according to the general contracting contract of construction project 1

Party A (the employer): _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Party B (the contractor): _ _ _ _ _ _ _ _ _ _. Party a will contract this project to party b by clearing the package, and the specific provisions are as follows:

1. Project name: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

2. Project content: _ _ _. For each extended day, Party A shall deduct _ _ _ _ _ _ _ _ _ _ yuan from the general contract payment of the project as liquidated damages. Delayed work or prolonged construction period caused by other reasons shall be settled by both parties through consultation.

4. General contract payment (RMB in words): _ _ _ _ _ _ _.

5. payment method: when party b starts construction, party a will pay party b _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ for construction; The balance _ _ _ _ _ _ _ _ shall be paid after the warranty expires.

6. Project quality: qualified, etc.

7. warranty period: _ _ _ _ _ _ _ years. Party B shall be responsible for all quality problems and all economic losses caused during the period.

8. Party B's responsibilities: Party B shall be responsible for all construction equipment; All the losses of raw materials and labor costs caused by unqualified construction or rework shall be borne by Party B, and Party A shall be compensated for the corresponding losses according to the specific circumstances.

9. Safety in production: Party B shall bear all problems and losses.

11. matters not covered in this contract shall be settled by both parties through negotiation.

11. this contract is made in duplicate, with each party holding one copy. It will take effect as of the date of signature and seal by both parties.

party a (official seal): _ _ _ _ _ _ _ party b (official seal): _ _ _ _ _ _

legal representative (signature): _ _ _ _ _ _ _ _ legal representative (signature): _ _ _ _ _ _ _ _ _. Capital Property Development Co., Ltd.

Party B: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

In order to ensure the commencement of the _ _ _ project on schedule and facilitate the entry of construction equipment and materials, Party A and Party B, in accordance with the Contract Law of the People's Republic of China and other relevant laws and regulations, At the same time, in order to clarify the rights, obligations and economic responsibilities of Party A and Party B in the construction process, the two parties reached the following agreements through consultation on the contracting of construction access roads in the first phase of the _ _ _ project:

1. General situation of the project

1. Project name: construction of access roads in the first phase of the _ _ _ _ project.

2. Work content: earthwork excavation for pavement surface cleaning, excavation of slag base, surface layer of water-stable layer, ditch excavation around pavement and maintenance of pavement for half a year.

2. Contract content:

According to the impression provided by Party A's engineering department, the first-phase construction service road in Mediterranean will be constructed, and the service road route will be determined by Party A's representative on site.

The construction method of access road is as follows:

① Remove the topsoil to a depth of 1.3m.

(2) the mountain slag is compacted with a thickness of 1.5m, the slope is placed in the middle of the service road, and the rainwater is discharged into the ditches on both sides of the service road.

(3) compaction of 1.1m thick surface layer of water-stable layer.

(4) the drainage ditch around the service road is excavated, and the phenomenon of road water accumulation is not allowed.

⑤ The maintenance period of the construction access road is 6 months. During the maintenance period, Party B is responsible for the maintenance free of charge.

III. Project price and payment method

1. Through negotiation between Party A and Party B, the construction access road is contracted at a fixed comprehensive unit price, and the comprehensive lump sum price is 59.11 yuan/m3. Settlement work quantity = volume of mountain slag base+volume of water stabilized layer.

the unit price of this contract has included all the expenses needed to complete the contracted contents of this project, including labor costs, materials costs, machinery costs, management fees, profits, taxes, and all the measures taken in the construction.

2. This project is a lump sum contract at the unit price. Once confirmed by both parties, no adjustment will be made (not affected by weather, market price, site construction conditions and other factors).

3. After Party B has completed all its projects, Party A will handle the project settlement according to the quantities determined by both parties.

4. Party A shall pay 95% of the project price to Party B within 11 days after the service road construction is completely completed and the project quality is confirmed by Party A in writing. The remaining 5% is used as the project quality warranty, and the warranty period is half a year. Party A shall pay the remaining amount to Party B in one lump sum within 11 days after the expiration of the warranty period (the warranty amount does not include interest).

iv. construction period requirements:

the calendar construction period of this contract is 25 days. Party A has the right to adjust the construction period in time according to the progress of the project. In case of delay caused by Party A, the construction period will be postponed.

v. Construction safety and management:

1. In order to strengthen site management, the person in charge of Party B's construction should keep in touch with Party A at the site at any time.

2. Party B shall strengthen the safety and civilized construction education of its construction personnel, consciously abide by the relevant regulations of the local government, consciously obey Party A's regulations on on-site safety and civilized construction, put an end to safety accidents and maintain the image of on-site civilized construction. In case of the above-mentioned events, Party B shall negotiate with the responsible party to solve them, and bear the economic responsibilities arising therefrom.

3. In case of any safety accident during Party B's construction, Party B shall bear the responsibility, which has nothing to do with Party A..

4. Party B shall be responsible for coordinating and handling the relationship with the villagers in the village during the project construction, and shall not have disputes due to other villagers' failure to undertake the construction of this service road project, which will cause the project to stop or delay. In case of the above situation, Party A has the right to terminate this contract and claim 11,111 yuan from Party B..

VI. Technical requirements for construction:

1. Party B shall notify Party A's engineers for inspection and acceptance after the self-inspection of each working procedure is completed, and the construction of the next working procedure can only be carried out after Party A's engineers pass the inspection.

2. Party B shall unconditionally rework and improve the unqualified parts detected in each process during the construction, and bear all its expenses.

VII. Other matters not covered shall be settled by both parties through negotiation.

VIII. This contract shall come into effect upon signature and seal, and shall become invalid upon completion of the contract. This contract is made in quadruplicate, three for Party A and one for Party B, all of which have the same legal effect.

attachment to the contract: construction access road method for _ _ _ _ _ _ _

Party A: _ _ _ Invest in Real Estate Development Co., Ltd. Party B: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Representative of Party A: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _. Words: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ Tel: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Date: _ _ _ _. (hereinafter referred to as Party B):

In order to fully perform the construction contract, strengthen the management of the project, improve the economic benefits of the enterprise, and increase the income of the project manager and project-related personnel, Party A has decided to implement the responsibility contract system for the management of the second phase of the Nanjing International (Jinmao) Plaza project. Through the comprehensive evaluation of Party B's professional qualification, construction performance, management ability and risk mortgage, Party B is determined as the contractor of the project. Based on the principles of openness, fairness, equality, voluntariness, honesty and credibility, the two parties have reached the following agreements:

1. Contract indicators

1. Cost indicators: see the annex (raw material expenses are not included in the cost unit price, and the specific workload is subject to actual completion).

2. quality index: the first acceptance rate is 111%.

3. Safety index: No serious injury or death accident occurred.

4. progress indicator: the construction task of the diaphragm wall will be completed from April 26th, 21XX to February 5th, 21XX.

5. Other agreements:

II. Reward standard

Party B will be given a yuan reward for completing the cost index; Meta-reward for completing quality indicators; Meta-reward for completing safety indicators; Complete the progress indicators given. Yuan reward.

III. Responsibilities and Authority of Party A

1. Responsibilities of Party A

(1) Responsible for providing the necessary start-up funds, production equipment and machines for the project; Organize the disclosure of the construction contract and the examination and approval of the construction organization plan, as well as the connection between the construction unit and local social and environmental resources; Submit the construction design drawing sets and corresponding construction technical data to Party B before commencement.

(2) according to the project requirements and Party B's request, sign labor subcontracting contracts, materials and equipment purchase contracts, mechanical materials leasing contracts, etc.

(3) assist party b in organizing the completion acceptance, final accounts and evaluation declaration;

(4) Be responsible for organizing the examination and audit during and at the end of project management; Cash the economic benefits (including salary) of the project contractor or implement economic compensation punishment;

(5) Assist Party B to select project managers, set up a project management department and allocate other production factors;

2. Party A's authority

(1) has the right to guide, inspect, supervise and coordinate Party B's construction management; Irregular information on project progress, quality, project inspection (test) and the use of project funds. Conduct supervision and inspection.

(2) Have the right to subcontract the project to a professional company unless specified by the construction unit;

(3) if party b violates the law, fails to implement the national standards, fails to manage the construction according to the specifications, or violates the relevant regulations of party a, party a has the right to make corrections, order the work to stop for rectification, impose economic penalties, terminate the contract, and adjust the contractor.

(4) Review the construction organization design, project progress plan and completed engineering quantity report prepared by Party B..

IV. Responsibilities and Authority of Party B

1. Responsibilities of Party B

(1) Implement project management on behalf of enterprises, abide by national laws and regulations, implement mandatory standards, implement relevant enterprise management systems, and actively safeguard the legitimate rights and interests of enterprises; Implement the whole process and comprehensive management of the construction project from the preparation for commencement to the completion acceptance;

(2) Organize the preparation of project management implementation plan according to national standards;

(3) Organize the allocation and management of production factors in the construction site;

(4) to organize the formulation and implementation of various management systems of the project management department;

(5) Be responsible for working contact and coordination with the construction unit, supervision unit, relevant departments of local government and enterprise management within the scope authorized by the enterprise, and be responsible for the management of labor subcontracting and cooperative units;

(6) solve the' problems in the construction site and project management department, and find and handle emergencies;

(7) Be responsible for the completion acceptance and settlement, and provide and prepare relevant technical and economic data;

(8) assist enterprises in project inspection, appraisal, evaluation and award declaration;

(9) Responsible for the management and education of employees, and the construction of corporate culture and spiritual civilization;

(11) Accept the inspection and supervision of the superior and local construction administrative departments, earnestly implement the rectification opinions, and improve the management level; Accept the inspection, supervision and assessment audit of the enterprise;

(11) Deal with the aftermath of the project and the quality warranty service of the project, and complete the clearing and handover of creditor's rights and debts such as the project payment;

(12) submit the completion of various indicators according to Party A's requirements;

(13) Pay all kinds of insurance and other expenses of employees in full and on time according to the regulations of the company; In case of work-related injury accident, the part of insufficient insurance premium payment shall be shared by Party A and Party B at the ratio of 3: 7; If Party B fails to pay the insurance premium, Party B shall bear the full amount of work-related accidents of employees.

(14) Responsible for raising funds needed for project operation and controlling other risks;

(15) expenses, fines, liquidated damages and economic losses caused by quality, construction period, safety and civilized construction and various violations shall be borne by party B .. In case of arbitration or litigation, after Party A bears the expenses, Party A has the right to recover all expenses including legal fees and attorney fees from Party B..

2. Party B's authority

(1) Implement project management on behalf of Party A, fully perform the construction contract, abide by national laws and regulations, and implement mandatory standards and norms and Party A's relevant management system;

(2) according to the authorization of party a, the project management department is established, and the project management department will work comprehensively; . The seal of Party A's Project Department can only be used for the signing of materials procurement contracts, the sending and receiving of engineering documents and the production of letters related to this project, and it shall not be used for the settlement and borrowing of funds such as materials, project funds and wages of migrant workers, or for activities unrelated to this project, or for changing the provisions of the owner's contract, and Party B shall not make promises to others without authorization in any name of the project; Otherwise; Party B shall be deemed to have breached the contract, and shall bear all responsibilities and economic losses caused thereby.

(3) determine the organizational structure of the project management department, and report the team members to Party A for examination and approval, and then submit them to the owner, supervision unit and relevant management departments for the record. Without the consent of Party A, the team members shall not be changed at will, otherwise it will be regarded as Party B's breach of contract;

(4) Party B has the right to choose management personnel and production workers, and the construction personnel hired by Party B shall have corresponding qualifications or qualifications, and their identity documents and certificates shall be copied for future reference; Otherwise, Party B is deemed to have breached the contract. Managers in a few key positions can be hired according to the prescribed procedures; Determine the responsibilities and authority of management personnel, and organize assessment, rewards and punishments;

(5) Party B has the right to select a labor service team from the list of qualified subcontractors determined by Party A, but it must be reported to the Employer for the record; Party B has no right to subcontract or subcontract this contract project, otherwise Party A has the right to terminate this contract, and Party A has the right to require Party B to bear 5% of the total contract price as penalty.

(6) organize material procurement by itself within the scope authorized by Party A;

(7) determine the use of project funds according to the company's fund management measures;

(8) determine the salary distribution of personnel in the project management department according to the principle of fixed income and priority of efficiency;

(9) according to the authorization of the enterprise, coordinate and handle the internal and external matters related to the project, focusing on tracking the follow-up projects and participating in the business activities of other projects.

V. Management of project payment, receipt and use: