Current location - Recipe Complete Network - Catering industry - How to deal with the fire of Guilin catering over 300 square meters?
How to deal with the fire of Guilin catering over 300 square meters?
Drawing by a qualified design unit-submit it to the fire department for review-issue an audit opinion-modify the drawing according to the audit opinion-re-submit it for approval-issue a construction opinion-submit the original audit to the construction unit for archiving-hand over the project construction-commissioning-submit it to Party A after completion-test by a professional unit-issue a test report-submit it to the audit unit for acceptance-issue a qualified opinion-

design drawing

1. Design specification

1) Engineering design basis 2) Building scale and design specification 3) Overall indicators 4) Adoption of new technologies, new materials, new equipment and new structures. 5) Fire protection design with special fire risk and problems that need to be solved or determined when design approval is required.

2. Master plan

1) Area plan 2) General plan

3. architecture, structure

1) plan view 2) elevation view 3) section view

4. Building electricity

1) plan of fire control room 2) automatic fire alarm system, with plan of alarm system on each floor 3) fire power supply and distribution lines.

Road and electrical equipment

5. Fire water supply and fire extinguishing facilities

1) General plan of fire water supply 2) System plan and layout of each fire water supply system 3) Plan of fire pool and fire pump room 4) Plan and layout of other fire protection systems 6. Smoke prevention, exhaust and HVAC.

1) Equipment layout of boiler room 2) Layout of other power stations.

7. Decoration professional design drawings

1) plan

2) Elevation view

3) Introduction

The following materials shall be provided for applying for fire protection design audit

1. Declaration Form for Fire Protection Design Audit of Construction Project

2. Legal identification documents such as the business license of the construction unit.

3. Construction project planning documents for new and expanded projects.

4. Qualification certificate of design unit

5. Fire protection design documents

1) Fire protection design documents shall include design specifications, design drawings of related disciplines, main fire protection equipment, fire protection products, and a list of components and building materials related to fire protection performance requirements, with emphasis on the design contents required by national technical standards for fire protection in engineering construction.

2) Fire protection design documents shall be prepared in the following order:

5.2. 1: cover: project name, design unit and date.

5.2.2: Title page: the names of the legal representative, technical director, project director, and professional directors of the design unit, which shall be signed or sealed by the above-mentioned personnel.

5.2.3 Directory of Design Documents

design instruction

6. Copy of support fee

Some construction units go to the financial window of the government examination and approval center to pay the supporting fees for fire-fighting facilities and get a receipt, and with this receipt, they go to the Finance Bureau to get a formal invoice.

build

1. The construction unit shall organize technicians from all construction units to conduct the blue prints.the design, and the design institute shall conduct design disclosure.

2. Carry out the construction of various disciplines, follow up the construction data, complete the project installation and system debugging.

3. The project is completed and accepted by Party A.

4. Professional construction data archiving

5. Professional preparation of construction drawings.

Completion handover

After the completion of the project, the construction unit, the user unit and the construction unit shall make an inventory of the on-site installation equipment. After the inventory is correct, the three parties shall sign and seal the handover form.

Professional test unit test

1. The inspection contents include fire control facilities inspection and electrical inspection, and the inspection fee shall be paid by the construction unit.

2. Unqualified detection shall be rectified, and a qualified report shall be issued after rectification.

To declare fire control acceptance, the following materials shall be provided

1. Declaration Form for Fire Control Acceptance of Construction Unit

2. Project completion acceptance report (completion data provided to the Project Construction Committee: complete set submitted to the archives)

3. Fire protection product quality certificate.

4. The certification documents that the building components, building materials and interior decoration materials with fire-fighting performance meet the national standards or industry standards, and the factory certificate (the above materials are tested by professional departments, and the expenses are paid by the relevant units of the materials submitted for inspection).

5. Fire fighting facilities. Qualification certificate of electrical fire control technology inspection

6. Legal identification documents of the construction, supervision and testing units.

7. Fire liability insurance (PICC, public gathering place)

8. Copy of supporting fees for fire control facilities

9. Copy of fire audit opinion.

10. Inspection record

1 1. Completion drawing (with completion seal)

12. Copy of legal person ID card, power of attorney and client ID card of the construction unit.

Opening fire inspection opinions

The fire department where the project is located shall issue the acceptance opinions on opening fire protection.

You can't start business until you get a fire permit.