Construction organization design of Wuhan six-story brick-concrete structure building project?

What is the specific content of the construction organization design of Wuhan six-story brick-concrete structure building project? The following Zhongda Consulting will answer your questions.

general description of the first chapter

purpose of the first section

on the basis of carefully reviewing the construction drawings and understanding of the project site, our company has carried out various relevant policies of the state and Hubei Province, referred to various technical standards, and combined with the actual situation of the project, and conducted full research and discussion on the construction organization design outline compiled by our company, so as to prepare the construction scheme of this project. This construction scheme reflects the overall conception and deployment of this project, and provides a complete programmatic technical guidance document for the construction of this project to guide the construction and management of this project scientifically. If our company is lucky enough to construct this project, we will follow our company's technical management procedures, design and construct in strict accordance with this construction organization, and ensure the completion of the construction task of this project with high quality, high speed, safety, low consumption and civilization.

compilation basis of the second section

compilation basis of this construction organization design

1. Construction blueprint of Wuhan XX Architectural Design Institute.

2. Relevant geological and geotechnical data.

3. Current national technical standards, construction and acceptance specifications, engineering quality evaluation standards and operating procedures; Sub-process construction standard.

4. the company's enterprise standards and quality manual.

5. Implement the international quality system standard ISO9112 and the standards of Quality Management and Quality Assurance.

6. Regulations on Construction Site Management of Construction Projects and Regulations on Quality Management promulgated by the Ministry of Construction.

7. Wuhan Municipal People's Government's local laws and regulations on building management, market management and environmental protection.

Chapter II Project Overview

Section I Project Overview

This project is located in Hanyang District, Wuhan City, with a building area of 4,922 ㎡, a six-story brick-concrete structure with a height of 2.85 M, an indoor-outdoor height difference of 1.45M, a length of 51.31M and a width of 17.61M m. The seismic grade of this project is six degrees, and the structural safety grade is two, so it is seismic.

1. Structural engineering

The cushion of this project is C11, the foundation is manually dug pile, the concrete is C21, the foundation beam, column and beam slab are C25, and the floor is prestressed C31 hollow slab. Masonry works: the elevation below 1.111 is MU15 lime-sand brick, and the elevation above 1.111 is M11 cement mortar, and the first to fourth floors are MU11 lime-sand masonry works. More than four layers of MU11 lime-sand bricks, M5 mixed mortar, reinforced with steel bars; The roof is an integral cast-in-place slab, and the steel bars used in the reinforced concrete structure are Grade I and II steel bars; Welding and binding connection shall be preferred for steel bar connection.

2. Decoration project

The exterior wall of this project is made of exterior wall tiles and exterior wall coatings, while the interior wall, kitchen and bathroom tiles and others are painted with white latex paint with mixed mortar, the ceiling is painted with fangci paint with mixed mortar, the roof is made of APP modified asphalt waterproofing membrane, the downpipe is PVC151 anti-climbing downpipe, the doors are plastic steel doors, plywood doors and anti-theft iron gates, the windows are plastic steel windows, and the stair brick railings.

3. Installation project

(1) Water supply and drainage project

The water tank and tap water are planned to be used for water supply in the building, and the indoor water supply system of the building is divided into zones, and the water supply system adopts downward feeding type. The building is equipped with an indoor water inlet pipe and an outdoor pipeline connected in a ring shape. Portable fire extinguishers shall be arranged in the floor aisles and corresponding positions.

the indoor domestic water supply pipe adopts PVC-U polyvinyl chloride water supply pipe and fittings.

PVC-U rigid PVC drainage pipes and fittings are used for indoor sewage pipes and rainwater pipes, which are socket-bonded.

the top soil of domestic water supply pipe is 1.75m; The support and hanger of PVC-U water supply and drainage pipe shall be constructed in strict accordance with the specification requirements, and pipe clamps shall be added to the stressed parts such as taps and valves to strengthen the stress strength.

(2) lighting project

the power supply incoming line of this project adopts YJV22-1KV power cable directly buried, with a voltage of 381/221 volts and a three-phase four-wire system.