to turn on the gas before installing the cabinet, because it needs to be tested after installation.
(10) Installation of cigarette machine tool
The range hood cooker is best installed with the cabinet on the same day, which is convenient for the master to coordinate.
(1 1) wooden door installation
The second day after the installation of the cabinet, the wooden door was measured more than a month ago, and you can make an appointment to install it now. The production of solid wood doors takes one month. Therefore, in order to make the construction period closely connected, the wooden door manufacturer will be invited to conduct on-site measurement after the main body is demolished.
(12) Floor installation
The wooden door can be installed on the second day, and several problems should be paid attention to in floor installation:
1. Before the floor is installed, let the manufacturer investigate whether the ground needs leveling.
2, before the floor installation, the ground should be clean, at the same time ensure that the ground is dry.
(13) Laying wallpaper
The day after the floor was installed, the house was cleaned up, but wallpaper was put up. Protect the floor on the day when the wallpaper is laid; Clean up the wallpaper glue left on the floor. Before pasting wallpaper, the wall should be "nothing".
(14) switch socket installation
In the bathroom, the socket and switch must be waterproof, and the socket should be covered. The light switch at the entrance is suggested to be inductive or fluorescent.
There are more switch sockets than less, and there are more and more household appliances. Once there is no socket, it is difficult to install it again.
(15) Installation of lamps and lanterns
After the lights were installed, the home lit up and bid farewell to the dazzling light of incandescent lamps.
(16) Installation of Hardware Sanitary Ware
Buy good pipe fittings, toilets, clothes hangers, etc. And install them together. After the "big pieces" are installed, the home is still "cold", and after the lamps and hardware sanitary ware are installed, the home is "alive".
(17) Installation of curtain rod
With the installation of curtain rods, home improvement is basically over.
(18) development and cleaning
Don't install curtains before opening and cleaning. When cleaning in the frontier, don't have unnecessary household appliances at home, and leave more "planes" for thorough cleaning.
(nineteen) furniture comes into play
For the purchase of furniture, it is suggested that the basic size of the water circuit is roughly the same after the transformation.
(20) Home appliances come into play
Home appliances should enter the site, be installed and be ready to move in.
(21) Home accessories
Might as well go to Taobao to buy some home accessories and put them in a conspicuous corner to make the home look no longer monotonous.