The earth is our home, disaster prevention and mitigation depends on everyone. In order to minimize the losses that may be caused by disasters, we often pre-prepared emergency plans. So, what should an emergency plan start from? Please read by me for you my hospital sudden power outage emergency work plan template, welcome to read, I hope you will like it!
Hospital emergency program template for sudden power outages 1A planned water outage emergency plan
1) municipal pipe network planned water outage
1. When receiving the notice of water outage, immediately inform the owners in writing, the users of water outage information, inform the contents include: implementation of the unit of the water outage, out of water, the reason, time and scope and restore the water supply time, etc.. The content of the notice includes: the unit that stops water, the reason for stopping water, the time and scope of stopping water and the time to resume water supply;
2. To remind the owners and users to reserve water in advance;
3. If the stoppage of water is too long, contact the water company to send the water.
2) Failure to stop water in the district
1. Upon receipt of the information on the water stoppage, immediately notify the *** use of parts, facilities and equipment maintenance personnel to the scene to view, and at the same time contact with the water company to confirm whether it is the cause of the municipal network;
2. After the cause of the stoppage of the water to identify, and immediately organize the personnel to repair;
3. If the repair time is long, should immediately post a notice in the area in a conspicuous place to inform the owners and users of the relevant area, the content of the notice, including: the reason for the suspension of water, the scope of the expected repair time, etc.;
4. If the suspension of water is too long, contact the water company to send water;
5. Afterwards, the reasons for the suspension of water identified, and inform the relevant person in charge in written form.
Second, the failure of the water emergency plan
1. Received the information on the suspension of water, immediately notify the *** with parts, facilities and equipment maintenance personnel to the scene to view, while contacting the water company to confirm whether the cause of municipal pipe network;
2. The cause of the suspension of water ascertained, and then immediately organize the personnel to repair;
4. If the suspension of water is too long, contact the water company to send water;
5. Afterwards, the reasons for the suspension of water to identify the relevant written notice to the relevant person in charge of the
Third, the emergency plan for planned power outages
1) municipal pipeline network planned power outages
1. Upon receipt of the power outage notice issued by the power supply department, three days before the power outage in a conspicuous place to post notices informing the owners of the area related to the power outage, the use of the content of the notice, including: implementation of the unit of the power outage, the reason for the power outage, the time and the range of The content of the notice includes: the unit implementing the power outage, the reason, time and scope of the power outage, and the time of restoring power supply. And remind the owners and users to turn off all electrical appliances during the blackout;
2.*** use parts, facilities and equipment maintenance personnel to prepare for unexpected troubleshooting and cooperate with the maintenance of equipment, and turn off the power supply to the relevant facilities before the blackout;
3. Stop the elevator operation in advance before the blackout and remind the owners and users to refrain from using the elevator for the time being;
4. Promptly start the motor power supply;
5. Strengthen the public **** order maintenance in the area during the blackout, to prevent lawless elements to fish in troubled waters;
6. After the power is restored, check the building area zoning the normal operation of the equipment.
Fourth, fault blackout emergency plan
1. Received blackout information, immediately notify the *** with parts, facilities and equipment maintenance personnel to the scene to check, while contacting the power supply company to confirm whether it is a municipal network of the reason;
2. Control center in a timely manner to see whether the elevator is trapped in the elevator, such as in accordance with the elevator trapped in the emergency plan disposal;
4. If there is in accordance with the elevator trapped emergency plan disposal;
3. power outage causes identified, immediately organize personnel repair;
4. notify the order of maintenance personnel to strengthen the power outage area of the patrol and the various access to the control of the rear, to see whether the elevator is trapped, whether other accidents;
5. turn off the power switch of the relevant equipment;
6. such as maintenance time is longer, should be immediately posted a notice in the district conspicuously. If the repair time is long, should immediately post a notice in the area in a conspicuous place to inform the owners and users of the relevant area, the contents of the notice include: the reason for the power outage, the scope, the expected repair time, etc.;
7. Power supply is restored to turn on the relevant equipment immediately, and check the public electrical appliances, equipment has been restored to normal operation;
8. After the incident, to identify the reasons for the shutdown of the relevant written notice to the relevant person in charge.
Hospital emergency program template for sudden power failure 2In order to do a good job in the hotel after a sudden power failure emergency rescue and disposal work, to ensure that the hotel in a sudden power failure emergency, effectively organize the relevant departments to carry out emergency rescue, minimize unnecessary losses and consequences, according to the relevant provisions of the higher level, combined with the actual hotel, specially formulated the hotel emergency program for sudden power failure, is now a sudden power failure. After the power outage, the work of all relevant departments is divided as follows.
Security Department work:
1, the hotel once a sudden power outage, by the department of the highest staff in the store immediately organize the post staff to take appropriate emergency measures, and convene all the security guards on duty for the division of labor, assigned security guards on the hotel to control the entry and exit of the intersections, the outgoing goods and personnel to check, strictly check to prevent the outflow of property.
2, quickly send security along the floors to check the elevator, the use of shouting, beat check the elevator whether there are trapped people, such as trapped people, immediately notify the Ministry of Engineering and actively assist in taking rescue measures.
3, send security guards along the floors constantly patrol, especially to strengthen the key parts, key places and areas of the security patrol inspection, mainly check the floor door locks, floor emergency lighting, and floor personnel activities, etc., to prevent the use of blackout waiting for an opportunity to commit crimes and take advantage of the fire.
4, notify the relevant departments to do a good job after the power outage of important facilities and equipment to protect the custody of the work, to prevent people from destroying.
5, make every effort to do a good job after the blackout of all kinds of emergencies emergency and disposal work.
6, actively supervise and assist the Ministry of Engineering to find the cause of the power outage, as soon as possible to restore the power supply.
Housekeeping Department work:
1, the hotel once a sudden power outage, by the department in the store the highest-ranking staff to immediately organize the post staff to take appropriate emergency measures, the floor staff should be on all floors of the room, the office to carry out a careful inspection, to prevent people from lighting candles or littering cigarette triggered fire accidents, and at the same time do a good job of prompting the guests and patient explanation of the work.
2, the power outage time is longer, the waiter to persuade the guests not to panic, try to meet the needs of guests, guests asked to leave the store, to do a good job of guiding, in case of emergency, but also to do a good job of evacuating people, and guide the guests to evacuate from the walking ladder to the outside of the store.
3, the front desk immediately do a good job of saving and backing up the guest history data, and notify the lobby assistant to stick to the post, deal with the relevant complaints and coordinate to solve the related problems arising from the power outage.
4, the baggage handlers should do a good job of guarding the guests' valuables, and try to control the outsiders to enter the hotel after the power outage.
5, the service center to do a good job in the transmission of information and a variety of consulting, make every effort to do a good job after the power outage of guest services.
Catering Department work:
1, the hotel in the event of an unexpected power outage, by the department in the store of the highest-ranking staff to immediately organize the posts of employees to take appropriate emergency measures, catering staff to the various business premises and consumption of the booths to carry out a careful inspection to prevent people from lighting candles or throwing cigarettes triggered by a fire accident, and do a good job of prompting the guests and patient explanation work.
2, when the power outage time is longer, the waiter should persuade the guests not to panic, try to meet the needs of guests, guests asked to leave the store, to do a good job of guidance, emergency, but also to do a good job of evacuating people, and guide the guests to evacuate from the walking ladder to the outside of the store.
3, consumption of more guests, the waiter should pay more attention to the accompanying staff, pay attention to and observe the consumption of guests and their surrounding movements, to do a good job of prompting and care of the guests' belongings, as well as the guests to deposit the items properly stored.
4, the kitchen staff should be on the stove, pipeline, high-power electrical appliances and other important equipment to carry out a careful inspection, and turn off the power supply, electrical appliances, oil valves and a variety of switches, to take appropriate precautions.
Engineering Department work:
1, the hotel once a sudden power outage, by the department in the store's highest-ranking staff to immediately organize the post staff to take appropriate emergency measures, first of all, in the first time, to figure out the cause of the power outage.
2, if the power supply bureau system blackout, immediately call all the staff on duty, a group of two people holding lamps were run to the lobby, distribution room, exchange stations, restaurants and floors, to see the emergency lighting facilities, and will be the corresponding electrical equipment switch to the closed position.
3, the elevator rescue personnel quickly open the elevator car door, call loudly, confirm whether the elevator is trapped in the guests and elevator location, if not in the flat position, then quickly rushed to the 14/F elevator machine room, open the door and immediately disconnect the power switch, remove the traction machine brake guard, with special tools to gently downward pressure on the mechanical brake, to be the elevator car slowly upward sliding to the flat position, the elevator car slowly upward sliding to the flat position. With the elevator special mechanical maintenance key to open the car hall door, to help trapped guests quickly evacuate the elevator.
4, the exchange station lithium bromide unit, plate exchanger and volumetric exchanger once the power outage, immediately turn off the steam to avoid damage to the equipment.
5, if the distribution room because of water, fire and other reasons can not be normal power supply, emergency situations can be switched to the fire standby power status to ensure that the life pumps, fire pumps, sprinkler pumps, elevators and monitoring room power supply to ensure that the important equipment equipment operation.
6, if the distribution room branch line electrical component failure, you can immediately disconnect the branch circuit, and hang a warning sign to protect the other circuits of normal power supply, and then try to solve.
7, during the blackout period, the use of open flame operation is strictly prohibited, flammable items should be set around the isolation zone, and strengthen the patrol.
8, during the power outage, the Ministry of Engineering employees on duty to listen to the manager of the unified command, timely reporting of the latest developments in their respective areas of responsibility.
The Ministry of Finance work:
Once the hotel unexpected power outage, by the department in the store the highest-ranking staff to immediately organize the posts of employees to take appropriate emergency measures, the Ministry of Finance office to do a good job of cash, cheques and seals of the storage, the front desk as well as the cash registers should be immediately do a good job in the management of cash and the guest history of the information preservation and back-up work.
Marketing, Human Resources, Purchasing, General Manager's Office:
Once the hotel has a sudden power outage, the highest-ranking staff in the store by the department immediately organize the post staff to take appropriate emergency measures, the office staff to adhere to their posts and do a good job in a variety of agreements, personnel files, and other important information on the management and storage of the work.
Special emphasis:
All departments should coordinate with each other, cooperate with each other, work closely together, and complete their work according to the contents of the plan, and strive to control and reduce the losses caused by the power outage to a minimum.
Hospital sudden power outage emergency work program template article 3First, the development of the purpose
In order to ensure the safety of patients' lives and reduce the loss of property, to ensure that the hospital electricity unimpeded, to promote the institutionalization of the emergency response to accidents and standardization of the work of the system, the rapid and orderly organization and restoration of power supply, based on the relevant laws and regulations of the State, combined with the actual situation of our hospital, the The development of this plan.
Second, the principle of emergency
The power outage accident handling work to implement the "prevention first, always be prepared" policy, follow the "unified leadership, improve the mechanism, clear responsibility, strengthen cooperation, rapid response, measures decisive The principle of the "unity of leadership, improve the mechanism, clear responsibility, strengthen cooperation, rapid response, measures decisive.
Third, the organization
The hospital set up a power outage emergency leading group, under the emergency repair team.
(a) blackout emergency leading group
Leader: Xia Qin
Deputy leader: Chen Jiaquan
Members: Zhao Xi, Mei Dengping, Lin Yong
Duties:
1, do a good job of the daily safety of the power supply work, the implementation of the responsibility system of production safety, to prevent blackout accidents.
2, the occurrence of blackout accidents, do a good job in a timely manner in the emergency response to power outages, as soon as possible to restore power supply.
3, according to the severity of the blackout accident, the decision to start and terminate the emergency plan.
4, timely report the accident to the superior and announced to the whole hospital.
5, if necessary, request external support.
6, the leader of the leading group is the first person responsible for the fulfillment of the provisions of this plan. Members of the unit should be under the unified command of the leading group, each in its own way, each responsible for its own responsibility, full cooperation, and do a good job in the blackout accident when the social integration of emergency work.
(B) emergency repair team
Leader: Chen Jiaquan
Members: Lin Yong, Zhao Xi, Mei Dengping
Responsibilities: in the event of an accident, the organization of personnel to carry out rescue operations; to the command team to report the accident, if necessary, the power supply department issued a request for assistance, and then summed up the lessons learned from emergency rescue work.
Fourth, emergency procedures
(a) logistics department electrician class emergency procedures
1, planned blackout emergency procedures
(1) electrician in the power supply department to notify the power outage of the phone or other forms of blackout notice, you must ask the time of the power outage, stop how long and the reason for the outage. Do a good job of recording, such as not in the shift, should be clear in the handover of the shift.
(2) notify the head of the emergency leadership team (night notification of the general duty officer), explaining the reasons for the power outage, the specific time of the power outage, how long the power outage, and do a good job of the preparation of the second backup power supply.
(3) If during normal working hours, time permitting, the hospital office should be issued in writing by the hospital to the whole hospital notice.
(4) If time is of the essence, the head of the emergency leadership team should be notified immediately upon receipt of the notification from the power supply department (night notification of the general duty officer), explaining the situation, and send a notification to the departments, and the important departments should talk to the department head and head nurse to clarify the time of the power outage and the power outage and the power outage plan.
(5) 30 minutes before the power outage to the distribution room, do a good job of switching to the second backup power supply pre-check. When the power outage to 10 minutes to ensure the normal start and delivery of the backup second power supply.
(6) When the external power grid power outage, start the generator power to ensure full coverage of power supply throughout the hospital.
(7) Make a good record of the operation of the backup power generation and the record after the restoration of utility power supply.
2, temporary power outage emergency procedures
(1) when there is a temporary power outage, you should immediately ask the power supply department by phone, ask the reason for the power outage and the duration of the power outage.
(2) Notify the head of the emergency team or the general duty to explain the situation.
(3) If the blackout time is short (within 5 minutes), you should wait for the utility to send high and low voltage power.
(4) If the blackout time is longer (more than 5 minutes), you should start the standby generator as soon as possible to ensure the power supply of the whole hospital.
(5) Make a good record of the operation of self-powered generation.
(6) when the hospital internal reasons for power outages, to identify the cause of the power outage, whether it is a high-voltage circuit or a low-voltage circuit. If the high-voltage circuit failure, should promptly contact the power supply department repair class, as soon as possible to restore, to ensure that electricity; if the hospital low voltage circuit failure, should quickly identify the cause, in accordance with the operating regulations to restore the circuit.
V. Safeguards
(a) electricians should do a good job of generator maintenance on a daily basis to ensure that the generator is always in use.
(ii) electricians usually master the knowledge of power supply and operating norms, pay attention to operational safety.
(C) clinical departments routinely equipped with emergency lights, torches and other lighting, regular inspection, to maintain a perfect state.
(D) logistics department to organize emergency power outage drills, 1-2 times a year, through drills, so that everyone is familiar with the emergency procedures for emergency response to sudden power outages, to ensure patient safety.
Hospital sudden power outage emergency work program template chapter 4
A sudden water emergency treatment
1 duty engineering staff received a notice of water outage from the owners or merchants, must immediately rushed to the site of the water outage, a detailed understanding of the scope of the water outage and related water outage.
2 on-duty engineering staff immediately to check the valve at the main gate of the suspended lot, if the valve is closed, timely understanding of the reasons for valve closure, to confirm that can be opened, open the valve to restore water supply.
3 If the total valve of the lot is not closed, contact the water company in time to understand the specific reasons for the water outage.
4 If the water supply is caused by the domestic pumping equipment, the following treatment:
(1) If the valve is closed to cause water supply, immediately understand the reasons for the valve closure, and take effective measures to restore water supply in a timely manner.
(2) If the water pump shutdown caused by water, immediately find the cause of the shutdown, and take effective measures to repair or replace parts, and timely restoration of water supply.
(3) such as municipal pipe network caused by water outages, immediately check whether the municipal pipeline inlet valve failure or contact the water company to understand the cause of water outages, the resumption of water supply time. Timely cooperation with the service center to do a good job of explaining the relevant work to the owners.
Second, the emergency treatment of sudden power failure
1, high-voltage ring cabinet sudden power failure
(1) engineering duty personnel should contact the power supply department of the high-voltage lines in a timely manner, and in the absence of identifying the cause of the failure before any operation is strictly prohibited.
(2) If the point of failure is not in the jurisdiction, it is estimated that the troubleshooting time is long, the high-voltage operators of the power supply department can be transferred to another high-voltage power line (if any), and the prohibited switch hanging "no closing" signage.
(3) After the fault is removed, the power supply department operator to restore the original power supply line.
2, distribution room circuit breaker tripped blackout
(1) engineering duty personnel received a blackout notice, immediately rushed to the blackout site, the circuit breaker will be under the branch load switch disconnect, the circuit breaker tripped hanging "line maintenance, forbidden to close" signage.
(2) With a shaking table to detect the branch lines.
3) After the fault line is identified, close the other lines to restore power.
4) Hang the "line maintenance, forbidden to close the gate" signboard on the switch of the problematic branch line, and further overhaul the line to eliminate the problem and restore power supply.
3, the owner of the room tripped
1) duty engineering staff received a blackout notice, immediately rushed to the scene of the blackout, inspection and maintenance before, should be aware of the owner of the meter tripped before the use of other electrical appliances, in order to quickly find the point of failure.
2) If the fault is the household main switch, immediately turn off the main switch and other sub-circuit air switch, and then open the main switch.
3) If the main switch does not jump, and then send the sub-switch, such as a sub-switch can not be sent on, that is, the line for segmentation testing, until the fault, restore power.
First, the purpose and significance of the exercise
1. Through the exercise, to improve the hospital's logistical support and the ability to dispose of the sudden public **** events, to protect the lives of patients and hospital property safety, to maintain hospital safety and medical order stability, to promote the comprehensive coordination of medical work in the hospital, and sustainable development. Development.
2. Through the drill, to enhance the staff's sense of worry and emergency awareness, social responsibility and self-help, self-help ability to improve the hospital's ability to deal with power supply emergencies rapid response.
3. Through the drill, test and examine the rationality and effectiveness of the hospital's power supply emergency mechanism, and put forward measures and methods of improvement, and further revise and improve the emergency plans for various accidents.
4. Through the drill, exercise logistics support emergency management and electrician group emergency rescue team, and constantly improve the mastery of the accident emergency treatment essentials, for once a large area of blackout events can be quickly and effectively disposed of and minimize the incident loss and accumulate experience.
5. test "xx city people's hospital emergency plan for large-scale power outages" operability.
Second, the basic requirements and principles of the exercise
1. Must follow the principle of safety first, well-organized, effective measures to ensure the safety of the exercise;
2. Must be from the actual combat, to be targeted, representative of the key departments, to ensure that the effect of the exercise;
3. Adopting a unified leadership, unified arrangement, graded responsibility method.
4. This drill specific exercises organized by the General Affairs Section, the hospital office coordination, the hospital's functional departments to cooperate with the active participation of the relevant departments and teams.
Third, the exercise time:
xx November 10, 7:00 am to 12:00 noon.
Fourth, the drill organization and responsibilities
1. Emergency leadership group leader responsibilities: in accordance with the requirements of this exercise program, unified leadership command hospital large-area blackout emergency response exercise work; organization to set up the corresponding emergency drill organization; responsible for the exercise of the overall program of the validation; coordination of the relevant departments of exercise Coordinate the relationship between the relevant departments of the exercise; announce the start and termination of the emergency plan; issue emergency instructions for the exercise. The exercise is evaluated and summarized.
2. Exercise office responsibilities: responsible for the organization of the development of exercise plans and overall program; responsible for the coordination of the coordination of the sections, organization and command; implementation of the specific work of the sections of the exercise.
3. Emergency repair team responsibilities: in the event of an accident, the organization of personnel to implement rescue operations; to the command team to report the accident, if necessary, to the power supply sector to send a request for assistance, and afterwards summarize the lessons learned from the emergency rescue work.
4. Each section team responsibilities:
1) responsible for section blackout material preparation.
2) Responsible for the emergency treatment of severe patients with power outage, to ensure that the patient ventilation, cardiac monitoring, treatment, etc., to ensure the safety of the patient
V. Exercise content
(a) Emergency start-up and event reporting
1, due to the 110kV Yingcheng substation station equipment accident caused by the loss of the whole station, resulting in a large area of blackout in Wencheng City, the city. City north of a large area of power outages.
2, the Southern Power Grid xx City Company Wencheng power supply office to the hospital electrician group report the accident situation notice. The head of the electrician group reported to the head of the large-area power outage emergency leading group and recommended measures.
3, the hospital emergency leadership team decided to start the "xx City People's Hospital large-area power outage emergency plan" according to the incident.
4, the exercise office will be blackout events and start "xx City People's Hospital large area blackout emergency plan" decision to notify the departments and teams.
(B) emergency treatment
1, emergency repair team
① Immediately start the first set of generator backup power to ensure the supply of medical power.
② If the first set of generator backup power failure, start the second set of generator backup power to ensure that the operating room, emergency department and other key departments of the power supply.
③ Check the elevator, if there is a lock on the passengers, immediately use manual methods to put all the passengers out, and at the same time to do a good job of passenger thinking. Restore the normal operation of the elevator.
2, the clinical departments, especially the emergency ICU, operating room, neonatal ward.
① Immediately look for ways to rescue the patient's power to maintain the rescue work, and open the emergency lights lighting.
② Critical patients, patients using the ventilator in surgery should be equipped with a simple respirator next to the machine, in case of a sudden power outage, health care workers immediately disengaged the ventilator, the use of simple respirator to maintain breathing. Patients using electric sputum suction, with a 50ml syringe connected to the suction tube sputum.
③ before the hospital generator power supply, medical staff should first ensure that the patient's rescue; nurses should be calm and sedate, on the ventilator using the hand-held ball method, on the monitor using manual measurement of blood pressure, pulse, electric sputum suction using a 50 ml syringe connected to the sputum suction tube suction, etc., and closely observe changes in the condition, and the use of emergency lights for illumination.
④ Strengthen the ward patrol, appease the patient, and pay attention to fire, theft.
⑤ Discontinue the use of boiling water and heating and other energy-consuming equipment.
3, medical department
① Check the operation of the uninterruptible power supply.
② equipment equipped with uninterruptible power supply in the hospital generator backup power supply before the resumption of power, to complete the ongoing checks after the shutdown standby.
③ The hospital generator backup power supply to restore power, start the normal project inspection. But must pay attention to observe the operation of the equipment. If the motor back-up power supply voltage instability caused by the hospital equipment operation is not normal must stop standby.
Six, the end of the emergency (emergency lifting and aftermath)
1. Setting the time of the exercise in four hours, the accident processing work into the end.
2. Municipal power grid resumed power delivery, the electrician group to the exercise office to report on the restoration of the grid, requesting the lifting of the state of the large-scale blackout event.
3. The emergency repair team is ready to switch the municipal power supply, notify the valuable equipment departments (such as radiology, ultrasound room, laboratory, etc.) to be ready to switch.
4. The head of the emergency leadership team decided to lift the state of the large-scale power outage.
5. The drill office sends a notice to each section shift announcing the lifting of the large-scale power outage emergency warning.
6. The large-scale power outage emergency leading group announced the end of the exercise.
7. Each section team to the exercise office to report on the exercise.
Seven, the drill evaluation summary
1. In order to make the drill to achieve the expected purpose, to ensure the smooth progress of the drill, the drill program review.
2. Summarize the end of the exercise, the exercise process evaluation, summarize the experience and shortcomings, the formation of the exercise evaluation report, the future work to provide reference and guidance.
Eight, the drill security measures and notes
1. Advance publicity should be carried out to eliminate the workers and patients on the drill doubts.
2. Before the start of the drill, each section of the team should do a good job of the relevant safety measures, strengthen the organization and leadership to ensure that the drill is safe and smooth.
3. In accordance with the emergency procedures, unified command, listen to scheduling, strictly according to the program.
4. During the exercise, hidden dangers or accidents were found, and the exercise work was stopped in time and reported to the office of the emergency leading group.
5. Drill process in the event of an emergency, the drill will be temporarily terminated.
Hospital sudden power outage emergency work program template Part 6Emergency measures taken after the power outage occurs:
1 Distribution room watchman found that the power outage faults, should be promptly notified to the management office engineering director.
2, the engineering supervisor immediately to the scene, the organization of the duty electrician to check the status of the power system, and promptly report to the director of the management office;
3, when the failure of the external line leads to the main supply power outage;
1, the duty electrician to check the indicator plate of the vacuum switch whether the split gate, and then check the voltage and the indicator light, when it is clear that the loss of voltage and power failure, according to the "Electricity Regulations" requirements will be the main supply power outage When it is clear that there is a loss of voltage and power failure, the main power supply cabinet vacuum switch will be withdrawn according to the requirements of the Electricity Regulations, and the "someone is working, prohibit the closing of the gate" sign will be put up;
2. The electrician in the duty room will report to the dispatch office of the Power Supply Bureau to understand the status of the outage of external wires;
3. The director of the project will report the status to the manager of the management office in a timely manner and mention the activation of the standby power supply. According to the "Electricity Regulations" to send on the backup power;
5, check whether the equipment operation is normal, blackout area has been restored to normal;
6, after the restoration of normal power supply, timely report to the director of the management office;
7, a detailed record of the whole process of the accident (time of blackout, time of the report, the name of the person who received the phone call, the report of the information, the time of leaving, the cause of the accident, etc.);
8, when the failure of the inner line leads to the main supply power outage;
9, the engineering supervisor to organize mechanical and electrical inspection of the cause of the power system failure and timely repair;
10, to strengthen the security patrol of the electric area;
11, the engineering supervisor to report the situation in a timely manner to the director of the management office, approved by the director of the management office, the reason for the phone to explain to the user and to remind users to prepare for the incoming call
12, the engineering supervisor asked the electrician on duty to prepare for the operation, according to the "Electricity Regulations" to carry out the operation of the power supply;
13, check whether the equipment is running normally, the blackout area has been restored to normal;
14, after the restoration of normal power supply, report to the director of the management office in a timely manner;
15, a detailed record of the whole process of the accident (blackout time, report time, the receiver of the call) time, report time, name of the recipient, report information, leaving time, cause of the accident, etc.)