Construction engineering is a professional technical engineering, need professionals to do, if you do not understand the profession, in this help, a few words can not give you a clear ah.
You are currently in the construction phase, accurately said the construction phase of the foundation construction stage. The design institute will design the blueprints after review and approval, to the construction unit. After the construction unit and construction unit signed the construction contract, the construction unit began to enter the site for construction preparation, all ready to start formal construction. Construction needs to be written in advance of the construction program, that is, the operation of the specific process and the need for people, materials, machines, construction schedule and measures to ensure safety, quality and so on. Construction program needs to be approved by the owner and the supervisor, and then in accordance with the approved construction program for construction.
The following are the specific steps.General construction process of the case through the sky:
1. Apply for a miscellaneous license ...... Fence temporary water and electricity
2. apply for a building license - together with the architect to apply for
3. report the start of construction
4. site engineering sampling
5. send the results of the identification of the boundary map
6. Excavation (to find the site of the nearby open space stacked up on the site backfill in the future good)
must pay attention to the depth of the excavation (you can trouble the master of the Fanben level to help you) 1- 3- 3 years. Measurement) 1 - 3 days
7. pc concrete pounding 10cm (in order to later good construction sampling) 1 day
8. sampling and ground beam reinforcement binding (model sampling)
(utilities sewage pipe installation) 2 days
9. bottom of the concrete pounding (pouring) 1 day
10. ground beam modeling 1-2 days
11. > 11. floor beam concrete pounding 1 day
12. demolding --- foundation backfill gradation (water and electricity piping installation) (installation of septic tanks) 2 - 3 days
13. 1 floor floor floor column reinforcement version of the reinforcement binding (water and electricity piping) 2 - 3 days
14. reported foundation survey (please civil engineer, structural engineer to take a picture)
15. 1 floor floor floor Pounding 1 day
(reinforcing steel concrete into the field to get with the manufacturer of steel radiation-free certificate of chlorine ion analysis report)
16. Column hoop reinforcement binding (plumbing) (1 floor modeling) (Hawk frame assembly) 1 day
17. Wall column reinforcing steel binding modeling plumbing 7 days
18 Beam reinforcing steel binding modeling plumbing 3 days
19. 19. version of reinforcing bar binding plumbing 3 days
20. concrete pounding 1 day
1 --- 3 floors are the same (can be required to make the concrete test body compression and tensile reinforcement)
(site to be kept clean and labor safety) the Environmental Protection Agency and the labor safety will come to the inspection)
(renovation work)
1. external wall lifting lines, laying out samples, and painting.
2. interior wall hanging line trimming strip construction
(general mud work general contractors to specify the material with trimming strip and seaweed powder)
3. bricklaying (compartment door wooden frame installation)
4. water and electricity compartment wall piping
5. windows and doors door frame installation (waterproofing work after installation foaming agent)
6. indoor priming painting
7. Indoor and outdoor tile work (dismantle the scaffolding after the completion of the project)
8. Indoor water and electricity wiring
9. Indoor flooring, staircase, floor tiles
10. Installation of doors, windows, handrails
11. Architects)
Your current work first needs to look at the geological survey report to see if the water level underneath is high or low and if there is a need to lower the water level, then you need to take measurements to locate and place the line, and lastly, you need to drive the piles.