Current location - Recipe Complete Network - Catering industry - China Construction Second Engineering Bureau General Contracting Company's projects
China Construction Second Engineering Bureau General Contracting Company's projects

1, the third hospital of Hebei Medical University orthopedic ward building

Project overview: the project is located in Shijiazhuang City, Ziqiang Road, the third hospital of Hebei Medical University, northwest of the hospital, the east side of the hospital and the original fourteen-storey comprehensive ward building adjacent to the construction. Total construction area of 32962 square meters, the main body of the project for the frame shear structure, underground 1 layer, 14 floors above ground, a total height of 57.65 meters. The actual start date of the project is April 19, 2006, the contract duration of 913 days, the contract cost of 55,566,500 yuan. The main materials of this project are all supplied by Party A. By the end of 2008, the project has been completed and delivered to use

2, Beijing Jinxiuudadi Green and Safe Food Specialized Market

The project is located in Beijing, with a floor area of 140,035 square meters and a contract value of RMB 212.17 million yuan. It is a steel frame and seismic wall structure, and the project was started in 2004 and completed on April 20, 2006, and the construction work was completed on April 20, 2006.

3. RUNSHI CENTER

This project is located in the vicinity of the third diplomatic embassy area of Liangmahe, Chaoyang District, Beijing, with Tianze Road to the west, separated from the U.S. Embassy by a road, Anjialou South Road to the south, Beijing City Plaza to the east, and Anjiacun Status Lake to the north. The project is invested and constructed by Zhonglian Runshi (Beijing) Investment Co., Ltd, designed by Beijing Municipal Architectural Design and Research Institute, and constructed by Second Bureau General Contracting Company.

The project has a total construction area of 98,698 square meters, of which: 65,848 square meters above ground; 32,850 square meters below ground, frame shear-wall structure, eave height of 77.05 m. Above 0.000 m, the two main buildings and the podium are respectively divided into three relatively independent structural units by anti-seismic joints. The number of floors above ground is 14 to 17, the first floor of the north and south buildings are used as commercial rooms except for setting the entrance and exit halls of each building block; the second and third floors of the south building are used as commercial rooms; the second and third floors of the north building are used as catering rooms; the first floor of the podium is used as a display hall; the second and third floors are hollowed out into a **** enjoyment space, and the roof is a light-reflecting glass roof; the standard floor is used as an office room. The number of underground floors is 4, the first floor for the supermarket, staff restaurant and other service rooms and weak power center, high voltage connection room, diesel generator room and air-conditioning plant room; the second floor for the parking garage, power distribution room and garbage collection room, the layer is also used as a logistics and transportation layer, goods and garbage in this centralized and diversion; the third floor of the ground floor for the parking garage; the fourth floor of the ground floor during the week for the parking garage, the wartime for the six-level material warehouse, other functions set up are Chiller room, chiller pump room, fire fighting pool and pump room, water pump room, living water pump room, heat station, ventilator room and so on. The total cost of the project is about $300 million. The project started on September 4, 2009, and by the end of 2009, the foundation pit earthwork was completed to -16.8m; spray concrete support and soil nails were all completed; slope protection piles were completed; water-stopping curtain piles were completed; and pre-stressing anchors were completed in the fourth course.

4, Taiyuan Wanda Plaza

Taiyuan Wanda Plaza is located in the south of Taiyuan North Street, west of Jiefang Road, north of Dry West Gate Road, east of Longtan Park on Xinjianbei Road. It is invested and constructed by Taiyuan Wanda Plaza Co., Ltd, designed by Taiyuan Architectural Design and Research Institute, and constructed by Second Bureau General Contracting Company.

The project is composed of commercial and residential buildings and a bar street, which is a comprehensive building integrating residential and commercial, with a total cost of about 3.94 billion yuan.

Of which the contract duration for Area B1: May 1, 2010 - September 16, 2011, ****504 calendar days. Contract scope: structure, interior preliminary decoration, electrical, water supply and drainage, heating and ventilation works. Building area: 5#: 16481.71 square meters; 7#: 16481.71 square meters; 6#; 16538.01 square meters; 8#: 16519.98 square meters; underground garage: 19447.9 square meters. 32 floors above ground, 3 underground (including mezzanine), total building height: 108.80 meters. Structure form: the main building is shear wall structure.

The bar street, in the base surrounded by the city road, is a two to five-story multi-purpose commercial building built along the road in a staggered height, each building is relatively independent, and through the organic combination to form a pedestrian street, including restaurants and recreational facilities, etc. The structure is frame structure, and the total building height is 1,940.80 meters. The structure form is frame structure, the total construction area is 57,319 square meters, including 37,134 square meters above ground and 20,185 square meters underground.

The project started on June 8, 2009, and by the end of 2009, the bar street: the ground floor of 3 floors, part of the 4 floors are completed; roofing works A-G area is completed; insulation works A-F area is completed; mechanical and electrical pre-burial is completed; the external network is completed on the north, south and west sides. 11# building in A2 area: the first floor of the main structure construction, the foundation construction of the 6# building.

5, Zhengzhou City Library New Hall (Citizen's Cultural Center)

The project is located in Zhengzhou City, Zhengdong New District, north of Kewen Street, south of Kewen Street, Xingrong Road to the north, Minsheng Road to the west. The construction agency is the First Construction Engineering Group Co., Ltd. of Henan Province; the design agency is Beijing Architectural Design and Research Institute; the supervising agency is Intech Engineering Consultant (Shanghai) Co.

The cost of the project is about 460 million yuan, with a total construction area of 72,095 m2, of which 19,053 m2 is underground and 53,042 m2 is above ground, and the total height of the building is 30.6 m. Number of floors: five floors above ground of the main building, two floors of the podium; one floor underground, and a mezzanine floor for local equipment. Structural form: reinforced concrete frame shear and frame; local steel structure, foundation adopts post-drilling grout pile plus water-resistant slab foundation. Contract scope of the project: civil engineering and supply and drainage works; ventilation and air-conditioning works; electrical works.

The project started on July 21, 2009, and by the end of 2009, the construction of the main structure of the first underground floor was completed.

6, PLA No.254 Hospital Ward Building

Project Location: No.60, Huangwei Road, Hebei District, Tianjin City

Construction Unit: Hospital Affairs Department of PLA No.254 Hospital

Design Unit: Architectural Design and Research Institute of General Logistics Department of the PLA

Supervision: Tianjin International Engineering Construction Supervision Company

Quality Supervision: Quality Supervision of PLA, China's People's Liberation Army. Quality Supervision: Tianjin Branch of the General Quality Supervision Station of the Chinese People's Liberation Army

Construction Unit: Second Bureau General Contracting Company

Contract Scope of Contract: Civil, Decoration, Water Supply and Drainage, Lighting, etc.

Contract Duration: Feb. 10, 2009 ~ Feb. 14, 2011, ****730 calendar days.

Contract quality standard: qualified

Project quality target: military region quality engineering.

Construction area: 78616.51m2

This project is a garage underground, and above ground consists of office, medical administration, surgery and ward, above ground floor area: 62659.34 m, underground floor area 15957.17 m, 20 floors above ground, 2 floors underground. Building height: 5.5m on the first underground floor, 3.8m on the second underground floor, 4.8m on the 1st-4th floors above the ground, 3.6m on the 5th floor, and 3.9m on the 6th floor and above. Building height building total height of 83.75 meters.

The project started in November 2008, by the end of 2009, the main structure: seven sections to 11 floors, six sections to 9 floors, four sections to 11 floors.

7, high-speed - Orchid Garden District

High-speed - Orchid Garden District for the Henan Province High-speed Real Estate Development Co., Ltd. development of the group of residential communities, covers an area of about 105,746.8 square meters, construction area of about 466,000 square meters, the district east-west length of about 455 m, north-south width of about 251 m. The entire district is divided into three construction bids, I units to undertake the construction of high speed - the Orchid Garden Ⅲ section of the project, including 6 #, 7 #, 9 #, 10 #, 14 #, 15 #, 16 # building seven high-rise main building, 6 #, 7 # underground garage and 19 # building underground clubhouse and so on 10 individual projects, the main building and garage foundation form for high-strength pre-stressed piles, the building structural form of the shear wall structure, frame - shear wall structure, no-beam pre-stressed structure of three kinds of forms, seismic The seismic intensity is 7 degrees, and the overall community design adopts the "Art Deco" style.

Contract duration 540 calendar days, total cost about 230 million yuan

Construction unit: Henan Expressway Real Estate Development Co.

Supervision unit: Beijing Construction Engineering Jingjing Dafang Engineering Construction Supervision Company

Design unit: Shanghai Lianchuang Architectural Design Co.

Construction unit: the second bureau of the general contracting company

The project started in August 2008, and was completed in June 2009, with a total of 2,000 square meters. The project started in August 2008, and by the end of 2009, the main structure of Building 6#, 7#, 14~16#, 9#, 10# was completed, and the internal and external decoration was constructed; the underground structure of Building 19 was constructed; the main structure of Garage 6# and 7# was completed, and the construction of fire fighting, ventilation and lighting was carried out.

8, Tianjin Port International Cruise Terminal Passenger Terminal Building

Project Name: Tianjin International Cruise Terminal Project (Passenger Terminal Building Project)

Project Location: South of Tianjin Dongjiang Port Area

Construction Unit: Tianjin Port (Group) Co.

Designing Unit: Zhongjian (Beijing) International Design Consultant Co.

Supervising Unit: Tianjin Port Engineering Co. >Supervision unit: Tianjin Port Engineering Supervision and Consulting Co.

Contract scope: civil construction, decoration, installation of several points within the scope of the drawings and lists

Coverage: about 59,000 square meters, building area: 21,388 square meters

Contract amount: 594,070,000 yuan

Construction period: Started on March 15, 2009 Completion on May 31, 2010

Contract quality target: qualified, striving for Luban Award

Auxiliary quality target: ensure to get Tianjin "Structural Haihe Cup"; ensure to get Tianjin "Haihe Cup Gold Medal"

To ensure to get Tianjin "Haihe Cup Gold Medal"

Contract value: 594.07 million Yuan p>Ensure to get the "China Construction Cup" of China State Construction Corporation (CSC)

Civilized construction target: Ensure to get the "Tianjin Municipal Civilized Construction Site"; Ensure to get the CI Model Site of CSC.

Scientific and technological innovation target: to ensure the title of "Science and Technology Promotion Demonstration Project" of China State Construction Corporation; to ensure that 1~2 QC achievements are released at provincial and ministerial levels.

The project started on March 15, 2009, and by the end of 2009, the exterior decorative glass was installed, 80% of the roof grc panels were completed, and the keel of the second floor partition wall was installed indoors.

9, production plant and ancillary facilities project

Project name : Beijing Jishuitan Hospital Huilongguan hospital

Project address : Beijing Changping District, Huilongguan Town

Construction unit : Beijing Jishuitan Hospital

Survey unit : Beijing Survey and Design Research Institute

Representative unit : Beijing Tianhong Group Company Jishuitan Hospital Huilongguan Hospital Project Management Branch

Design unit :Beijing Architectural Design and Research Institute

Supervision unit :Beijing Ceres International Engineering Consulting Co.

Construction unit :The Second Bureau of General Contracting Company

Gross floor area Gross floor area is 68,520 square meters, with the underground area of 22,571 square meters, and the above ground area of 45,949 square meters. 45949 square meters

Building height: 46.99m for the main building, 19.29m for the podium

Storey number: 11F above ground, 3F below ground for the main building, 4F above ground, 2F below ground, 3F locally for the podium

Contractual period: The construction is scheduled to start on August 9, 2007; the completion date is scheduled to be June 26, 2009; and the scheduled period is scheduled to be 688 days. 688 days.

Contract quality objective: Ensure the Great Wall Cup of Beijing Structure and strive for Luban Award.

The project started on May 15, 2007, and by the end of 2009, 85% of the wall plastering of the second basement was completed, and the glass curtain wall of 10-15 axes was completed.

10, Beijing Jishuitan Hospital Huilongguan Hospital District Project

Project Name : Beijing Jishuitan Hospital Huilongguan Hospital District

Project Address : Huilongguan Town, Changping District, Beijing

Construction Unit : Beijing Jishuitan Hospital

Survey Unit : Beijing Survey and Design Institute

Representative Unit : Beijing Tianhong Group Corporation Jishuitan Hospital Huilongguan Hospital District Project Management Branch

Design unit :Beijing Architectural Design and Research Institute

Supervision unit :Beijing Ceres International Engineering Consulting Co. Building area 45949 square meters

Building height: 46.99m for the main building, 19.29m for the podium

Storey number: 11F above ground, 3F underground for the main building, 4F above ground, 2F underground, partially 3F for the podium

Contract period: The construction period is planned to start on August 9, 2007; the completion date is planned to June 26, 2009; the construction period is planned to be 688 days. The construction period is 688 days.

Contract quality target: Ensure the Great Wall Cup of Beijing Structure and strive for Luban Prize.

The project started on May 15, 2007, and by the end of 2009, 85% of the wall plastering of the second basement was completed, and the glass curtain wall of 10-15 axes was completed.

11, Henan Electric Power Company comprehensive scheduling building project

Henan Electric Power Company comprehensive scheduling building is located in Zhengzhou City, South Songshan Road, South Plaza Road, three underground, 32 floors above ground. The main floor height of 4.5m, 5m, building area of 64,810 square meters. The elevation of the basement raft surface is -13.800m, the roof elevation is 174.900m, the steel structure top elevation is 206.000m, the tower antenna elevation is 235.300m.This project adopts the following four floors are reinforced concrete cylinder -- section steel concrete frame structure, five floors above are reinforced concrete cylinder --The project adopts the structure of reinforced concrete cylinder-type steel concrete frame below the fourth floor, reinforced concrete cylinder above the fifth floor-type steel concrete columns, H-type steel beams, and pressed steel plate cast-in-place concrete floor slab. The overall shape of the building is chic and novel, and the decoration is of high grade. After completion, it will become a landmark building in Zhengzhou.

Project started in December 2008, to the end of 2009, the main structure to the 6-storey construction

12, Zhengzhou City Railway Station West Exit Project Ⅱ section

Project name: Zhengzhou City Railway Station West Exit Plaza and Underground Parking Lot Project Ⅱ section

Construction unit: Zhengzhou City, "one stop, one bridge" project construction project department A way" project construction project department

Construction location: Zhengzhou City, the new railway station, west of the west station, east of Jingguang Road, south of Zhongyuan Road, north of Longhai Road, west of the site of Taihe Road.

Design unit: Zhengzhou Municipal Engineering Design and Research Institute

Zhengzhou Architectural Design Institute

Survey unit: Zhengzhou Geological Engineering Survey Institute of the Ministry of Chemical Industry

Supervision unit: Henan Hongye Construction Engineering Management Co.

Construction unit: Second Bureau of General Contracting Company

The construction period of this project is 180 days, and the structural form is Frame structure, the number of building floors for the underground layer, the height of 5 meters, the use of the function of the station for the distribution plaza, for the single-built underground garage, the project to ○ 26 axis south of 3800mm at the back of the watering zone for the Ⅱ standard section (including the back of the watering zone). The east-west width is about 128 meters, locally about 171 meters, and the north-south length is about 207 meters. The total construction area of the project is about 30,000 square meters, and the contract value is 108.18 million yuan.

The foundation of this project adopts CFG pile composite foundation, the seismic grade of the frame shear wall structure is four, the structural form of the top slab is partly cast-in-place concrete hollow floor slab, the beam part of this project all adopts upturned concrete beams, which are poured at one time, and some of the large-span beams are pre-stressed girder-slab structure.

The project started on August 1, 2008, by the end of 2009, the sparse forest square stone paving is complete; square stone paving is complete 90%; indoor flooring is complete; 1 #, 2 # east ramp top plate is complete; backfill is complete 95% of the road is complete 80%; sunken plaza fence construction is 80%; fire pool top plate is complete.

13, Tianjin Hi-tech Zone National Software and Service Outsourcing Industry Base Core Area B2 and B3 Lot Project

Project Overview: The project is located in the Tianjin New Technology Industrial Park Hitech Huake Nine Road, the owner of Tianjin Hitech Science and Technology Development Company Limited, by the Tianjin Municipal Architectural Design Institute design.

The contract value of the project is 228.23 million RMB, which consists of Lot B2 (Building No.1, No.2 and No.3) and Lot B3 (Building No.1 and No.2), all of which are industrial buildings. Among them, the building area of Lot B2 is 61010 square meters, with one underground floor and five floors above ground, reinforced concrete frame structure, and the total building height is 23m; the building area of Lot B3 is 41030 square meters, with one underground floor and five floors above ground, reinforced concrete frame structure.

The contractual construction period of the project is from February 18, 2008 to September 20, 2008.

The quality target of the project is to strive for the Tianjin Haihe Cup and to reach the Tianjin Safe and Civilized Site.

The project started on February 18, 2008, and by the end of 2009, the project will be fully completed.

14, Hitech Innovation Base Project B1, B2, B3, C area project

Project overview: the project is located in Tianjin Hitech Development Five Roads, the construction unit for the Hitech Fangcheng Investment Co., Ltd, the design unit for the Tianjin Architectural Design Institute, supervised by Tianjin Jianhua Construction Engineering Supervision Company, the Bureau of General Contractor construction.

The contract value of the project is 83.46 million yuan, with a total construction area of 61088 square meters, consisting of office area and plant area, Building B1, B2 and B3 are class C plants, structure type: foundation is bearing platform foundation, the main body is reinforced concrete frame structure, of which: Building B1 has five floors on the ground, with a construction area of 5045.62 square meters, and a total height of the building of 26.15m; Building B2 has eight floors on the ground and six floors locally, with a construction area of 5045.62 square meters, and a total height of 26.15m; Building B2 has eight floors on the ground, and six floors locally. Eight floors, local six floors, building area 18900.04 square meters, total building height 36.65m; B3 building six floors above ground, building area 4257.83 square meters, total building height 28.5m. C area for scientific research and office building, including A, B, C building, total building area 32883.98 square meters, building level: one underground, A building eight floors above ground, B building four floors above ground, C building twelve floors above ground, total building height 51.2m. The total height of the building is 51.2m, structure type: foundation is bearing platform foundation, main body is reinforced concrete frame structure.

The project started in October 2007, and by the end of 2009, the project was fully completed.

15, Peking University Third Hospital Reconstruction and Expansion Project, Sports Medicine Building, Outpatient and Emergency Medical and Technical Building

Project overview: the project is located in the hospital grounds of the Third Hospital of Peking University, the construction unit is the Third Hospital of Peking University, and the design unit is the Zhongyuan International Engineering Design Institute. The total construction area is 77078m and the contract value is 316.5 million RMB.

Quality target: Qualified; Beijing Structure and Architecture Great Wall Cup Gold Medal

Civilized construction target: Beijing "Safe and Civilized Site"

Sports Medicine Building Contracting Scope: Architecture, Decoration, Strong Electricity, Weak Electricity, Fire Alarm System, Water Supply and Drainage, Fire Hydrant System, Sprinkler System, Heating System, Ventilation and Air Conditioning.

Total building height: 64.30m; number of floors (above/underground): 15/2; structure type: foundation is beam-slab raft, main body is frame-shear-wall structure.

Duration: Started on June 20, 2007 and completed on June 3, 2009, with a construction period of 715 calendar days;

Contracting scope of the outpatient and emergency medical building: all the construction works, decoration works, electrical works, water supply and drainage works, fire-fighting works, ventilation and air-conditioning works, and medical gas pipeline works as shown in the bidding drawings.

Total building height: 37.40m; number of floors (aboveground/underground): 8/2; structure type: foundation is beam-slab raft, and the main body is frame-shear wall structure.

Requirements for the construction period:. Started on June 20, 2007 and completed on November 15, 2008, construction period: 515 days.

The project started on August 18, 2007, and by the end of June 2008, the structure of the sports medicine building and the outpatient and emergency medical building was topped out. During the Olympic Games, work was suspended. 2009 end, sports medicine building exterior wall tiles finished 30%, indoor flooring finished, bathroom leveling finished 70%, waterproofing 20%. Outpatient and emergency medical building exterior wall insulation is complete, stone curtain wall is complete 30%, glass curtain wall and aluminum curtain wall is complete 90%, indoor flooring play 90%, hot and cold water is complete 90%.

16, Industrial and Commercial Bank of China Limited Business Operation Center

Project Overview:

Project Location: No.55 Fuxingmennei Street, Xicheng District, Beijing, China

Construction Unit: Industrial and Commercial Bank of China Limited Business Operation Center

Design Unit: Bei's Architecture Firm, Beijing Municipal Institute of Architectural Design

Project Scale: Contract Value: RMB628.01 million, Total Building Height: 45.00m, Total Building Area: 61325m2, 11 floors above ground (including one mezzanine floor), with a building area of 46,000m2, and 3 floors below ground, with a building area of 15,325m2.

Structural Form: Reinforced Concrete Frame Shear Wall System below ground, and steel support above ground transmitted to the foundation by the underground shear wall. The steel support above ground is transmitted to the foundation by the underground shear wall. The first floor is a transition floor, using section steel concrete columns. The above ground structure is steel frame structure with partial support or center support, the beam adopts solid web H-beam, and some horizontal members adopt small truss. The air bridge adopts one-story through-height steel truss.

The project started on July 16, 2007, and by the end of June 2008, all the basement wall masonry was completed, and all the steel structure installation was completed. At the end of 2009, the bathroom wall and floor stone finished; the west side of the 7-9th floor, the east side of the 2-6th floor of the core cylinder wall dry hanging stone finished; air conditioning room acoustic panel finish finished, glass partition installation finished; south elevation overhanging wings of the glass curtain wall, the mezzanine and the second floor of the glass railing panel installation; air conditioning, electrical insulation, garage hot air curtains, distribution boxes, the first floor of the threading and lighting socket cable laying.

17, Beijing New Children's Palace

Project Overview: Beijing New Children's Palace is located in Chongwen District, Beijing Longtan Lake Baiguoyuan 3, the construction unit for the Beijing Student Activity Management Center, the design unit for the Beijing Municipal Architectural Design and Research Institute. Contract period September 28, 2007 to May 7, 2009, ***588 calendar days. Total construction area 40374.39m2, Contract quality standard: qualified, ensure Beijing "Structure Great Wall Cup" Gold Award. Project Quality Target: Beijing "Great Wall Cup of Construction" and Luban Prize.

The main functions of the project are art activity area, sports activity area, green science and technology center, student activity center, theater, underground garage and ancillary facilities.

Construction features: the whole building consists of five units and the central hall, two units in the east are the art activity area, including rehearsal hall (theater) and various rehearsal halls; three units in the west are the sports, comprehensive activity area, green science and technology center, and student activity area, and the first-floor podium is the central hall, which is connected to the five units. This centralized plus decentralized layout is conducive to all parts of the classroom have good direct lighting and natural ventilation, in the case of no or less use of air-conditioning equipment to achieve the requirements of health and comfort.

The design adopts the petal-like layout with staggered heights and the shape of branch-like curves, which makes the fa?ade form full of a sense of hierarchy, dynamism and growth. The above ground construction area is 23600.82m, the underground construction area is 16773.5m, and the human defense construction area is 1555m. Number of floors: 5 floors above ground (including 1 floor of podium), 2 floors underground. Eave height is up to 31.7 meters.

Structural form: the foundation is raft plate foundation, the main body is shaped shear wall structure, the roof is reinforced concrete and local steel structure.

The project started on December 28, 2007, and the main structure was fully completed in June 2009, entering the decoration stage, but the work began to stop due to the financial problems of the Party.