Current location - Recipe Complete Network - Catering industry - Shijiazhuang catering waste treatment equipment
Shijiazhuang catering waste treatment equipment
? This paper introduces a truly efficient septic tank-annular baffled anaerobic reaction tank.

(Wuxi is vigorous and environmentally friendly? Han Shengjian)

ABR anaerobic baffled reactor (ABR anaerobic baffled reactor) is commonly known as high-efficiency biological septic tank, but its internal structure is completely different from all kinds of septic tanks, and it belongs to the international advanced third-generation new high-efficiency anaerobic reactor.

The invention has the advantages of strong biosolids interception capacity, good hydraulic mixing conditions, separation of sludge retention time and hydraulic retention time, greatly shortening the time required for anaerobic treatment of high-concentration organic wastewater, greatly improving the treatment capacity, treating effluent well, simple structure, stable and reliable operation, and being capable of generating biogas for collection and utilization, as well as emptying and discharging. This is a truly efficient septic tank.

The annular baffled anaerobic reaction tank is suitable for the treatment of various organic wastewater, and its treatment efficiency and quality are much higher than those of septic tanks and integrated biochemical tanks, which can greatly improve the effluent quality standard. It is especially suitable for areas where sewage treatment plants cannot be connected and need direct drainage.

The annular baffle anaerobic reaction tank is made of glass fiber reinforced plastic, with 1 slag storage bin and 8 plug-flow anaerobic bins. It has compact structure, small volume, convenient installation and use, less investment and high efficiency. Can be widely used in residential quarters, hotels, institutions, factories and mines, schools, as well as livestock breeding, food processing and other high-concentration wastewater treatment.

The schematic diagram of the annular baffled anaerobic reaction tank is as follows:

According to the experience of rural areas in Shanghai, the urban drainage system in some rural areas in Shanghai can't keep up with the construction. On the basis of improving the original rural septic tank, experts arranged pipelines along the river to collect sewage into the newly-built high-efficiency biological septic tank (baffled anaerobic reaction tank). The pollution concentration of domestic sewage is greatly reduced after precipitation, filtration, anaerobic acidification and biodegradation in high-efficiency biological septic tank. This practice has basically eliminated the black smell that has plagued the villagers for a long time and is well received by the villagers. It has a good reference for the regulation of black and odorous rivers in areas without sewage collection system nearby.

List of specifications and models:

Specifications and models

Lead ZL-3

Lead ZL no.5

Lead ZL- 10

Lead -ZL- 15

Lead -ZL-20

Lead ZL 30

Diameter× height

1.6×1.5m.

1.8×2.0m

2.4×2.3 meters

2.8×2.5 meters

2.8×3.3 meters

3.0×4.3 meters

Rated volume

3 cubic meters

5 cubic meters

10 cubic meter

15 cubic meter

20 cubic meters

30 cubic meters

Applicable number

15

25

50

75

100

150

? Integrated and efficient biological septic tank (annular baffled anaerobic reaction tank)

Installation and use method

The integrated high-efficiency biological septic tank is transported to the construction site, buried in the floor according to the position and elevation requirements designed in the drawings, and can be used after pipeline connection (see schematic diagram). There are the following points in installation and use:

1. Integrated high-efficiency septic tanks are generally set under green spaces or sidewalks. If it is set under the roadway or the depth of soil cover exceeds 1m, reinforcement measures should be taken to expand the bearing area and reduce the pressure above the tank.

2. The size of the pit buried in the pool body should be suitable for the pool body, and the bottom of the pit should be flat. If necessary, proper gravel can be laid at the bottom of the pit for leveling. The elevation of the pit bottom should meet the requirements, and the elevation of the water inlet of the pool body should not be higher than that of the upstream water inlet pipeline; The elevation difference between the water outlet of the water tank and the elevation of the downstream sewage pipe should be more than 250px.

3. In areas with high groundwater level, after the integrated high-efficiency septic tank is positioned in the foundation pit, the tank is filled with water first, and then the foundation pit is covered with soil to prevent groundwater from floating up to the tank. When covering the soil, it should be watered and tamped by layers, and it is not advisable to tamp in large pieces.

4. After the tank is buried underground and the surrounding soil is backfilled, manhole rings can be built in the center of the tank top and around the slag outlet, and the elevation is flush with the outdoor ground, and then the outdoor ground can be prepared, or lawns and flowers can be planted. In future inspection or slag removal, just open the manhole cover and open the slag removal cover of the manure storage bin.

5. Before covering the top of the pool with soil, it is necessary to pay attention to connecting the gas outlet (exhaust) pipeline with the lower part of the downspout of the nearby house with tee, and then covering the soil, so that the decomposed waste gas in the pool and the air at the drain outlet can be discharged into the air through the downspout.

6. The integrated high-efficiency septic tank does not need personnel to maintain at ordinary times, and the manure and sundries in the manure storage bin can be cleaned once more than one year. If there are no non-degradable items entering, it can be cleaned for several years. When cleaning, open the slag cleaning cover, suck out or remove the slag cleaning debris and cover the cover plate.

Schematic diagram of installation: