What specific matters should the Infrastructure Office coordinate? Learn something for the leaders' reference first. Urgent.
As a unit is about to carry out an infrastructure project, it is necessary to organize a team of members to complete the relevant procedures of project construction on behalf of Party A, organize the implementation of design, supervision, survey and construction bidding, and organize the supervision and management of the construction site, which is referred to as "Infrastructure Office" for short.

I. Composition of the Infrastructure Office

Party A, the construction subject, is responsible for the preparation of the members of the Infrastructure Office. The person trusted by the general unit is the person in charge, which may include professionals who know something about engineering construction, and the number may be 3- 10.

Second, the role of infrastructure office

The establishment of the Infrastructure Office is mainly to cooperate with the project-related partners, such as construction application, design, supervision and construction, to complete the project construction, coordinate the relationship between the parties on behalf of the construction subject, namely Party A, organize various bidding procedures, and supervise and manage on-site operations.

Three. Responsibilities of the Infrastructure Office

Ensure the orderly and rapid implementation of the project construction, ensure the progress, quality and safety of the project, effectively control the number of projects, and save the project cost for Party A. ..

Then I will give you a summary and prospect of the work of the school infrastructure office, which should be your reference.

2009 Annual Work Summary and 20 10 Work Plan of Infrastructure Office

With the stability of our school's scale, on the basis of meeting the basic teaching needs, the capital construction projects in 2009 mainly focused on improving the scientific research environment, improving the teaching practice environment and improving the living service facilities to meet the requirements of the school's characteristics and connotation development. The work of the Infrastructure Office in 2009 is summarized as follows:

First, strengthen the study of political theory and professional knowledge, and improve work enthusiasm and work ability.

1. Political theory study.

This year, there is an upsurge of learning from Scientific Outlook on Development in the study of political theory. Scientific Outlook on Development is the party's guiding ideology stipulated by party constitution, the producer party of China, the development of Marxism and Mao Zedong Thought by the fourth generation of the party's leading collective with Hu Jintao as the general secretary, and an important part of Socialism with Chinese characteristics's theoretical system, which points out the ideas and strategies for us to further promote China's economic reform and development. In our work, we should use Scientific Outlook on Development to guide our work, adhere to all-round development and make overall plans.

2. Business knowledge learning.

Infrastructure office is a highly technical management and service department. At present, the knowledge level and knowledge structure are updated very quickly, and the application of new technologies, the introduction of new laws and regulations and the implementation of new policies are constantly impacting every technical manager. Facing the new situation, only by continuous learning can we adapt to the needs of work. The leaders of the Infrastructure Office encourage comrades to strengthen their business study and improve their business and management level through various means.

3. Online publicity and learning.

In 2009, the website of the Infrastructure Office was revised and its appearance was completely new. The new website strengthens the publicity and implementation of laws and regulations, as well as the update of new professional technology and knowledge for everyone to learn and communicate; The information disclosure of capital construction projects has been strengthened, including basic information such as project overview, project pictures and project progress, which can be inquired; There are also links to download declaration forms and documents commonly used in the construction field, which greatly improves work efficiency. Website construction is a platform for publicity, learning and communication.

Two, strict capital construction management procedures, improve work efficiency and effectiveness.

According to the current national laws and regulations in the field of construction and the local laws and policies of Anhui Province and Hefei City, we strictly follow the basic construction management procedures, act according to laws and regulations, make government affairs open and transparent, and further improve work efficiency and achievements.

1. The supporting fees for construction projects were reduced by nearly 6 million yuan in the whole year.

According to the regulations of Hefei municipal government, all construction projects must pay a large amount of urban construction supporting fees to the government. The library project, catering center project and wheat regional innovation building project started in our school this year should pay 4.56 million yuan, 2.32 million yuan and 6 1 10,000 yuan respectively; After reporting to the municipal government, my office requested the municipal government to consider reducing or exempting the large supporting expenses for supporting the development of education. The municipal government reduced the large supporting fees of the three projects by 4 1.8 million yuan, 1.32 million yuan and 350,000 yuan respectively, totaling 5.85 million yuan.

2. Make full use of the bidding mechanism to save construction funds about120,000 yuan.

Publicly release the bidding information of construction projects, publicly bid and bid, and evaluate and select the bid fairly and justly. Make full use of the buyer's market in the construction field, and combine the good reputation of our school in strictly performing the contract in Hefei construction market. Our office works closely with the relevant departments of the school, carefully conceiving the bidding documents and answering questions, and recruiting the winning bidder at a reasonable low price. Bidding for construction, decoration, installation and building materials procurement of several construction projects this year has saved about120,000 yuan in construction funds.

3. Strict site management, quality and quantity.

A. Actively ask for supervision and audit to improve the transparency of work. All aspects of infrastructure management actively invite and sincerely accept the supervision of the school discipline inspection commission, and invite the school discipline inspection commission to conduct on-site supervision and inspection from the aspects of bidding information release, qualification examination, bidding document preparation, bill of quantities preparation, and bidding for building materials and equipment. In order to effectively control the investment, our office actively requires the school audit department to intervene in advance and follow up the audit throughout. The acceptance of concealed works, important design changes, expensive economic visas and the determination of material prices are all decided by the school audit department.

Infrastructure work has always been carried out in an open and transparent environment, which has curbed the occurrence of violations from the source, ensured the healthy and orderly development of infrastructure work, and provided a strong organizational discipline guarantee for the construction of the project, avoiding many suspicions from the outside world.

B. Implement the project supervision system and strictly control the project quality. Due to many infrastructure tasks, heavy workload and few personnel, in order to ensure the quality of engineering construction, in accordance with state regulations, the supervision system is introduced through public bidding, and the construction unit is inspected and supervised by a third party. As the basic construction management department of our school, the Capital Construction Office assigns more than two people to cross the site for each project to jointly manage the construction site with the supervision unit, and urges the construction unit to strictly follow the contract terms, current engineering specifications and national mandatory standards, and requires the supervision to conduct supervision and inspection and stand by.

C. clarify responsibilities and strengthen quality supervision and management on the construction site. The site representative stationed at the site is responsible for the project quality. Site management personnel are familiar with the construction drawings and acceptance specifications, always pay attention to the quality and progress of the project, sample the building materials entering the site, and witness the sampling and inspection; Hold supervision meetings on a regular basis, sum up the quality and progress in the early stage in time, solve the site problems, arrange the construction plan for the next stage, and report to the superior leaders in time for matters that cannot be determined by the Infrastructure Office, so as to implement all the work and make the project proceed smoothly and orderly.

In order to ensure the quality and quantity of the work completed on time, the problems found in the project will be rectified in time and will never be soft. For example: ① During the pier foundation construction of the restaurant center project, the construction enterprise mistook the concrete with the design strength grade of C25 for C 15 concrete, and poured it into the pier foundation, which was found by the site management personnel during the on-site inspection and reported in time. Our office immediately ordered the construction enterprises to stop construction immediately and carry out internal rectification. At the same time, the administrative person in charge and technical person in charge of the construction enterprise are required to go to the construction site to solve problems, strengthen the internal management of the enterprise, replace the original project management team of the project, and instruct the construction enterprise to carry out rectification according to the technology developed by the design institute. ② During the construction of the library project, it was found that the design of the construction drawing was rough, and there were a series of problems such as unclear identification, wrong size, dislocation between the structure and the building, and lack of structural safety considerations. Contact the design institute immediately after finding the drawing problems, and organize the design, construction and supervision units to make disclosure, revision and improvement of the construction drawings for many times. Because there are too many problems in the construction drawing designed by the design unit, which can not be solved in time, the construction site once stopped working and waited. Our office strongly requires designers to answer questions on the spot. Shenzhen Architectural Design and Research Institute Co., Ltd. entrusts its Hefei branch to send people to the construction site to answer questions and solve problems in the drawings. At the same time, the chief engineer of the design institute is required to organize the professional designers of the project, such as architecture, structure, water supply and drainage, electricity, heating and ventilation, to conduct comprehensive drawings mutual review and improve the construction drawings by themselves; When the design institute failed to provide on-site service in time, our office sent personnel to Shenzhen with the construction enterprise to communicate with the designer to solve the drawing problem and make the project go smoothly. However, there are too many problems in the construction drawings designed by the design unit, and they are still communicating to solve the problems in the drawings.

4. Further standardize the management of economic visas and design changes.

In order to further control the investment cost, all design change orders, technical contact orders, economic visa orders, etc. In the process of project construction, any increase or decrease in project cost must be strictly examined and approved before construction can be carried out, which can be used as the basis for final accounts of the project. The increase or decrease of the project cost within RMB 6,543,800+0,000 shall be approved and confirmed by the director of the Infrastructure Office; The increase or decrease of project cost between 1-50000 yuan shall be approved and confirmed by the person in charge; Where the project cost is increased or decreased by more than 50,000 yuan, it shall be approved and confirmed by the client.

5. Cooperate with the Provincial Department of Education to carry out special treatment of outstanding problems in the construction field.

In order to fully implement the Notice on Printing and Distributing (Jian Jian [2009] No.28), effectively control the outstanding problems in the field of engineering construction, ensure the standardized operation of the transaction behavior and administrative power of school engineering construction, and further promote the construction of anti-corruption in schools. Our office has formulated an implementation plan for special treatment of outstanding problems in the field of engineering construction.

Conduct a comprehensive investigation of engineering projects since 2008, especially those invested by the government, using state-owned funds and under construction, carefully find out the main problems existing in key parts and key links such as project decision-making, planning, project establishment, design, bidding, investment and construction, deeply analyze the causes of the problems, and earnestly carry out rectification. Improve the rules and regulations of school capital construction management, form a unified and standardized engineering construction procedure, standardize market behavior and administrative behavior, promote the innovation of project management system and mechanism in our school, and promote the sound development of school capital construction.

Three. Main work completed in 2009

1. Library project

Library project, with a construction area of 42546m2, with the approval number of Development and Reform Agency [2006] 122. This project completed the bidding for civil works this year 1 month, and then completed the demolition of bungalows, three links and one leveling, planning permit and construction permit within the construction site, and started construction on June 6, 2009.

At present, the main building has completed the structural engineering of civil air defense basement and conference center. In order to facilitate the smooth connection of other professional work in the later period, during this construction period, civil air defense equipment bidding, fire engineering bidding, elevator bidding, interior decoration and exterior curtain wall design and construction bidding were carried out, and coordination with the general contractor was organized.

The bidding for HVAC engineering and weak current integrated wiring design is under way.

2. Catering Center Project

The catering center project, with a construction area of 12068m2, has been approved with the approval number of [2008] No.574. This year, the plan design positioning audit, the bidding work of the construction unit and supervision unit, the planning permit and the construction permit have been completed. The project broke ground on September 9, 2009 19, and the pile foundation construction is currently under way.

3. Science and Technology Building Project

Science and technology building project, with a construction area of 2564 1m2, has the approval number of Jiaojiji [2006] No.6. At present, the project is under construction of architectural design scheme. According to the instructions of the school leaders, geological survey, preliminary design demonstration, construction drawing design, bidding by construction units and supervision units, environmental assessment and other work are carried out simultaneously.

4. Agricultural Park Complex Building Project

The comprehensive building project of agricultural park, with a construction area of 9,989 square meters, was approved by J&J [2006] No.84, and the construction site is high-tech agricultural park. This year, the construction drawing design, pre-qualification of construction bidding, supervision bidding registration, health audit, fire audit and construction drawing audit have been completed, and the planning permit is being processed.

5. Graduate apartment and comprehensive building project

Postgraduate apartment and comprehensive building project, with a construction area of about 70,000 ㎡, with approval numbers of No.464 and No.309 of Development and Reform Society Letter [2007]. This year, the project approval of 40,000 ㎡ comprehensive building was completed, and the fire protection, sanitation, environmental protection, earthquake resistance and architectural design scheme and positioning were reviewed, and the preliminary design was demonstrated by experts. At present, geological survey and construction drawing design are under way.

6.5#, 6# student apartment construction project

Student Apartment 5# and 6# student apartment building projects, with construction area of 13022m2, with approval number of [2006] 147. In June 2008, 165438+ 10 broke ground and was put into use at the end of August 2009. This year, the interior decoration project, water and electricity installation project, student apartment furniture bidding installation and outdoor road engineering bidding construction will be completed; Complete fire control acceptance, indoor environmental inspection, lightning protection and grounding acceptance, environmental protection acceptance, planning acceptance, urban construction archives filing, quality supervision and acceptance filing and other related procedures, and successfully complete the acceptance and delivery.

7. Tea teaching experimental factory

The tea teaching experimental factory project, with a construction area of 1 196m2, has been approved by documentNo. [2006]262, and the construction site is in the high-tech agricultural park. It started in August 2008 and was completed and put into use in May 2009.

8. Wheat Regional Innovation Building

The wheat regional innovation building project, with a construction area of 3 196m2, is a scientific research project invested by Agricultural College in the agricultural park with the approval number of Development and Reform Society Letter [2007] No.759. The construction site is in the high-tech agricultural park. In April 2009, ground was broken. At present, the main building has been completed and the outdoor supporting projects are under construction.

9. Reconstruction project of three canteens' kitchens

The renovation project of the back hall of No.3 canteen, with a construction area of about 650m2, started at the end of 2008. Due to the concession of the planning road red line of Anqing West Road in Hefei, it was delayed for some time. It was put into use in the summer of 2009 and is now running normally.

10.GMP construction enterprises bid.

1 1. Cooperate with the Provincial Department of Education to conduct investigation and statistics on capital construction in various periods.

12. Bidding registration, prequalification and inspection of the construction enterprise of the second track and field stadium.

Four. 20 10 work plan

1. Library project

20 10.65438+ 10 HVAC project bidding

2010.1-March weak current integrated wiring design and construction bidding

From March to August, 20 10, the materials provided by Party A, such as granite, aluminum alloy doors and windows, distribution boxes, were invited for bidding and professional subcontracting.

20 10. 1-9 construction capping of main structure.

2010.10-12 entered the stage of hydropower, weak current, fire protection and decoration construction.

2. Catering Center Project

Complete the structural construction, decoration construction, water and electricity installation construction, outdoor engineering construction and other construction contents of the catering center project, and go through the acceptance procedures of fire protection, environmental protection, sanitation and planning, and deliver it to use in September of 20 10.

3. Science and Technology Building Project

Because the project is an emergency project required by the school leaders, the capital construction procedure is unconventional, and in order to strive for construction time, synchronous construction is adopted.

2009.12-2010.1construction bidding and supervision bidding

2009.10-20/kloc-0.1,approval of single building scheme and positioning.

2010.1-February construction drawing design

20 10.3 construction drawing design review

20 10.3 reduction and exemption of application fee for planning and construction.

2010.3-April Construction permit and planning permit shall be handled.

2010.4-65438+February, main structure construction.

4. Agricultural Park Complex Building Project

The project is newly built along Hehuai Road in High-tech Agricultural Park, aiming at strengthening the management of the practice base of agricultural specialty and improving the service and management level of the practice base. At present, the bottleneck of this work is the environmental protection evaluation and approval in the process of planning permit handling. It is planned to complete the planning application for construction, fee reduction and planning permit from 20 10 to1-April; Complete the construction bidding and supervision bidding; And handle the construction permit, and strive to start construction at the end of April.

5. Infrastructure construction of hydropower grid in agricultural park

The water and power grid infrastructure of high-tech agricultural park can no longer meet the basic construction and operation needs of the park, and infrastructure construction is imminent. At present, the agricultural park has taken the lead in designing the water and power grid infrastructure of the whole park, and will be fully constructed after the preliminary work is completed.

6. Graduate apartment complex project

The project has completed the single building design scheme and positioning review and preliminary design expert demonstration organized by Anhui Provincial Department of Education. However, due to the unfinished house demolition work on the construction site, geological prospecting and construction drawing design cannot be carried out. At present, the project is in a state of suspension and waiting for materials. Once the geological survey conditions are met, a series of work such as geological survey, construction drawing design and bidding will be carried out immediately. The demolition of houses in the site is the key to restrict this project.

Problems and shortcomings in the work of verbs (abbreviation of verb)

Looking back on the management of capital construction in the past year, although some achievements have been made, there are still many shortcomings, mainly as follows:

1. Learn.

Lack of opportunities to learn and communicate with the outside world. Technical knowledge can be learned from books, but management knowledge and experience need to be exchanged and learned, especially from brother colleges and other departments and units in the field of off-campus architecture. In the future, we should strengthen exchange and study, as well as the study of new technologies and norms.

2. Project management.

Lack of investment budget management. The construction cost of Jian 'an is well controlled, and the unilateral cost is lower than that of colleges and universities in the province. However, in the early stage of project construction, the content and budget of project investment are not clear. In the future, it is necessary to strengthen the management of investment budget of construction projects.

School infrastructure office

December 22nd, 2009