Current location - Recipe Complete Network - Catering industry - Building safety agreement
Building safety agreement
In study, work and life, agreements are used more and more frequently, and signing agreements can ensure the happy cooperation between the two sides. So is it really difficult to write an agreement? The following are five construction safety agreements that I have compiled for you. Welcome to read the collection.

Construction Safety Agreement 1 Party A: (hereinafter referred to as Party A)

Party B: (hereinafter referred to as Party B)

As the newly-built student canteen in Nanzhong Teachers' Dormitory needs to be demolished, Party B shall be responsible for the demolition. According to the principle of "whoever constructs is responsible" in safety work, in order to ensure safety and clarify responsibilities, Party A and Party B agree to sign the following construction safety contract:

Article 1 Project, Address and Scope:

1. Demolition of teachers' dormitory in South Middle School

2. On the campus of Nanzhong Middle School.

3. All seven rooms in the east-west direction were demolished, and all other rooms in the north-south direction (1 1) were demolished.

Article 2 Structure and Unit Price:

1, brick-wood structure, 7 rooms in the east-west direction, 1 1 in the north-south direction, *** 18 rooms, each room is RMB * * (in words:)

2. At the beginning of the demolition project, the project payment shall be paid in one lump sum and a fine of 5,000 yuan (5,000 yuan) shall be imposed.

Article 3 Project duration

April 20xx to May 20xx. In case of force majeure affecting the construction (rain, water and electricity have not stopped), with the consent of Party A, the construction period can be extended accordingly. ..

Article 4 Responsibilities and Obligations of Party B

1. As the contractor of this project, Party B shall be responsible for personal injuries and accidents during the project construction.

2. Temporary fences or warning signs shall be set up within the construction scope, and construction shall not be carried out beyond the specified construction scope, and irrelevant personnel are prohibited from entering the construction site. Take safety precautions, do a good job in peripheral protection, show safety warning signs, delimit safety warning lines, and prohibit non-construction personnel from entering the construction site.

Article 5 Liability for breach of contract

If Party B causes personal injury, equipment damage and other property losses to itself or a third party, Party B shall bear the responsibility and compensate the third party for the economic losses caused thereby.

Article 6 Other matters

All old materials removed by Party B shall be owned by Party B; Garbage should be taken outdoors and must be moved to the ground. After the acceptance by Party A, Party A will refund the overdue fine.

Article 7 This agreement shall come into force after being signed by both parties, and shall automatically terminate from the date of signing to the date of dismantling this project. This agreement is made in duplicate, one for each party.

Party A: Party B:

Tel: Tel:

Signing time: year month day

Article 2 of the construction safety agreement: Party A: _ _ _ _ _ _ _ _ _ Investment Real Estate Co., Ltd.

Party B: _ _ _ _ _ _ _ Construction Engineering Co., Ltd.

The _ _ _ _ _ _ construction project invested by Party A is contracted out to Party B for construction. In order to clarify the responsibilities, the following agreement is reached on the cost of safety construction measures, which both parties shall abide by:

1. The basic cost of measures for on-site civilized construction and the on-site assessment fee shall be _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Second, Party B shall abide by the management regulations on safety production in engineering construction, organize construction in strict accordance with safety standards, and make reasonable investment. It is strictly forbidden to misappropriate basic expenses and on-site assessment fees. Take necessary safety protection measures to eliminate hidden dangers of accidents.

Three. Party B shall take safety protection measures in power equipment, transmission lines, underground pipelines and construction of main roads along the street. The cost of protective measures arising therefrom shall be borne by Party A after being confirmed by the engineer.

4. If the construction site is temporarily shut down, Party B shall do a good job in site protection, and the required expenses shall be borne by the responsible party or executed according to the contract.

Verb (abbreviation of verb) Party A shall conduct safety education for its employees on the construction site and be responsible for their safety. Party A shall not require Party B to carry out construction in violation of safety management regulations. If a safety accident is caused by Party A, Party A shall bear the corresponding responsibilities and expenses.

6. This agreement is made in duplicate, signed by the representatives of both parties and stamped with the official seal of the unit. Each party holds one copy and supervises the implementation.

Chapter III of Construction Safety Agreement Party A: XXXXXXXXXXX

Party B: XXXXXXXXXXX

Party A and Party B have reached an agreement on the construction of road traffic safety facilities in Luzhou Liquor Concentrated Development Zone in accordance with the Contract Law of People's Republic of China (PRC), the Road Traffic Safety Law of the People's Republic of China and other relevant laws and regulations, and following the principles of equality, fairness, honesty and credit. Details are as follows:

I. Overview of the Project

(1) Project Name: Project Name: Project Name: Project Name: Project Name: Project Name

(II) Project Location: XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

(3) Project scope: Installation of road markings and signboards. See attached drawings for specific construction contents.

(4) Contracting method: contracting for work and materials.

(5) See the attached drawings for the supplementary explanation of materials and processes.

Second, the contract time limit for a project and postpone conditions

(1) construction period

The total contract duration is about 53 days from the actual commencement date, and the completion date is 20xx165438+1October 25th.

(2) Conditions for extending the construction period

1. Party A fails to provide the construction drawings as agreed;

2. Design change or increase of engineering quantity;

3. Party B stops working for more than 24 hours due to water cut, power cut and gas cut;

4. Party B stops working for more than 24 hours due to other force majeure.

(3) Within 1 working days after Party B meets the conditions for extending the construction period, Party A shall put forward a written request for extending the construction period, and Party A shall confirm it within 1 working days after receiving the report. Fails to confirm, as agreed to extend the construction period.

Third, the construction and safety requirements

(1) construction requirements

1. Party A shall assist Party B in handling relevant construction permit procedures and coordinate all aspects.

2. Party B shall design the construction scheme for Party A free of charge in strict accordance with relevant national requirements, and submit the planning scheme to Party A within seven working days after signing the contract.

3. Party B shall complete the processing of the main components and deliver them to the site within seven working days after receiving the notice that Party A's construction drawing is approved.

4. Party B shall purchase and process in strict accordance with the requirements of construction drawings, and provide relevant materials to ensure the quality.

5. Party B shall carry out civilized construction in strict accordance with the construction requirements specified in the construction permit, and Party B shall bear all the responsibilities for the losses caused by the barbaric construction not as required.

(2) Safety requirements

Party B shall abide by the management regulations on safety production in engineering construction, organize construction in strict accordance with safety standards, take necessary safety protection measures to eliminate hidden dangers of accidents, and accept the supervision and inspection of Party A's representative.

Fourth, the project quality, acceptance and quality assurance

(1) quality standard

Party B shall carry out the construction in strict accordance with the clear requirements of Code for Design of Reinforced Concrete GBJI0-87 and Code for Setting Road Traffic Signs and Marks JTGD82-20xx to ensure the engineering quality.

(2) Project acceptance

1. Party B shall send a written acceptance notice to Party A ten working days in advance. If Party A fails to attend the acceptance on schedule, it shall reply to Party B in writing within three working days, and the acceptance date shall be agreed separately.

2. If Party A does not raise any objection after receiving the acceptance notice from Party B, but fails to organize the acceptance on the due date, the project shall be regarded as completed and qualified.

3. After the project is completed and accepted, the project handover shall be completed within three working days from the next day of acceptance.

(3) Engineering quality assurance

The warranty period of this project is within one year from the date of project completion acceptance, and Party B is responsible for the warranty of this project. During the warranty period, except for the engineering maintenance caused by force majeure, all expenses such as materials and labor costs involved shall be borne by Party B. After the warranty period expires, Party B will provide lifelong maintenance services.

Verb (abbreviation of verb) settlement of contract amount and expenses

(1) Contract amount: RMB two million eight hundred and thirty-six thousand four hundred and eighty-three Yuan only, in figures ¥ 2,836,483 Yuan.

(II) Within five working days after signing the contract, Party A shall pay Party B 30% of the total contract amount as the first progress payment.

(3) Within 7 working days after the equipment installation, Party A shall pay 50% of the total contract amount to Party B as the second-stage progress payment.

(4) Party A shall pay 15% of the total contract amount to Party B as the third progress payment within 20 working days from the date when the project is completed and accepted.

(5) 5% of the total contract amount is used as the quality guarantee, and the warranty period is one year. If there are no quality problems during the warranty period, Party A shall pay the quality deposit to Party B in full within ten working days after the expiration of the warranty period.

Liability for breach of contract of intransitive verbs

(1) Party A breaches the contract.

If Party B fails to pay the project progress payment on time as agreed in the contract due to Party A's reasons, which causes Party B to delay the construction period, Party A shall bear the extra expenses such as material storage and lost work caused by the construction period delay.

(2) Party B breaches the contract

1. Except for force majeure, if Party B fails to complete all the projects and pass the acceptance inspection on the date stipulated in this contract, Party B shall pay Party A a penalty of one thousandth of the total contract price for each overdue day, and the calculation time shall be the date when all the projects pass the acceptance inspection.

2. If the project cannot be put into normal use due to Party B's reasons, Party B shall pay Party A a liquidated damages of 10% of the total contract price and bear all losses caused to Party A from this.

3. For any safety accident caused by Party B's failure to comply with the requirements of safety production regulations in the construction process, Party B shall bear all responsibilities and compensate all losses caused to Party A by this accident.

Seven. Dispute mediation

Disputes between Party A and Party B in this project shall be settled through negotiation as far as possible. If negotiation fails, either party may bring a lawsuit to the court where the contract is performed.

Eight. supplementary terms

(1) This contract is made in quadruplicate, with Party A and Party B holding two copies respectively, and shall come into effect after being signed and sealed by both parties.

(II) For matters not covered in this contract, both parties may sign a supplementary agreement through consultation according to specific conditions and relevant regulations, and the supplementary agreement has the same effect as this contract.

(3) Appendix to the Contract

1. Standards, specifications and related technical documents;

2. Construction drawings;

3. A written agreement or document between the two parties on project negotiation and change.

Party A: XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

Address: xxxxxxxxxxxxxxxxxxxxxx

On behalf of:

Telephone/fax: xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx

Bank: XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

Account number: xxxxxxxxxxxxxxxxxxx

Party B: XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

Address: xxxxxxxxxxxxxxxxxxxxxxx

On behalf of:

Telephone/fax: xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx

Bank of deposit: XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

Account number: XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

Signing time: year month day

In order to strengthen management, improve safety awareness and self-protection awareness, and avoid major accidents, industrial accidents and fire hazards, Article 4 of this construction safety agreement is specially formulated:

1, each construction group belongs to each type of work, we should study hard, strictly abide by the implementation of safety technology operating procedures, and abide by safety production rules and regulations.

2. Take an active part in all kinds of safety activities, conscientiously implement safety disclosure, do not violate the rules and regulations, and obey the guidance of the safety officer. Construction personnel must wear safety helmets when entering the construction site.

3. Carry forward the spirit of unity and friendship, help each other in production safety, supervise each other, and conduct three-level safety education for new workers.

4, actively put forward opinions on unsafe operation, and have the right to refuse illegal instructions.

5. Ensure that no fatal accidents, industrial accidents, fire accidents and public security traffic accidents occur in this project.

6, such as death and traffic accidents, should immediately protect the scene, immediately report, assist the higher authorities to do a good job in the investigation.

7, the construction site must have a person in charge at the scene is responsible for the safety construction, in order to deal with emergencies.

8. It is forbidden for construction personnel to work after drinking.

9, for special type of work construction personnel must hold relevant certificates, it is forbidden to unlicensed construction.

10, smoking is prohibited in the construction site, and construction is not allowed without bare arms and slippers.

1 1. Don't tamper with electrical equipment and wires at the construction site. If necessary, find a leader or professional and technical personnel, and don't tamper with fire-fighting facilities, fire-fighting equipment and materials.

12, no participation, no fighting, no drugs, no drinking, no trouble.

In any of the following circumstances, the parties concerned shall be punished according to the specific circumstances:

1. Whoever steals at the construction site shall be punished by twice the price of the stolen goods;

2. Managers who enter the construction site in violation of regulations shall be fined twice;

3, do not comply with the site management regulations, a total of three times a week, will be expelled from the site.

Construction unit: Construction unit:

Signature: signature:

Year, month, sun, moon, sun.