1. Before construction, construction technicians and lofting personnel shall conduct field measurement and lofting, mark the position of decorations with ink lines on the site according to the design drawings, and check whether there is any error between the site and the drawings before construction.
2, on each floor layout +50cm elevation line, and the chalk line pops up on the wall, as the standard benchmark of interior decoration, the measurement error is plus or minus 3 mm. ..
3. The setting-out point on the ground is confirmed by steel nails, and the top surface of the wall is marked with paint.
Second, the electrical construction
1, indoor power distribution
(1) The rated voltage of the conductor used shall be greater than the working voltage of the line, and the insulation strength of the conductor shall conform to the laying mode and environment of the line. The cross-sectional area of the conductor should meet the requirements of power supply quality and mechanical strength.
(2) When laying wires, try to avoid joints. If connection is necessary, try crimping or welding.
(3) The connection and branching of wires shall not be affected by mechanical actions. Wires should be firmly connected to equipment terminals.
(4) Wires or cables passing through pipelines should not be connected under any circumstances. If you must connect, you can put it in the junction box, lamp holder box and switch box.
(5) All kinds of exposed wiring should be horizontal and vertical.
(6) Protective tubes should be added when the conductor goes through the wall, and both ends of the tube should be no less than 10mm, which will affect the appearance if it is too long.
(7) When the wires cross and approach each other, a plastic pipe should be put on each wire and the casing should be fixed to prevent short circuit.
(8) A certain distance should be kept between indoor wires and other pipes, not less than100 mm. ..
2, the construction procedure
(1) According to the plan and details, determine the location of electrical installation, the laying path of wires and the location of wires passing through walls and floors.
(2) Decorate insulating brackets, fixtures, brackets or protective tubes, etc.
(3) laying wires.
(4) Install lamps, electrical equipment and components.
(5) Test the wire insulation and connect it.
(6) Check and test the power supply.
3. Installation of lamps and lanterns
(1) Before installing the lamps, check whether the fittings are complete, whether the appearance is damaged, deformed and the coating falls off, and test whether the insulation is good.
(2) The installation position and height of lamps and lanterns should meet the design requirements.
(3) Lamps and lanterns with the weight below 1kg can be directly hoisted with flexible wires; Lamps with a weight above 1kg should be lifted by a chain hoist; Lamps weighing more than 3 kg should be fixed on embedded hooks or bolts.
(4) There shall be no less than two bolts for fixing lamps and lanterns.
(5) When lamps and lanterns are installed in flammable parts, fire prevention treatment should be done well, and fire-retardant coatings should be painted on surrounding structures.
(6) When there are multiple groups of lamps and lanterns in the same room, they should be arranged neatly and meet the design requirements, and the light lines should be unified. If necessary, a size adjustment plate should be added.
4, socket installation
(1) When sockets in the same place are installed in rows, the height difference should not be greater than 1mm, and the height difference should not be greater than 5mm when installed separately.
(2) The height of the concealed socket from the ground is 0.3m
(3) When wiring the socket, the wire color separation should be unified and correct. The right pole of the socket is connected to the phase line, the left pole is connected to the zero line, and the ground wire is on it.
5, lighting distribution box installation should comply with the design requirements.
(1) The insulating tube shall be arranged on the lead-out surface of the conductor.
(2) The vertical deviation of the distribution box should not be less than 1.5/ 1000. The edges around the panel of concealed distribution box should be close to the wall.
(3) Each cycle has a sign indicating the name and purpose of the cycle. If different types or different voltage levels of power distribution equipment are installed in the same box, there should be obvious difference signs.
(4) The installation height of the distribution box should be between 1.2m and 1.5m, and the working zero line and protective grounding line in the box should be strictly distinguished.
(5) The internal wiring section of the distribution box should meet the specification requirements.
Three, light steel keel gypsum board ceiling
1, the ceiling base must have sufficient strength. Clear the ceiling and surrounding obstacles. Concealed works such as ventilation, water and electricity pipelines in the ceiling should be installed, and the fire protection system should be installed and pressure tested. The ceiling keel shall not be thrown or collided during installation and transportation. Keels should be laid flat to prevent deformation. The surface should be smooth, the edges should be neat and the color should be uniform.
2, according to the ceiling design elevation, along the wall around the elastic line, as the standard line of ceiling installation, its horizontal allowable deviation is within plus or minus 5 mm, and determine the installation position of the keel along the border, and fix the keel along the border on the wall around.
3. Draw the position line at the top of the suspender on the ceiling, find out the symmetrical reticle on the ceiling, draw several intersecting lines according to the frame size of the ceiling keel, and fix the suspender firmly on the ceiling with internal expansion bolts. The suspender adopts No.8 full bolt suspender, and the spacing between suspenders is not more than 1200mm. When the derrick meets the top equipment and pipeline, the position of the lifting point should be adjusted and the derrick should be added.
4. Fix the hanger below the derrick, and pull the wire according to the height of the side keel, and re-check and adjust the height of the derrick to a suitable position.
5. Put one end of the load-bearing keel on the side keel, hang the load-bearing keel with a hanger and fix it with screws. Load-bearing keel connection, with the main keel connector connection extension. The distance between main load-bearing keels is generally 900- 1200mm, and the middle part should be arched, and the arch height should not be less than1/200mm of the short-side span of the room. After the main keel is installed, its position and elevation should be corrected in time. Light lamps should be hung on the main keel or additional keel, while heavy lamps or other decorative parts should not be connected with the ceiling keel, and hooks should be set separately.
6. Fully correct the position and levelness of primary and secondary keels, and tighten and clamp all hangers and fittings after correction. Connectors shall be installed in a staggered manner.
7, all kinds of pipeline installation, shall not destroy the keel system, or directly on the keel erection. After the pipeline is accepted, the cladding can be installed.
8. There should be no bubbles, peeling, cracks, pollution and incomplete patterns on the panel.
9. Gypsum board should be installed along one end of the ceiling. The long side of gypsum board should be installed vertically with the facing keel. The short sides of gypsum board shall be staggered, and flat-fell seam shall not be formed.
10, use gypsum board tapping screws to fix the board face and keel; Self-tapping screws should be driven by electric screw gun at one time, and the nail head should be embedded in gypsum board by 0.5 mm- 1 mm, so as not to damage the gypsum on the paper surface. Self-tapping screws shall be installed along the edge of cladding, with a distance of 10 mm- 15 mm, a distance of 15 mm-20 mm and a screw spacing of150 mm-170 mm. The connection between gypsum board and keel shall be fixed from the middle of the board to the periphery. Paint the nail head with antirust paint and smooth it with caulking paste.
1 1. Joint treatment: clean board joints and remove sundries. Fill the joint of the plate with caulking paste, and compact it. The thickness is equal to that of the plate, and it shall not be higher. After curing, apply caulking paste on both sides of the joint, each side is not less than 50 mm, stick the joint tape on the joint, scrape it with a scraper and compact it, and there shall be no air bubbles between the tape and caulking paste. Make the center line of the paper tape coincide with the center line of the board seam, and the width of the paper tape on both sides of the seam is equal. Scrape the sealing paste pressed from the edge of the paper tape on the paper tape, smooth it and compact it, so that the paper tape is buried in the sealing putty.
Four, light steel keel gypsum board partition
1. Pop up the vertical line connecting the partition wall and the wall according to the drawing requirements; Mark the installation positions of upper and lower keels, and mark the positions of doors and windows.
2. Install keels along the ground, along the roof and along the edge: the horizontal keels are connected with the roof and the ground of the building, and the vertical keels are connected with the walls and columns, which are fixed by metal expansion riveting bolts. The distance between the fixed points is 600 mm Under normal circumstances, a long rubber strip sealing strip or sealant should be pasted on both sides of the contact surface between the light steel keel and the surface of the building matrix for waterproof and sound insulation.
3. Installation of vertical keel: the length of vertical keel is 5mm shorter than the clear height of partition wall, and the spacing is 400mm. When installing the vertical keel, it should be arranged from one end of the partition wall, and the doors and windows should be expanded from the doors and windows to both sides. When the last vertical keel spacing along the wall and column is greater than the keel spacing specified in the design, vertical keel must be added. Push the vertical keel with pre-cut length between the top keel and the ground keel, place the flange in the direction of the cover panel and fix it with self-tapping screws. When installing, pay attention to the height of each keel through hole must be on the same horizontal line. The vertical keel at the entrance of doors and windows should be reinforced by double layers.
4. Installation of the through keel: the spacing of the cross brace keel is 1500mm, and the through keel passes through the through holes on each vertical keel. When extending, connectors should be used to install Cato on the opening face of vertical keel, so that it can be locked with the cross brace keel, and corner codes should be added on the back of vertical keel and fixed as required.
5. Installation of transverse brace keel: When the height of partition skeleton exceeds 3m, transverse keel should be added and fixed with Cato and corner brace and vertical keel.
6. Installation of gypsum board: Before installation, strengthening measures should be taken for pipe fittings and related wall-attached equipment in the embedded partition wall. Gypsum board is installed on one side of the skeleton, and gypsum board is vertically installed as a partition wall. The long side seam falls on the vertical keel, and the gypsum boards on both sides of the keel should be staggered. Use the whole plate. If docking is necessary, it should be tight, but it should not be forced into place. After in place, the upper and lower ends and the vertical edge should have a 3mm gap between the upper and lower floor surface and the wall cylinder, and the gap between the top and the ground should be filled with caulking paste before paving, and the caulking paste should be squeezed to make it closely connected with the light steel keel. The screws should sink into the board surface by 0.5 mm- 1 mm to avoid damaging the paper surface and exposing gypsum. Self-tapping screws should be installed along the seam edge, and the distance between the self-tapping screws and the edge of the plate should be 10 mm- 15 mm, and the distance between the screws should not be greater than 200mm on all sides and 300mm in the middle. After installing gypsum board on one side of the partition wall, fix the conduit required on the wall surface on the keel as designed. The junction box can pass through the through hole on the keel, and the installation of the junction box can open a hole in the wall. At most two junction box holes can be opened between every two vertical keels on the same wall, and the distance between the holes and the vertical keels is150 mm; The openings of the two junction boxes must be staggered up and down, and the distance between the vertical direction and the horizontal direction shall not be less than 300 mm. If the distribution box is installed in the wall, the auxiliary keel can be installed horizontally between two vertical keels, and the keels are connected and fixed with core-pulling rivets. Electric welding is not allowed.
7. After the electrical installation is completed, sound insulation rock wool board can be installed if required by the design. Rock wool sound insulation boards are evenly distributed in the inner cavity of light steel keel, and the rock wool boards are fixed with hanging nails to avoid falling off. Then install gypsum board on the other side of the skeleton. The joints of the board cannot fall on the same keel as the opposite joints, and must be staggered.
8. Nail head, joint and corner treatment: same as gypsum board ceiling treatment process.
Five, stone veneer
1. Carry out base treatment: chamfer and level the bonded base to ensure that the board can be in place and the protruding parts are chiseled away. And remove the residual floating ash on the wall.
2. Hanging vertically, finding a square, and finding rules: According to the design requirements, the outer contour of the decorative panel is led out from the wall, and the height of the large surface and the left and right ends is marked with high test pieces, and the bonding control line is determined by pulling wires.
3. Trial arrangement and material selection: according to the overall size and stone specifications, the joint width is left, and the brick arrangement scheme is determined.
4, wipe the bottom mortar. Wet the base with water in advance, brush the bonding interface agent and plain cement after drying slightly, and use the brush to make the base; The bottom ash is made of 1:3 cement mortar with a thickness of about 12mm, which is operated on both sides. The first time is about 5mm, and the second time is about 7 mm. After the bottom ash is compacted and leveled, the bottom ash surface is scraped.
5, inlaid with plates. After the primer is solidified, it can be divided into blocks, and then the wet block is smeared with 2 mm-3 mm thick cement slurry mixed with dry powder binder for solidification, tapped with a mallet and leveled with a guide rule.
6. Surface joint and seam wiping. After bonding, the surface mortar shall be wiped off with clear water in time, and jointing shall be carried out after 24-48 hours.
Six, wall tile facing
1, grass-roots treatment: clean up the mortar debris on the wall and chisel out the obvious prominent parts. The bottom mortar should be absolutely flat, and the angle of Yin and Yang should be absolutely square. Before laying bricks, the surface of the base should be watered and wetted, and then leveled with cement mortar.
2. Elastic line: according to the design requirements of the drawings, according to the layout of the doorway and the vertical and horizontal decorative lines.
3. Priming: Before tiling, the surface of the base should be watered and wetted, and then the cement mortar leveling layer should be painted. The bottom mortar should be absolutely flat, and the angle of Yin and Yang should be absolutely square.
4, tile paste: according to the design elevation pop-up horizontal and vertical lines, and then according to the design requirements and tile specifications to determine the width of the frame joint. Bricks are paved with plain cement slurry from bottom to top, which can be completed at one time. Brush cement mortar on the wet bottom layer before sticking the adhesive layer. At the same time, spread the brick on the wooden pad, coat it with a thin layer of plain cement slurry, and then paste it. After the unit brick is paved stably, the bending and torsion gap is adjusted with a metal dial before the cement mortar solidifies, so that the spacing is even. After all bonding layers are laid and finally set, caulking shall be done with thick white cement slurry, and the joints shall be wiped hard to make them full and dense.
Seven, coating engineering
1. Basic treatment: After the surface is cleaned, the wall shall be leveled with putty. After the putty is dry, first level the excess putty with a shovel, and then polish it with 1 sandpaper. Paper tape for panel stitching. Brush the nail head with antirust paint and smooth it with gypsum putty. Filled joint paste for internal corners.
2. Plate surface coating process
(1) Full scraping putty and polishing: After the large gaps in the indoor painting surface are filled up, full scraping latex paint putty with batch embedding tools, and all small sand holes and shrinkage cracks shall be fully scraped, which shall be subject to compactness, smoothness and neat edges. Scrape horizontally one by one along the wall, the thinner the better, no leakage, no seams, no fouling of doors, windows and other surfaces. Apply putty twice in turn. After the putty is completely dried, wrap it on a flat sand rack with 1 sandpaper, and smooth the putty paint and uneven places. Pay attention to the uniform stress and protect the edges and corners. Clean it up with a broom after grinding.
(2) Brushing: Before brushing, the surface of the base must be cleaned and the floating ash must be wiped off. The order of painting should be from top to bottom, from left to right, first horizontal and then vertical, then edges and corners, then facets and then facets. There shall be no residual paint in the internal corner and no wrapping in the external corner.
(3) Re-putty: After the paint is completely dried, it should generally be inspected. If there is any defect, it should be repaired locally.
(4) Polishing: After the patching putty is completely dried, fine sandpaper should be used to polish the surface of the coating film smoothly, and the force should be light and even, and the coating film should not be worn through.
(5) The second coating.
Eight, pasting project
1, grass-roots treatment: the grass-roots wall should be flat, the obvious unevenness should be repaired flat, and the smaller pits and stains should be filled flat with putty. The wall should be kept dry to prevent mildew after installation. The wall should be clean, free of dust and floating ash. And paint a layer of primer on the wall.
2, elastic line: horizontal and vertical, considering the symmetry and uniformity of wallpaper, the format is symmetrical. The first piece of paper on each wall should be arranged straight as a guide line, and the second piece should be pasted from top to bottom in turn.
3. Cutting: The wallpaper should be planned as a whole according to the material specifications and the wall size, and numbered in sequence. The cutting length of wallpaper should be slightly longer than the size of the pasted part100 mm-150 mm. ..
4. Paper pasting: Choose a good location and hang a vertical line to ensure that the first wallpaper is pasted vertically and evenly. Adhesive should be prepared as needed, limited to the amount of the day. Hydroxymethyl cellulose is first dissolved in water for about 10 hour, then filtered with fine pore sand to remove impurities, and then mixed with other materials and stirred evenly. The thickness of the glue solution is convenient for installation. Brush the glue evenly on the wall with a combination brush, then gradually put down the cut wallpaper into a roll from top to bottom according to the requirements of flowers, smooth the wallpaper with a wet towel and stick it firmly, and cut off the redundant paper materials from top to bottom with a blade. The installation can be carried out by grinding method. Two adjacent pieces are at the flat-fell seam, and the last piece is about 3cm higher than the previous one. Then, use a ruler and a cutter to cut through the double-layer wallpaper in the middle of the overlapping range, and tear off the two cut wallpapers. For wallpaper with patterns, in order to ensure the integrity and continuity of the patterns, the splicing method can be adopted when mounting, and the patterns can be spliced first and then spliced. After the patterns match up and down, scrape the glue obliquely with a scraper to make the flat-fell seam dense, and then scrape out the excess glue in the flat-fell seam and wipe it clean. For wallpaper with important overlap and matching, it should be mounted and matched first. After the glue dries to a certain extent, the remaining edges should be cut off, and then leveled and compacted. Use the knife evenly. Cut straight at one time to avoid knife marks. When mounting and collage, the internal corners should overlap, and the external corners should not have seams, so the corners should be compacted. Use the whole wallpaper in the obvious place on the wall, and stick one less wallpaper in the dark or inconspicuous place. The connection with the hanging mirror line, skirting line, face sticking and other parts should be close, and there can be no gaps. Then evenly drive the glue from top to bottom to discharge bubbles, and wipe off the excess glue when using.
5. Finishing: If local nonconformities are found, remedial measures shall be taken in time. If wrinkles appear on the paper, wipe it with a wet towel before drying it, flatten it with your hands, and then flatten it with a rubber roller. If the wallpaper is dry, it needs to be reworked and pasted again.
In short, the basic process of hotel decoration has the above eight items.