Current location - Recipe Complete Network - Catering training - What are the contents of desulfurization maintenance work plan?
What are the contents of desulfurization maintenance work plan?
Analysis of desulfurization operation and maintenance capacity and promotion planning report 1, desulfurization operation and maintenance capacity analysis The desulfurization system operates normally, stably, reliably and efficiently, which involves the vital interests of customers. At the same time, whether the desulfurization system is reliable depends on whether the design of the whole desulfurization system is reasonable, whether the equipment is reliable, and more importantly, whether the operation and maintenance meet the requirements. At present, most domestic large-scale units' ammonia desulfurization operation and maintenance projects adopt EPC mode, which has a high degree of technical secrecy and little experience to learn from. However, it is difficult to introduce experienced talents, and the personnel are unstable, which is not conducive to the safety and stability of equipment and has great environmental risks. At present, the construction period is tight and the task is heavy. Considering the shortage of personnel in relevant positions, the technical force can not meet the needs of current production work, and the desulfurization operation and maintenance technology is still lacking and insufficient, and the outsourcing team with relatively mature technical ability needs to participate in cooperation. Second, the desulfurization operation and maintenance capacity improvement plan At present, our company has entered the stage of single machine debugging, and the desulfurization mode of unit configuration is ammonia desulfurization. Due to the lack of professionalism and pertinence, the desulfurization system specially applied to the industrial energy-saving company to adopt the operation and maintenance outsourcing method. In order to ensure the safe and stable operation of the project, the leaders of the industrial energy-saving company decided to temporarily outsource the desulfurization system for one year. According to the requirements of the superior company, after the operation and maintenance outsourcing contract expires, in order to successfully take over the operation and maintenance of our company, we will strive to cultivate and build a high-quality personnel team to avoid the unfavorable situation of being busy, chaotic and poor at that time. Now, regarding the staffing and training management of the desulfurization system, the plan is as follows: (1) Improve the staffing of 1. Operation: 4 main desulfurization personnel, 4 deputy desulfurization personnel and 8 desulfurization inspectors; 2. Maintenance: 1 desulfurization technician, 1 monitor, 8 maintenance workers; 3. Ammonium sulfate packaging: bagging, palletizing and loading 6 people. The above personnel can be recruited in the society, and can also be transferred from existing personnel for centralized training. Because this part of the staffing plan was not included in the previous company plan, the staffing needs to be increased by 32 people. (2) Strengthen the professional management of desulfurization 1. Improve various rules and regulations, improve various rules and regulations of desulfurization system, and supplement or revise rules and regulations according to their scientificity and practicality. After revision, it is necessary to realize the guidance and standardization of this major, ensure scientific management and sustainable development, and be simple and easy to operate. 2. Strengthen the basic management of safety, strengthen the management of the "two measures" plan and put it in place, compile safety technical measures and anti-accident measures in line with the actual situation on site, ensure the smooth and efficient operation of personal safety and desulfurization system, improve various basic data, strengthen personnel safety training and learning, and improve the safety awareness of all staff.

3. Strengthen management functions After the desulfurization rules and regulations are revised and improved, it is necessary to strengthen the professional management functions of desulfurization on this basis, strictly implement and implement various rules and regulations, and have supervision, inspection, implementation and assessment. (3) personnel training 1. Training objectives At present, although the internship team members in the production preparation stage of our company have received theoretical and on-site follow-up training, the desulfurization knowledge they have learned is far from the actual situation of our company, and there is still a certain distance from the maintenance requirements of our company after the operation and maintenance outsourcing. Therefore, this training plan is formulated through reasonable training arrangement and assessment according to the actual situation of operation and maintenance of ammonia desulfurization. Complete the professional technical and business knowledge training required for the operation and maintenance of ammonia desulfurization in a targeted manner, and meet the technical post grade standard of production work and the requirements of "three practices and three uses" (three practices: familiar with equipment, systems and basic principles; Familiar with operation and accident handling; Familiar with the rules and regulations of this position. Three functions: correct operation and analysis of running state; Be able to find and eliminate faults in time; Can master general maintenance skills), so that trained personnel can be competent for the operation and maintenance of ammonia desulfurization. 2. Training methods Training methods are divided into centralized theoretical training, practice (or simulation training) of the same type of units, and follow-up training of unit commissioning. Theoretical training is carried out by our company's desulfurization specialist and shift supervisor, while theoretical and practical training is carried out by the same type of unit plant specialist. Practical training is carried out in combination with our company's ammonia desulfurization monomer debugging and overall debugging. After the unit enters the trial production operation, the desulfurization operation and maintenance personnel of our company will receive training together with the personnel on duty. Through these trainings, the professional skills of operation and maintenance personnel will be improved to a higher level, so as to achieve the goal of qualified posts within the specified time. The training content of desulfurization post should include equipment system composition, equipment working principle, interlocking protection of system design, equipment start-stop monitoring requirements, routine test of system equipment, general exception handling principles, typical equipment accident cases, etc. , should also include the post daily management requirements and matters needing attention in daily work. 3. Training and implementation (1) desulfurization operation and maintenance personnel training, including professional foundation and professional knowledge training, internship training of the same type of units, etc. (2) The professional foundation and professional knowledge training (simulation training) of desulfurization operation and maintenance personnel should be full-time training; (3) The training content of desulfurization operation and maintenance personnel should be determined in combination with the training outline, equipment and system of Shanxi Zhongneng Lu 'an Waste Heat Power Generation Co., Ltd.. In the design and arrangement of training content, we should adhere to the integration of theory with practice, highlight the training of operational skills and pay attention to the improvement of operational skills;

(4) According to the characteristics of equipment and system, the training mode can be determined according to different training stages, and the combination of independent training and entrusted training should be implemented, focusing on improving the pertinence, effectiveness and practicability of training; (5) Establish an effective training mechanism with Jiangnan Environmental Protection, and conduct on-site training according to the desulfurization personnel configuration of our company. 4. Training plan (1) professional knowledge 1 master the professional knowledge training content of desulfurization duty and maintenance positions; 2. Master the layout and operation mode of desulfurization. (2) Professional skills: 1. Master the relevant measures to protect auxiliary power and the relevant contents of "25 key anti-accident measures"; 2. Master each link, composition and principle of desulfurization equipment and system; 3. Can correctly start and stop the main and auxiliary equipment according to the requirements of operation regulations; 4. Be able to patrol and inspect equipment, systems and local operation control devices; Be able to monitor and adjust the main and auxiliary equipment to make it run safely and economically; 6. Be able to find defects and anomalies in time and handle them correctly; 7. Be able to test the equipment regularly according to regulations; 8 can correctly execute the operation ticket and take various safety measures; 9. Adhere to the principles of prevention first, spot inspection and repair, and quality first, so as to keep the equipment in good condition and ensure the stable and efficient operation of the equipment; 10 can strengthen technical management, earnestly implement the maintenance responsibility system (the principle of compulsory maintenance and good maintenance), and implement the three-level acceptance system for maintenance; 1 1 The annual maintenance plan of flue gas desulfurization system equipment can be made according to the operating technical conditions of flue gas desulfurization equipment and the problems left over by the equipment in the previous year, with reference to the annual maintenance plan of boiler units; 12 You can prepare the articles before the maintenance starts. (3) Training content

Training Content Training Requirements and Methods Hours (Month/Day)

Desulfurization principle and technology; Master the technology and equipment of desulfurization system 03.05438+0—03.07.

Flue gas system; Equipment maintenance of flue gas system familiar with the equipment composition, characteristics and operation of flue gas system; Equipment maintenance of flue gas system 03.08—03.438+04

Absorption tower system; Equipment maintenance of absorption tower system familiar with the equipment composition, characteristics and operation of absorption tower system; Equipment maintenance of absorption tower system 03. 15—03.338+0

Ammonia system; Familiar with the equipment composition, characteristics and operation of ammonia system preparation system; Overhaul of absorber equipment 03.22—03.28

Ammonium sulfate system is familiar with the equipment composition, characteristics and operation of ammonium sulfate system 03.28—04.03.

Exhaust gas, process water and instrument air system are familiar with the equipment composition, characteristics and operation of process water system.

Start-up of ammonia desulfurization system; Confirm the conditions before starting, and be familiar with the equipment composition, characteristics and operation of ammonia desulfurization system 04.10-04.16.

Start-up of ammonia desulfurization system; Start the whole desulfurization system and be familiar with the equipment composition, characteristics and operation of ammonia desulfurization system 04. 17—04.23.

Start-up of ammonia desulfurization system; The dehydration, drying and packaging system of ammonium sulfate was started as a whole. Familiar with the equipment composition, characteristics and operation of ammonia desulfurization system.

Process adjustment of ammonia desulfurization system: maintenance of booster fan familiar with the equipment composition, characteristics and operation of ammonia desulfurization system; Maintenance of booster fan 05.01-05.07

Process adjustment of concentration section; Maintenance of Agitator Familiar with the equipment composition, characteristics and operation of concentration section process 05.08—05.438+04.

Process adjustment of demister; Maintenance of slurry circulating pump in absorption tower Familiar with the equipment composition, characteristics and operation of demister process; Maintenance of slurry circulating pump in absorption tower 05. 15—05.438+0

Anti-blocking regulations for system pipelines; Familiar with the equipment composition, characteristics and operation of the system pipeline for oxidation fan maintenance; Maintenance of oxidation fan 05.22—05.28

Normal operation of ammonia desulfurization system; Familiar with the composition, characteristics and operation of equipment related to normal operation when the secondary circulating pump is switched from 05.29 to 06.05.

Normal operation of ammonia desulfurization system; Start the standby slurry circulating pump, discharge pump, underflow pump and centrifugal pump, and be familiar with the composition, characteristics and operation of equipment related to normal work.

Normal operation of ammonia desulfurization system; Switch the discharge pump, underflow pump and centrifugal pump, and be familiar with the equipment composition, characteristics and operation related to normal work.

Accident treatment of desulfurization system; Excessive pressure difference of demister; Familiar with the equipment composition, characteristics and accident handling operation of sealed fan maintenance; Maintenance of sealed fan 06.21-06.27

Accident treatment of desulfurization system; Familiar with the composition, characteristics and operation of equipment for handling flue gas overheating accident in concentration section from June 28 to July 04.

Accident treatment of desulfurization system; Familiar with the equipment composition, characteristics and operation of secondary circulating pump trip accident treatment 07.05—07.6438+0 1.

Accident treatment of desulfurization system; All main circulating pumps trip; Familiar with the equipment composition, characteristics and operation of secondary circulation spray blockage 07. 12—07.438+08.

Accident treatment of desulfurization system; Be familiar with the composition, characteristics and operation of accident treatment equipment for high solid content in circulating tank 07. 19—07.25

Accident treatment of desulfurization system; Auxiliary power supply is interrupted; Familiar with the equipment composition, characteristics and operation of 07.26-08.438+0 absorption tower wall leakage accident treatment.

Accident treatment of desulfurization system; Treatment of screw blockage accident of dryer feeder 08.02—08.08 Familiar with equipment composition, characteristics and operation.

Auxiliary power supply is interrupted; Leakage of absorption tower wall; Familiar with 08.09—08.8+05 equipment composition, characteristics and operation of main pipeline and flange leakage accident treatment connected with absorption tower body.

Deactivation of ammonia desulfurization system; Maintenance personnel of flue gas damper are familiar with the composition, characteristics and operation of equipment related to system shutdown; Maintenance of flue gas damper door 08. 16—08.22

Boiler shutdown treatment; Equipment maintenance of crystallization drying system, familiar with the composition, characteristics and operation of equipment related to system shutdown; Equipment maintenance of crystallization drying system 08.23—08.29

Stop the operation of liquid ammonia (ammonia water) system, and be familiar with the composition, characteristics and operation of equipment related to system shutdown.

Stop replenishing process water; Familiar with the composition and characteristics of the equipment and the operation related to the system shutdown of the cyclone separator; Maintenance of Hydrocyclone 09.07—09.438+03

Stop the operation of the water washing device; The maintenance personnel of the dryer are familiar with the equipment composition, characteristics and operation related to the system shutdown 09 438+04—09.20.

Stop the operation of the discharge pump and the primary cyclone separator, and be familiar with the composition, characteristics and operation of the equipment related to the shutdown of system 09.438+0—09.27.

Stop the operation of the secondary circulating pump; Familiar with the composition and characteristics of equipment and the operation related to the shutdown of centrifuge maintenance system; Maintenance of centrifuge 09.28 ——10.04

Stop the operation of the main circulating pump; Stop the centrifuge, and be familiar with the equipment composition, characteristics and operation related to the system10.05—10.1shutdown.

Stop the operation of the oxidation fan; Familiar with equipment composition, characteristics and operation related to fan maintenance system shutdown; Fan maintenance10.12-10.18

Familiar with the composition, characteristics and operation of equipment related to the shutdown of circulating tank and slurry emptying system of absorption tower10.5438+09-10.25.

Stop the operation of the process water system; Familiar with the composition, characteristics and operation of parking related equipment in storage tank equipment maintenance system; Maintenance of storage tank equipment10.26—11.02

Isolation measures of desulfurization unit Be familiar with the composition, characteristics and operation of equipment related to system shutdown11.03—11.09.

Check after the desulfurization unit is shut down as a whole. Be familiar with the composition, characteristics and operation of equipment related to system110—11.16 shutdown.

Stop the operation of the primary cyclone system; Stop the operation of the secondary cyclone system, and be familiar with the equipment composition, characteristics and operation related to11.17-1.23 system shutdown.

Stop the operation of ammonium sulfate drying and cooling equipment, and be familiar with the equipment composition, characteristics and operation related to the system11.24-1.30 shutdown.

Inspection, maintenance and troubleshooting of ammonia desulfurization equipment; Familiar with equipment composition, characteristics and operation, system maintenance and troubleshooting; 12.438+0— 12.07.

Desulfurization inspection, maintenance and precautions; Rubber, glass flake, glass fiber reinforced plastic lining equipment maintenance familiar with the composition, characteristics and operation of system maintenance and fault handling equipment; Maintenance of rubber, glass flake and FRP lining equipment12.08—12.14

Phenomenon, causes and treatment of desulfurization system accidents; Familiar with the composition, characteristics and operation of system maintenance and fault handling equipment; 12. 15— 12.438+0.

Brief introduction of ammonia desulfurization electrical system: power supply and distribution system; Familiar with the equipment composition, characteristics and operation of electrical system of lightning protection and grounding system12.22-12.38+0.

The overall training, operation ticket training and maintenance training of desulfurization system are familiar with the equipment composition, characteristics and operation ticket operation of desulfurization system as a whole, and the equipment maintenance is 2016.05438+0.01-2016.31.

The actual operation and maintenance level of desulfurization system has been improved as a whole, and the actual operation and maintenance level has been steadily improved by 2016.02.05438+0-2016.02.29.

five

Baidu library VIP limited time discount is now open, enjoy 600 million +VIP content.

Go get it now

Desulfurization operation and maintenance capacity planning

Analysis of desulfurization operation and maintenance capacity and promotion planning report

1, desulfurization operation and maintenance capability analysis

The normal, stable, reliable and efficient operation of desulfurization system involves the vital interests of customers. At the same time, whether the desulfurization system is reliable depends on whether the design of the whole desulfurization system is reasonable, whether the equipment is reliable, and more importantly, whether the operation and maintenance meet the requirements. At present, most domestic large-scale units' ammonia desulfurization operation and maintenance projects adopt EPC mode, which has a high degree of technical secrecy and little experience to learn from. However, it is difficult to introduce experienced talents, and the personnel are unstable, which is not conducive to the safety and stability of equipment and has great environmental risks. Maintenance of desulfurization and denitrification system

skill

skill

square

situation

Tenderee: xxxxxxx Construction Company

Address: xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx

Date: 20 19 12/04

I. Overview of the Project

The overhaul project of desulfurization and denitrification system of 2×350MW unit in Shuozhou Thermal Power Company of huadian power international mainly includes desulfurization equipment system (including absorption tower and liquid metering system, oxidized air system, gypsum slurry equipment and slurry supply system, overflow box system, vacuum belt dehydrator, filtrate pool system, accident slurry box and pit system in absorption tower area, process water system, instrument compressed air system and other related equipment and systems, limestone pulverizing system and equipment, etc. ). Daily maintenance, fault repair, technical transformation and other maintenance work of all equipment of denitration equipment system (including urea dissolution, storage and transportation, circulation system, demineralized water system, pit system, denitration device in horizontal flue, instrument compressed air system and other related equipment and systems).

Page 1

Second, the construction organization and deployment

Our unit has established a strong leadership team, organized first-class technical management personnel and skilled construction personnel, and implemented the project manager responsibility system, which is fully responsible for the quality, time limit, safety and cost of the project. The project department set up a project steering group, with the project manager as the team leader. The Group shall coordinate, supervise and inspect the whole construction process, solve the problems existing in the overhaul construction, implement the requirements of the construction unit, check the progress, quality, safety and civilized construction of the emergency repair project, ensure the smooth construction of the overhaul maintenance project, and ensure the smooth completion of the project according to the contract.

1, construction management objectives

page 2

We will follow the management policy of "pursuing Excellence, providing excellent products, caring for life and benefiting society", provide users with satisfactory projects and services, and complete all the work within the scope of the contract in time to make it meet the operating conditions of the tenderee's equipment and various technical and management standards of the tenderee; Ensure that:

The project quality reaches the qualified standard;

The first acceptance rate of the project100%;

The major quality accident rate is zero;

The rate of major occupational safety and health accidents is zero;

The compliance rate of noise and pollutant emission is100%;

Page 3

General and above equipment accidents will not occur due to the responsibility of the bidder's personnel;

No fire accident;

Misoperation will not occur;

Unplanned shutdown accidents caused by the responsibility of the bidder's personnel will not occur;

No environmental accidents;

Achieve safe production throughout the year.

Three. General rules for maintenance and repair

1. The equipment maintenance of flue gas desulfurization and denitrification system adheres to the principle of prevention first, spot inspection and repair, and quality first, so as to keep the equipment in good condition and ensure its stable and efficient operation.

Page 4

2. Strengthen technical management, earnestly implement the maintenance responsibility system, and implement a three-level acceptance system for maintenance.

3. In principle, the maintenance interval and occupation period of equipment in flue gas desulfurization and denitrification system depend on the boiler unit.

4. Full-time engineers should work out the annual maintenance plan of the equipment according to the operating technical conditions of the flue gas desulfurization and denitrification system equipment and the problems left over by the equipment in the previous year, with reference to the annual maintenance plan of the boiler unit.

5. Before the maintenance, the equipment of flue gas desulfurization and denitrification system should make the following preparations:

5. 1 According to the annual maintenance plan, technical conditions of equipment operation and equipment defects, the professional person in charge will conduct on-site inspection, deeply analyze all kinds of data, do necessary maintenance work and implement maintenance projects.

Page 5

5.2 Prepare the maintenance network diagram and organize relevant maintenance personnel to learn.

5.3 Organize relevant maintenance personnel to learn safety work procedures.

5.4 Work out the labor organization plan, coordinate the cooperation between maintenance teams and types of work, and cross-work of related maintenance teams.

5.5 Prepare the technical record and determine the spare parts drawings for measurement and inspection.

5.6 Organize the construction personnel to study and discuss the maintenance plan, project, schedule, measures and quality requirements, and master the relevant safety, quality and schedule requirements of maintenance.

Page 6

5.7 Prepare materials (including materials, spare parts, accessories, safety appliances, construction appliances, instruments and meters, etc.). ) and arrange the construction site.

Four, desulfurization system equipment maintenance process specification

4. 1 Maintenance of absorber body

4. 1. 1 Cleaning, inspection and maintenance of demister

1) cleaning from top to bottom, that is, upper part of secondary demister → lower part of secondary demister → upper part of primary demister → lower part of primary demister.

2) Check whether the demister is damaged and complete, and replace the damaged demister.

Page 7

3) Check whether the position of demister is placed on each support beam smoothly. If a single demister has any displacement, place it firmly on the support beam. The clips between demisters are complete.

4) Check whether the flushing water pipeline of demister is firmly fixed on the supporting beam, and whether the clips and fasteners are complete.

5) Check whether the flushing water pipe of demister is unobstructed and leaks.

6) Check whether the flushing water nozzle of demister is complete and the nozzle is unblocked.

4. 1.2 maintenance of nozzles and nozzles