(1) Curtain walls and aluminum alloy members shall be horizontal and vertical, with correct elevation, and the surface shall be free of mechanical damage (such as scratches, scratches and indentations) and defects to be treated (such as spots, stains and stripes).
(2) All exposed metal parts (pressure plates) of the curtain wall should be flat in appearance from any angle, and no slight deformation, ripple, indentation or protrusion of fasteners is allowed.
(3) After the iron bracket is fixed with the T-shaped groove, it should be welded firmly, and the gap between the iron bracket and the concrete contact surface of the main structure should not be greater than lmm, and it should be filled with galvanized steel plate. The joint of bracket iron and curtain wall must be padded with shockproof rubber pad. Welds of steel parts welded at the construction site shall be coated with two layers of antirust paint at the site.
(4) Asphalt paint with a thickness greater than 100um must be painted on the metal surface in contact with the masonry, plastering or concrete surface.
(5) When the glass is installed, there must be a gap between its edge and the bone to ensure the gap from top to bottom. At the same time, it is necessary to prevent the glass from being polluted, especially the coated side. Yujia should pay attention to prevent the coated film from falling off and forming a paint surface. The installed glass surface should be almost complete without warping.
(6) rubber strip and rubber strip should be fully plugged, and the joint of two rubber strip must be sealed with sealant. When caulking with caulking material, caulking should be full and uniform, and the appearance should be smooth.
(7) Interlayer fireproof and heat-insulating mineral wool materials shall be tightly packed and shall not be omitted.
2. Finished product protection
(1) The personnel shall be responsible for the lifting of the hanging basket, and elastic soft materials shall be set inside to prevent the curtain wall and glass from being damaged. When the work is over, the hanging basket should be placed on the floor (or ground) where the fixed curtain wall has not been installed.
(2) The installed curtain wall shall be supervised by designated personnel, and the upper part shall be covered with baffles to prevent the curtain wall from being damaged by blanking during the upper part construction. When welding the upper floor, a special "spark bucket" should be set to prevent the curtain wall from being damaged by sparks. When working near the curtain wall, shielding measures should also be taken to prevent aluminum alloy materials from being polluted and glass from being damaged.
(3) Before completion, use window cleaner to scrub the curtain wall.
3. Project acceptance
(1) The curtain wall project shall be accepted after the building is completed (excluding the secondary decoration), and its surface shall be scrubbed clean before acceptance.
(2) The following materials shall be submitted when the curtain wall project is accepted:
1) design drawings, documents, design modification and material substitution documents;
2) Ex-factory quality certificate of materials and components, profile test report, silicone structural sealant compatibility and adhesion test report;
3) Acceptance documents for concealed works;
4) Building installation self-inspection record.
(3) Curtain wall engineering quality should be inspected according to appearance inspection and sampling inspection. Take one curtain wall as the inspection unit, and each curtain wall should be inspected.
(4) The appearance inspection of curtain wall engineering shall be carried out according to the following requirements:
1) The frame material of the open frame curtain wall should be vertical and horizontal; Unit flat-fell seam or hidden frame of unit curtain wall
Curtain wall frame glass flat-fell seam should be firm, flat, seam width should be uniform, and meet the design requirements;
2) The variety, specification and color of glass should be consistent with the design, and the color should be basically uniform. Aluminum alloy materials should not have alkali precipitation, mildew and coating shedding;
3) The installation direction of the glass should be correct;
4) The color of metal materials should be consistent with the design, and the color should be basically uniform, and aluminum alloy materials should not have peeling phenomenon.
5) The surface of aluminum alloy decorative pressing plate should be smooth, and there should be no defects such as deformation, fatigue lines or local rolling that can be detected by naked eyes;
6) The treatment of upper, lower, side seals, settlement joints, expansion joints and seismic joints of curtain wall and lightning protection system shall comply with the provisions of brick doors.
7) Curtain wall concealed node cover sealing decoration should be neat and beautiful.
8) Curtain wall shall not leak.
Construction technology of aluminum-plastic board for external wall
Pay-off → Fixing skeleton connector → Fixing skeleton → Installing aluminum plate → Closed structure treatment → Inspection.
1) Pay-off
Fix the skeleton and bounce the position of the skeleton to the base. The skeleton is fixed on the main structure. Check the quality of the main structure before setting out.
(2) Connectors for fixing bones
Weld connectors on the columns of the main structure to fix the skeleton.
(3) Fixed skeleton
The skeleton is treated with antiseptic. Install the skeleton accurately and firmly. Check the center line and surface elevation after installation. In order to ensure the installation accuracy of the plate, theodolite should be used to penetrate the vertical frame members of the beam. Properly handle deformation joints, settlement joints, variable cross sections, etc. , to meet the use requirements.
(4) Install aluminum plate
The installation and fixation of aluminum plate should be firm, reliable and simple.
1. Gaps between plates shall be internally treated to make them smooth.
2. After the aluminum plate is installed, cover it with plastic film or other materials to protect the easily contaminated parts.
C, aluminum canopy construction scheme