Jilin construction project cost management measures
Article 1 in order to strengthen the construction project cost management, standardize the construction project costing behavior, reasonable determination and effective control of construction project cost, and safeguard the legitimate rights and interests of all parties involved in the construction project, according to the relevant laws and regulations, combined with the actuality of the city, the formulation of these measures. Article 2 The city administrative area of the construction project cost and its supervision and management activities, the application of these measures. Transportation, water conservancy, electric power and other professional construction project cost management, the state, the province has other provisions, from its provisions. Article 3 The construction cost of construction works referred to in these measures, refers to the construction project from the project to completion, in accordance with the relevant provisions of the state and the province should be included in the construction project investment in the construction and installation costs, equipment and purchase of tools, construction costs, other costs, preparatory costs, taxes and interest on loans during the construction period, and other costs.

The measures referred to in the construction project costing, refers to the construction project cost determination and control activities. Article 4 the municipal construction administrative department is responsible for the supervision and management of the city's construction project costing activities, the specific work entrusted to the municipal construction project cost management organization.

County (city) construction administrative department is responsible for the supervision and management of construction project cost activities within the jurisdiction.

The financial department is responsible for the financial capital investment project budget, completion of the final (final) evaluation and review.

Construction project cost management organization in accordance with the law to perform their duties, the financial sector in accordance with the relevant provisions of the state and the province to be guaranteed. Article construction cost industry association shall strengthen industry self-discipline, play the role of industry services and coordination. It shall not monopolize the market in any form, impede fair competition, harm the legitimate rights and interests of consumers, non-member enterprises and other economic organizations, or the interests of the social public ****; it shall not restrict its members from carrying out legitimate business activities or participating in other social activities. Article 6 Construction project costing basis in accordance with the provisions of the "Jilin Province Construction Project Cost Management Measures".

In case of inconsistency in the understanding of the contractors and contractors on the basis of construction project costing, the municipal competent department for construction administration shall explain. Article 7 The municipal construction administrative department shall determine the one-time supplementary quota for construction works, collect, measure and summarize the price information of labor, materials, construction machinery benches, etc., and collect and measure the cost of quality and safety of construction works in accordance with the type of building structure, and report it to the provincial housing and urban-rural construction administrative department.

The price of one-time supplementary materials for construction projects shall be formulated by the municipal administrative department of construction and released in accordance with the regulations. Article 8 The costing of construction works mainly includes:

(1) preparation and examination of investment estimates, preliminary design estimates, construction drawing budgets, bills of quantities, tender bids, tender control prices, tender offers;

(2) agreement and adjustment of the contract price;

(3) project settlements and final accounts;

(4) determination of the construction works cost and control of other activities. Article 9 investment estimates, design estimates, construction budget, bill of quantities, tender bids, bidding control price, bidding price, completion settlement and final account of the completion of the project cost results shall be prepared in accordance with the relevant provisions of the state, provinces and municipalities.

Registered cost engineers and cost of construction personnel with the ability to prepare professional supporting units, can prepare and review the unit's cost of construction results; other units should be entrusted with the appropriate qualifications of the construction cost consulting firms to prepare and review the cost of construction results. Article 10 of the construction project costing using bill of quantities pricing or fixed price pricing.

Construction works using the pricing method, shall be set out in the bidding documents and agreed in the construction contract.

All the use of state-owned capital investment or state-owned capital investment in construction projects, must use the bill of quantities pricing. Article 11 the implementation of the bill of quantities of construction projects for bidding, the bidder shall be based on the national and provincial pricing basis and relevant provisions of the preparation of the tender control price, submitted to the city, county (city) construction administrative department for the record.

The bidding control price shall be announced at the time of bidding and provided to the bidders as an integral part of the bidding documents, and shall not be adjusted upward or downward.

The bidding control price and the winning bid shall not be lower than the announced quality and safety costs of the current construction project. Article XII of financial capital investment in construction projects list of quantities, bidding control price and the completion of the project settlement by the financial sector or the financial sector entrusted with the appropriate qualifications of the construction project cost consulting enterprises to prepare and review. Without review, shall not be used as the basis for the settlement of the project price. Article 13 The bidding price shall be based on the requirements of the bidding documents, in accordance with the national, provincial and municipal pricing basis issued by the city and the relevant provisions, and combined with the market situation and the enterprise's own situation independently determined, but shall not be lower than by the provincial housing and urban and rural construction of the administrative department of the construction works announced by the cost of the current construction project quality and safety prices, and shall not be higher than the bidding control price. Article 14 The construction project contractor and the contractor shall sign a written construction contract, and make a clear agreement on matters relating to the cost of construction works. Article 15 The construction contractor shall, within 7 working days from the date of signing the construction contract, report the contract and the bidding documents, the notice of award and other information to the municipal and county (municipal) departments in charge of construction administration for the record in accordance with the regulations.

The filing department shall complete the filing review within 7 working days from the date of receipt of the filing information. The filing department finds that the contract violates the laws and regulations, shall inform the contractor and the contractor to correct.

Filing of the contract changes in accordance with the law, the contractor shall, within 7 working days after the contract changes, to the original filing department for the record.