How to check and accept the shop after renovation?

1. ceiling inspection: check whether there are cracks, inclination, peeling and other problems.

2. wall inspection: check whether there are hollows, cracks and water seepage problems, whether the drip line has been carefully done, whether the kick line is made of cement mortar according to the standard, and if there is an external wall design, whether it has been insulated.

3. ground inspection: check whether there are any problems such as hollowing, cracks and sand, and whether the surface is complete and stable.

Second, the acceptance of the water project

The water project also needs to be inspected at the time of decoration, otherwise it will be very troublesome to find problems during operation. The main inspections are as follows:

1. Whether the floor-crossing pipeline in the wall is equipped with sleeves and whether the whole pipeline system is waterproof.

2. Whether the exposed PVC water pipe is equipped with fire-fighting sleeve. (The fire department will also conduct spot checks on this point)

3. Give out whether the installation of the water pipeline system is firm enough, and whether there is any breakage or looseness.

III. Acceptance of electrical engineering

Electrical engineering is basically a concealed engineering. This step involves some electrical related knowledge, so it is best to arrange a special person to accompany it. The main inspections are as follows:

1. Whether the electrical circuit is set reasonably, whether the number of circuits can meet the daily operation and use, and whether there is leakage and grounding protection.

2. Check whether the line is correct and the path meets the national standard when it is powered on.

3. Whether there is any discrepancy between the indoor electrical safety protection system and the contract constraint.

4. What is the safety and firmness of the distribution box and whether the appearance is damaged?

IV. Acceptance of door and window works

Here, we mainly talk about shop facade works, and mainly check these aspects:

1. Shop facade: whether the facade design and brand specifications are inconsistent with the contract, whether the glass and shop door are scratched, damaged, abnormal, etc., whether the installation is proper, and whether the lock handle is firm.

2. Windows: Whether the airtightness and integrity of window sash and accessories meet the standards, and whether there are drainage holes, anti-falling and anti-collision devices.

V. Acceptance of infiltration works

Generally speaking, the shops located on the 1 th floor should be well protected against water, and the main inspections are as follows:

1. Whether the floors and walls with waterproof requirements are well protected against water in the contract.

2. Do the water storage test at the designated place &; Water splashing test (e.g. restaurant kitchen, toilet, etc.).

VI. Acceptance of the design project

In the last article, we mentioned that many designers fooled customers when making design drafts, so we must

1. According to the orientation and area of the previous store, whether the ventilation and lighting problems meet the design standards.

2. Whether the finished products such as props and counters in the store are made according to the styles and materials bound by the contract.

3. Whether there is an exhaust hole in the reserved position of the air conditioner, water leakage protection, etc.

4. if it is a restaurant, is there a floor gap between the kitchen and the main storefront area?