Article 1 Project Overview
1.1 Project Name:. 1.2 Project location:. 1.3 Project contents and practices (see: Project Budget Quotation Table and Construction Drawings for details). 1.4 Project contracting mode: Both parties agree to adopt the following _ _ _ _ _ contracting mode. (1) Party B contracts for labor and materials.
(2) Party B contracts for some materials, and Party A provides some materials (see Details of Decoration Materials Provided by Party A and Decoration Materials Provided by Party B for details);
(3) Party B's contractor and Party A's contractor (for details, please refer to the List of Decoration Materials Provided by Party A). 1.5 The project duration is _ _ _ _ calendar days, the commencement date is _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
1.6 contract price: please refer to the quotation sheet of project budget for the project cost of this contract. If there are any items added or deleted during the construction process, both parties shall increase or decrease the cost after negotiation and signature confirmation.
Article 2 Construction Drawings
Both parties agree that the construction drawings shall be provided in the following _ _ _ _ _ _ _ _ _ _ _:
(1) Party A shall design and provide the construction drawings in duplicate, one for Party A and one for Party B (see: Design Drawings for Decoration Project);
(2) Party A entrusts Party B to design the construction drawings in duplicate, one for Party A and one for Party B (for details, please refer to the design drawings of decoration engineering), and the design fee is _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Article 3 Party A shall
create conditions for Party B to enter the site for construction 3.1 days before the commencement of construction. Including: removing indoor furniture and furnishings or stacking and covering indoor furniture and furnishings that are not easy to move, on the principle of not affecting construction; If Party A fails to take necessary protective measures, resulting in loss of furniture and furnishings, Party A shall be responsible for it.
3.2 Be responsible for the application, approval and other procedures involved in the construction, and pay all the expenses of the property management office and approval
3.3 Be responsible for providing water and power needed for the construction;
3.4 Responsible for coordinating the relationship between Party B and its neighbors and the property management office;
3.5 If the indoor load-bearing structure is not removed, the non-load-bearing structure or equipment pipeline of the original building needs to be removed, and the relevant examination and approval procedures shall be handled by the relevant departments;
3.6 During the construction period, Party A still needs to use the site in part, and be responsible for the security and fire control of the construction site;
3.7 Participate in the inspection and supervision of project quality and construction progress, handle the acceptance, change registration procedures and other matters, and be responsible for the material entry and completion acceptance.
3.8 Provide self-purchased materials for construction on time, in good quality and in good quantity.
Article 4 Obligations of Party B
4.1 Appoint Party B as the site supervisor to be responsible for the performance of this contract; Organize the construction according to the requirements, ensure the quality and quantity, complete the construction tasks on schedule, and handle and solve all matters that Party B is responsible for.
4.2 During the construction, strictly implement the safe and civilized construction operation specifications, fire safety regulations, construction specifications and quality standards, and complete the project with good quality on schedule;
4.3 Strictly implement relevant regulations on construction site management, carry out safe and civilized construction in strict accordance with drawings or instructions, and make various quality inspections and construction records;
4.4 Protect the indoor furniture and furnishings in the original place to ensure the smooth flow of indoor water supply and drainage pipes; 4.5 Ensure the cleanliness of the construction site, and be responsible for cleaning the construction site after the project is completed.
4.6 Before the completion of the project is handed over to Party A, be responsible for protecting all the facilities and finished products on site.
Article 5 Engineering Changes
If there is a need to change the engineering project and construction method, both parties shall reach an agreement through consultation, and both parties shall sign for confirmation, and at the same time, adjust the related engineering cost and construction period (see the list of increase or decrease of decoration projects).
Article 6 Provision of Materials
6.1 The materials and equipment provided by Party A (see the list of decoration materials provided by Party A for details) shall meet the requirements of facilities, and Party A shall be responsible for the engineering losses caused by quality problems or specification differences. Party A shall notify Party B before the materials are delivered to the construction site, and both parties shall accept and handle the handover procedures; Party B shall be responsible for safekeeping after acceptance.
6.2 For the materials and equipment provided by Party B (see the list of decoration materials provided by Party B for details), Party B shall notify Party A before the materials are delivered to the construction site and accept Party A's inspection. If the quality does not meet the requirements or the specifications are different, it should be prohibited to use; Party B shall be responsible for the losses caused to the project if it has been used.
Article 7 Delay in construction period
7.1 If the completion date is delayed due to the following reasons, the construction period will be postponed accordingly upon confirmation by Party A; (1) Engineering quantity change and design change; (2) Force majeure;
(3) Other circumstances in which Party A agrees to postpone the construction period.
7.2 If the time limit for a project is affected by Party A's failure to complete the work it should be responsible for as agreed, the time limit for a project will be postponed; If the quality of the project is affected by the unqualified materials and equipment provided by Party A, the rework cost shall be borne by Party A, and the construction period shall be postponed.
7.3 If Party A fails to pay the project payment on schedule, the contract period will be postponed accordingly.
7.4 If the construction period is affected due to Party B's failure to start construction on schedule or stop work halfway for no reason, the construction period will not be postponed; If there are problems in the project quality due to Party B's reasons, the cost of rework shall be borne by Party B, and the construction period shall not be postponed.
Article 8 Method of payment of project funds
8.1 After the contract comes into effect, Party A will directly pay the project funds to Party B according to the following stipulations:
The first time: when signing this contract, Party A will pay% of the total amount (including the total amount of project funds and the amount of additional projects) determined by Party B's quotation, that is, RMB.
The second time: carpenters enter the site, and Party A pays% of the total amount (including the total project amount and the added project amount) determined in Party B's quotation, namely RMB.
for the third time: the fan-painted paint enters the site, and Party A pays% of the total amount (including the total project amount and the added project amount) determined in Party B's quotation, that is, RMB.
the fourth time: after the completion of the project and the completion acceptance, after the settlement, Party A will pay 5% of the total amount (including the total project amount and the added project amount) specified in Party B's quotation, namely RMB.
8.2 After the acceptance of the project, Party B shall propose the project settlement to Party A and send the relevant materials to Party A.. If Party A has no objection within days after receiving the information, it shall be deemed as agreement. Both parties shall fill in the project settlement form and sign it, and Party A shall settle the balance of the project with Party B when signing it.
8.3 After all the project funds are settled, Party B shall issue a formal unified receipt to Party A.. The project payment paid by Party A shall be subject to the receipt issued by the Finance Department of Party B and stamped with the special financial seal.
8.4 after the acceptance of this project, the warranty period is February from the date of signing by both parties.