Which projects in Qingdao need "site selection" approval before construction, and what is the process? Where is the acceptance unit?

Any project in Qingdao needs to be submitted to Qingdao Planning Bureau for "site selection" for approval before construction.

site selection and approval process:

1. 1 application forms for construction projects (sealed by the construction unit);

2. 1 copies of the application site description report (in order to specify the land scale and construction scale required by the construction project, a preliminary sketch of the construction plan is attached if necessary);

3. 1 current topographic maps (including planned road red lines, underground pipelines and survey marks);

4. 1 copies of the approval of the proposal for the construction project of the approved project, the consent of the approved project to carry out the preparatory work, and the filing documents;

5. For projects involving cultural relics, scenic spots, landscaping, rivers, transportation, etc., 1 written opinions of the corresponding departments shall be provided;

6. Construction projects that are independently located outside the scope of planned construction land and regional infrastructure projects that may have a significant impact on urban and rural planning shall also provide construction project site selection demonstration materials.

commitment time for examining and approving the site selection proposal: 7 working days (excluding reporting and publicity).