The previous paragraph of the abandoned soil refers to the excavation of the project needs to be transported out of the residual soil and stone, including engineering residue, engineering slurry, etc.; discarded material refers to a variety of waste masonry, concrete, wood, pipe, asphalt, etc.. Article 4 of the construction waste to implement the principle of minimization, resource utilization, harmlessness and whoever produces who bears the responsibility. Article 5 the city and district people's governments shall strengthen the organizational leadership of the management of construction waste, strict implementation of the administrative licensing law, in accordance with the requirements of the reform of simplification and decentralization, release of management, optimization of services, simplify the approval process, strengthen the management of the incident, and provide quality services.
The municipal people's government shall develop construction waste reserve planning, clear landfill standards and specifications to prevent secondary pollution. Article 6 municipal urban and rural management department in charge of the city's construction waste management, in conjunction with the relevant departments in accordance with the city's urban master plan, land use planning and national economic and social development planning, the preparation of construction waste disposal sites, transfer stations, comprehensive utilization of facilities construction planning.
The municipal environmental health management department is responsible for the specific management of construction waste in the city.
District municipal environmental health management department in the city under the guidance of the municipal environmental health management department, to do a good job in the administrative area of the management of construction waste.
Street offices, township (township) people's government in the district under the guidance of the management of municipal environmental health departments, to do a good job in the jurisdiction of the daily management of construction waste.
Housing construction, environmental protection, public security, land, planning, transportation, housing, gardening, forestry, water and other departments in their respective areas of responsibility to do a good job in the supervision and management of construction waste. Article 7 Any unit or individual on the indiscriminate piling, littering, dumping, throwing construction waste and other acts have the right to report and complain.
Municipal environmental health management departments in the receipt of complaints, reports should be dealt with in a timely manner and will deal with the results back to the complaint, the informant. Chapter II Construction Waste Article 8 The construction unit, the construction unit shall implement engineering management, take measures to reduce the generation of construction waste.
Construction sites should be set up enclosures, cover the dust-prone materials, site implementation of wet work, hardening of the road in and out, cleaning vehicles in and out of the bulk of the material sealed transportation. Article IX unit of construction waste, construction waste should be generated location, time, type, quantity, disposal and other matters to the municipal environmental health management department to declare registration. Article 10 The construction project construction unit shall manage the construction site in accordance with the following provisions:
(1) Classification of collection and stacking of construction waste, prohibit the mixing of domestic garbage into construction waste;
(2) timely backfill, clearing construction waste, can not be backfilled in a timely manner or clearing, should be taken to prevent dust, seepage, landslides, and other measures;
(3) the engineering (C) the implementation of slurry slurry water separation, standardized discharge, conditions should be drying treatment;
(D) hardened construction site entrance and exit roads, equipped with vehicle washing facilities to ensure that the transport vehicles out of the net car. Article XI of the demolition project construction unit shall be in accordance with the following provisions of the management of the demolition site:
(a) take spray dust removal measures and set up enclosures, dust control facilities, the implementation of isolated operations, construction waste removal within twenty-four hours after the completion of the construction to achieve synchronization of dismantling and transportation;
(b) can be recycled for recycling of construction waste to implement the classification of recycling;
(iii) Arranging for full-time staff to carry out on-site supervision. Article XII of the road network, landscaping and greening construction units should be shielded from segregation operations, and timely removal of construction waste. For special circumstances can not be timely removal, dust control measures should be taken. Article 13 The construction waste generated by decorating the house shall be classified and bagged, and piled up to the designated location, by the construction waste transportation unit for removal. Article 14 encourages the industrialized production of buildings, and gradually implement the standardized design and factory production of buildings and structures fittings, as well as promote the assembly of buildings, and increase the proportion of new homes fully decorated to reduce the generation of construction waste.
Encourage the use of reusable materials to erect temporary construction site buildings, temporary enclosures. Chapter III Construction Waste Transportation Article 15 The transportation of construction waste to implement a permit system.
Transportation of construction waste enterprises shall meet the following conditions:
(a) according to the "Chinese People's Republic of China *** and the State Road Transportation Regulations" of the road transport business license;
(b) a certain number of construction waste and meet the city's requirements for the transport of construction waste vehicles;
(c) have a fixed office, parking lot, with the corresponding
(4) construction waste vehicle operation, safety, quality, maintenance and other management systems;
(5) other conditions prescribed by laws and regulations.
Enterprises transporting construction waste shall apply to the municipal environmental health management department. Municipal environmental health management department shall be reviewed within twenty days from the date of acceptance of the application. If the conditions are met, approval shall be granted; if the conditions are not met, the reasons shall be advised in writing.
No unit or individual shall not be forged, altered, trading in the transportation of construction waste permit procedures.