One, the name of the construction project: Dongjiadu 14 lots
Two, housing demolition and relocation of people: Tonghai Construction Co.
Three, housing demolition and relocation of the implementation of the unit: the South Bund Group of Shanghai property pre-development Co.
Four, the scope of demolition and relocation of the construction project:
Nanchang Street: Lane 30 (all), No. 32-38 (double), Lane 40 (all), No. 42-80 (double), Lane 82 (all), No. 84-98 (double)
South Nitpi Lane: No. 1-15 ( single)
China Road: No. 622-630 (double)
Dongjiadu Road: No. 388-448 (double), Lane 450 (all), No. 452-524 (double), Lane 526 (all), No. 528 554 (double)
Sugar Square Lane: No. 5-15 (single); Lane 37, No. 1 and No. 2
Dongjiangyin Street, No. 1-35 (single), Lane 37 (all), No. 39-107 (single)
Dongjiangyin Street, No. 1-35 (single), Lane 37 (all), Lane 39-107 (single) <
Sugar Square North Lane No. 2-20 (double)
West Jade Hook Lane (all), Sheep's Intestine Lane (all), Fugu Street (all)
V. Duration of the house demolition:
From September 29, 2007 to June 30, 2008
Sixth, the induction license number: 0001559 0001810 0001433 0001816 0001561, etc..
VII. If you have any objections to the Housing Demolition and Relocation License issued by the Bureau and published in this notice, you may apply for administrative reconsideration to the People's Government of the District or the Shanghai Municipal Administration of Housing, Land and Resources within 60 days, or you may file an administrative lawsuit to the People's Court of the District within three months from the date of the announcement of the notice. During the period of administrative reconsideration and litigation, the normal progress of demolition and relocation will not be stopped.
Eight, housing demolition and relocation of the site office address: the third floor of No. 109 Gomer Zhu Street.
Shanghai Huangpu District Housing and Land Management Bureau
September 29, 2007