Current location - Recipe Complete Network - Catering franchise - Equipment installation schedule management
Equipment installation schedule management
Equipment installation schedule management

According to the design and technical quality requirements of equipment engineering, the installation process of equipment engineering is a working process in which all kinds of equipment and parts are installed and connected on site to form an overall operation with expected functions. I have compiled an article for you about the management of equipment installation schedule. Let's see:

1, progress management of equipment installation process

In order to ensure that the equipment installation schedule can meet the requirements of the overall schedule of equipment engineering, it is necessary to prepare the equipment installation schedule and control its implementation. The main contents of schedule management of equipment supervision engineer during equipment installation include the following aspects.

(a) to assist the owner's work

(1) Organize bidding for equipment installation and assist the owner to determine the installation and construction unit;

(2) Assist the owner to determine the time limit for equipment installation according to the total schedule of equipment engineering;

(3) According to the entrustment of the owner, assist the owner to handle relevant engineering construction procedures (construction permit, quality supervision, etc.). ).

(2) Documents to be prepared

(1) Prepare the progress plan of equipment installation supervision;

(2) Prepare detailed rules for the management and supervision of equipment installation progress;

(3) When the equipment engineering is contracted in parallel and there are multiple installation contractors on site, the equipment engineering installation master schedule is prepared according to the equipment engineering master schedule;

④ Prepare the monthly report of equipment engineering supervision and the summary of installation engineering supervision.

(3) Audit work

(1) Review the equipment installation schedule prepared by the equipment installation unit. Mainly review whether the installation time limit target meets the time constraint requirements of the total equipment project time limit and each milestone, as well as the coordination of equipment installation labor plan, installation machine use plan, material plan and civil engineering plan, equipment supply plan, etc.

(2) Review the progress report submitted by the installation unit.

③ Review the schedule adjustment plan submitted by the installation unit.

(4) Review the contractor's claim report.

⑤ Review progress payment, change price, payment application for completion settlement, completion report, etc.

(4) Control and coordination.

(1) Check the installation progress of key lines and key working procedures at any time, and make progress records;

(2) Participate in the inspection and test as stipulated in the contract or at the time agreed by both parties;

(3) If the actual installation progress is found to be deviated from the planned progress (ahead of schedule or behind schedule), the possible impact of these deviations should be analyzed, and the installation unit can be required to speed up the construction, slow down the construction or adjust the progress when necessary to meet the needs of equipment project progress management;

(4) If the installation progress is affected because the equipment supplier fails to deliver the equipment as planned or the design unit fails to submit the design documents as planned, it shall urge the installation unit to deliver the equipment and drawings in time or require the installation unit to adjust the progress in order to achieve the time limit for the equipment project;

⑤ Preside over the on-site coordination meeting, coordinate the relationship between the owner, the design unit, the installation unit and the equipment supply and manufacturing unit, and handle all kinds of problems, claims or disputes in the process of equipment installation in a timely and fair manner.

2, equipment debugging schedule management

The process of equipment debugging can be divided into three stages: single equipment debugging, trial operation of the whole equipment system and performance guarantee testing.

Different stages have different purposes, different scopes and different requirements. At the same time, the debugging of the equipment has obvious logic, and the next stage can only be entered after the debugging of the previous stage is completed, otherwise it may cause losses.

;