The natural gas company undertakes the main task of supplying gas to the residents of Lvliang city. Within the production department, comprehensive department, safety inspection department, business department, technical department, engineering department, production department is responsible for urban pipeline operation and management, residential users of indoor gas appliance maintenance, etc., set up under the pressure regulator group, line patrol group, maintenance group, business department set up under the customer service center, business hall, government hall charge point. At present, more than 90 kilometers of gas pipeline network has been built, a natural gas gate station, two in the middle of the regulator station, 60 low-pressure regulator station, the gas penetration rate of 93.6%, there have been 32,000 residential users, while the burden of 381 hotels, catering industry, 20 schools gas supply tasks. The daily gas supply is 200,000 cubic meters, and the gasification population reaches 155,000 people. In the municipal party committee and municipal government's strong support, in 2009, started the natural gas authorization operation application work, in May 2009, completed the "Lvliang City (Li Shi urban area) city natural gas planning program", through the expert review, and got the authorization of the provincial government. 2013 June, the urban natural gas has been completely replaced.
On May 18, 2012, the company started the natural gas utilization project. The project is responsible for providing living gas to the residents of Lvliang urban area, further alleviating the shortage of clean energy in the area, improving the local energy structure and reducing the emission of pollutants. In order to protect the natural ecological environment, enhance the taste of the city, improve the quality of life of residents, as early as 2009 the company began to apply for approval of natural gas development and utilization of the project management rights, and do everything possible to introduce natural gas - clean energy instead of coke oven gas. After more than a year of efforts, Shanxi Province, the comprehensive development and utilization of coalbed methane (natural gas) leading group issued "on the Lvliang Dongyi Coal Gasification Co., Ltd. natural gas business license approval of the relevant issues", agreed to the company to operate natural gas and related businesses. Natural gas utilization projects include: natural gas pipeline construction, transportation and management, and natural gas sales within the urban area of Lvliang City.
On August 20, 2012, China Mobile Shanxi Company and Lvliang Dongyi Group Coal Gasification Company Limited jointly launched the cell phone payment of gas bills. Lvliang citizens will be able to pay their gas bills in a convenient way through cell phone payment.
Starting now, in Lvliang City, Shanxi mobile users, open the cell phone payment business and ensure that the account has a full amount of pre-deposit, simply send a designated text message "lldymq # gas card number # amount" to 10658518, according to the prompts to operate, you can realize the payment of gas charges, check the balance of the gas card and other matters, the whole operation process is convenient, simple and easy to operate. The whole operation process is convenient and simple, which greatly reduces the waiting time for customers to queue up to pay bills on site and facilitates the gas payment needs of the majority of mobile users.
At 21:00 on September 25, 2012, the company's natural gas pipeline network section of the first successful test pressure. This marks the first phase of the Lvliang urban natural gas utilization project constructed by the company, the entire line through, has the natural gas replacement conditions.
On the afternoon of October 2, 2012, the first batch of natural gas replacement in the urban area of Lvliang City was successfully completed. Under the leadership of the company manager and the on-site command of the Minister of Production, all the staff of the Production Department worked overtime for many days and nights to complete the first batch of replacement safely and without accidents. During the period occurred a lot of singing and crying deeds, regulator group members in the city to ensure the normal operation of the situation, still in the newly established door station on time duty, they do not care how much pay is still fighting in the gas front line of the spirit of the other departments is very admirable.
In June 2013, the city's natural gas has been completely replaced.
The project is involved in Lvliang city thousands of households of a people's project, to improve the urban environment and air quality, improve the livability of the city taste is of great significance, but also the Dongyi company to reduce losses for profits, to achieve diversified development, sustainable development and transformation of the important initiatives across the development.
The following infrastructural projects of the company have now been selected and announced, and will be started in 2013
Lvliang Lijiawan Natural Gas (Coalbed Methane) Gate Station
Lvliang Dongyi Group Coal Gasification Co., Ltd. intends to build Lvliang Lijiawan Natural Gas (Coalbed Methane) Gate Station about 130 meters southwest of Wangjiashan Village of Li Jiawan Township of Liulin County. The gate station covers an area of 0.35 hectares, with a construction scale of 45,000 cubic meters per day.
The project's gas source is from the Lishi Substation of the Linxian-Liu Lin-Linfen CBM (natural gas) transmission pipeline, which mainly provides domestic gas for the residents of Lvliang city.
Lvliang Tianjiahui Natural Gas Sub-transmission Station, Gate Station and Filling Parent Station
Lvliang Dongyi Group Coal Gasification Co., Ltd. proposes to construct the Lvliang Tianjiahui Natural Gas Sub-transmission Station, Gate Station and Filling Parent Station about 220 meters southeast of Shanglouqiao Village, Tianjiahui Street Office, Lvliang Lishi District. The sub-transmission station, gate station and gas refueling mother station cover an area of two hectares, and the construction scale is 45,000 cubic meters per day.
The project's gas source comes from the Yulin-Jinan natural gas pipeline. The natural gas sub-transmission station and gate station will mainly provide living gas for the residents of Lvliang city, and the gas filling mother station will supply gas to the gas filling sub-stations in the city through tanker trucks.
Lvliang Zaolin Natural Gas (Coalbed Methane) Sub-transmission Station, Gate Station and Filling Mother Station
Lvliang Dongyi Group Coal Gasification Co., Ltd. proposes to construct the Lvliang Zaolin Natural Gas (Coalbed Methane) Sub-transmission Station, Gate Station and Filling Mother Station about 30 meters south of Zhangjiashan Village of Zaolin Township, Lvliang Lishi District. The sub-transmission station, gate station and gas refueling mother station cover an area of 1.5 hectares, with a construction scale of 50,000,000 cubic meters per day. The gas source of this project comes from the natural gas transmission pipeline of Sanjiao Block. The natural gas distribution station and gate station mainly provide domestic gas for the residents of Lvliang city, and the gas filling mother station supplies gas to the gas filling sub-stations in the city through tanker trucks