The plan puts forward the main objectives: all newly started housing construction and municipal infrastructure projects (hereinafter referred to as "construction sites") in the city should be equipped with video monitoring systems; The construction site realizes "six hundred percent" of enclosure around the construction site, material stacking and covering, wet earthwork excavation, road hardening, vehicle cleaning in and out, and closed transportation of muck vehicles; "Three Guarantees" (neatness, orderliness and beautification) can be realized on both sides of the site exit 100m pavement.
Specific work measures are as follows:
(1) Strictly control the examination and approval of construction permits, and promote the use of online monitoring and video monitoring systems.
Video monitoring system should be installed on the construction site of newly started houses and municipal infrastructure projects, online monitoring equipment should be installed on the construction site of earthwork above city scale, and at least spherical cameras and license plate capture devices should be installed at the entrance and exit of transportation vehicles on the construction site of newly started decoration projects. Online monitoring and video monitoring systems are shared with relevant law enforcement departments. The project that has obtained the construction permit, started construction and has not installed the video monitoring system requires immediate shutdown and rectification, and can only be resumed after rectification is in place; Refuse to rectify, withdraw the construction permit.
(two) the establishment of special supervision system, consolidate the responsibility of dust prevention.
In the city's earth and stone works, housing demolition projects, key projects construction site, the implementation of dust control special inspectors. According to the principle of territorial management, the municipal, district housing and urban-rural development committees arrange special personnel to supervise the dust control on the construction site of the above projects. The Municipal Housing and Urban-Rural Development Committee is responsible for dust control and supervision of key projects such as the city sub-center, the new airport, the CBD core area and the Winter Olympics venues, and the District Housing and Urban-Rural Development Committee clearly assigns special personnel to supervise the dust control of other projects within its jurisdiction. From the date of publication, the District Housing and Urban-Rural Development Committee will arrange special personnel to conduct on-site inspections on the construction sites that have investigated and dealt with dust pollution violations, and urge the construction parties to earnestly fulfill the main responsibility of dust control.
(three) clear the scope of work stoppage, to ensure that the dust control standards.
1. Downtime: 20171.05 to 20 18.03 15.
2. Work stoppage scope: all areas in Dongcheng District, Xicheng District, Chaoyang District, Haidian District, Fengtai District and Shijingshan District; Tongzhou District, Daxing District, Fangshan District, Mentougou District, Yanqing District, Changping District, Huairou District, Miyun District, Pinggu District, Shunyi District, Yizhuang Economic and Technological Development Zone and built-up area.
3. Work stoppage content: stop all kinds of earthwork operations such as road engineering, water conservancy engineering and house demolition and construction.
For major livelihood projects and key projects involving earthwork, it is really impossible to stop work, the project construction unit shall apply, which belongs to the preliminary examination of the regional housing and urban-rural construction Committee, and declare to the municipal housing and urban-rural construction Committee in the name of the district government, and implement it after being approved by the municipal government.
(four) to strengthen law enforcement inspection, severely dealt with according to law.
1. During the heating season, the Municipal Commission of Housing and Urban-Rural Development scored the real estate development enterprises that refused to stop earthwork operations and house demolition projects according to law, and included them in the dynamic supervision and management of the qualifications of real estate development enterprises in Beijing, suspended the examination and approval of newly started projects, and suspended the bidding qualifications of supervision units and construction units in the Beijing construction market for six months.
2. During the period from the date of publication to 5438+05 June/kloc-0, if the dust control project is found to be unqualified, the bidding qualification of the construction enterprise of this project in Beijing construction market will be suspended for 30 days; 65438+1October 16 to165438+1October/October 15, found that the dust control project is not up to standard, suspended the bidding qualification of the project construction enterprise in Beijing construction market for 60 days; 165438+1October16 to 65438+February 15, found that the dust control project is not up to standard, and suspended the bidding qualification of the project construction enterprise in Beijing construction market for 90 days; During the period from 20 17 12 16 to 20 18 03 15, a project with substandard dust control was found, and the bidding qualification of the project construction enterprise in Beijing construction market was suspended for 6 months.
3. Within one month, it is found that three or more projects of the same construction enterprise are not up to standard, and all the projects under construction in this city are suspended for 30 days for rectification, and its bidding in Beijing construction market is suspended for 6 months according to law. For three consecutive months, it was found that the dust control of the same construction enterprise was not up to standard, and its bidding in Beijing construction market was suspended for six months.
4. Within one month, it is found that three or more projects of the same real estate development enterprise are not up to standard in dust control, and all their subordinate projects are suspended for rectification for 30 days. At the same time, the examination and approval procedures for newly started projects were stopped, and the municipal planning and land commission and other departments were requested to suspend their trading qualifications in the Beijing land market for three months.
5. If three or more projects are found to be unqualified in dust control within one month or the same supervision company fails in dust control for three consecutive months, its bidding qualification in Beijing construction market will be suspended for three months.
6. During the heating season, it is found that the dust control on the construction site of major livelihood projects and key projects that can carry out earthwork operations with the approval of the municipal government is not up to standard. In addition to the above penalties, the qualification for earthwork operation is cancelled.
7. See the Special Inspection (Acceptance) Table of Dust Control on Construction Site for the inspection standard of dust control on construction site (see annex). If the inspection score reaches 85 points (inclusive) or above, and the score of each participating item is not less than 50% of the total score, it is up to standard, and if it is lower than the above standard, it is not up to standard.