Current location - Recipe Complete Network - Catering franchise - What is the name of the swimming center of the 2008 Olympic Games
What is the name of the swimming center of the 2008 Olympic Games
Water Cube

I. Project Overview

(I) Project Overview

The National Aquatics Center is one of the landmark buildings of the 2008 Beijing Olympic Games, and is the only landmark Olympic venue designated by the Beijing Municipal Government to be constructed by the donations of Hong Kong, Macao, Taiwan and overseas compatriots. During the Olympic Games, it undertakes swimming, diving, synchronized swimming and water polo competitions. After the Olympic Games will become a multi-functional large-scale water sports center, can provide the public with water entertainment, sports, leisure, fitness and other services.

The National Aquatics Center is located in the southwest corner of Olympic Park B. The main building is adjacent to the city's central axis, and is arranged in a balanced manner with the National Stadium relative to the central axis.

The east side of the landscape road, the west side of the landscape west, the south side adjacent to the North Top Nyonya Temple, the north side of Chengfu Road. The project covers an area of 62,828 square meters, the race building area of 79,532 square meters, building eaves height of 31 meters, the base area of 177 meters × 177 meters, standard seating 17,000, (of which about 13,000 temporary seats, 4,000 permanent seats). The main structure of the project is designed to have a service life of 100 years. The approved project investment is 1.02 billion RMB. The project started on December 24, 2003 and is scheduled to be completed in October 2007.

(B) Project management system

According to the authorization of the Beijing Municipal Government, the Beijing Municipal State-owned Assets Management Limited Liability Company, as the owner of the project, is solely responsible for the construction and operation and management of the National Aquatics Center. The China Yangtze River Three Gorges Project Development Corporation was hired as the project manager, responsible for the specific construction management.

Designer: China State Construction Corporation National Swimming Center Design Consortium (including China State Construction Engineering Corporation, China State Construction International (Shenzhen) Design Consultant Company Limited, Australia PTW and Arup Engineering Consultants);

Construction Supervision Unit: Beijing Parker International Engineering Consulting Co. Development Company.

Second, the design

At the end of June 2003, our company through the international scope of the design competition, after the technical pre-qualification, expert review, contract pre-negotiation, public voting and technical demonstration, and reported to the municipal government and the Organizing Committee for the Olympic Games, the municipal government on July 28, 2003, the mayor's office meeting approved: China State Construction Engineering Corporation, China State Construction Engineering Corporation, China State Construction Engineering Corporation, PTW Australia Ltd., Australia PTW and ARUP company composed of four design consortium to participate in the "Water Cube" program for the National Aquatics Center implementation plan.

(a) Design concept

This is a building about water. The microscopic molecular structure of water in foam form is amplified into the organic spatial grid structure of the building through the deduction of mathematical theory, thus becoming the building itself. The "Water Cube" is an impeccably pure square that calmly expresses the courtesy and respect for the main stadium, and complements the complete circle of the main stadium.

(ii) structural characteristics

The external wall and roof enclosure structure adopts a new type of steel membrane structure system, which consists of a series of steel mesh frame units similar to cells and crystal bodies and ETFE (polyethylene-tetrafluoroethylene*** polymer) inflatable film **** with the composition.

Third, engineering and technical difficulties

(a) the National Aquatics Center "Water Cube" structural key technologies

"Water Cube" structure follows the most common form of structural composition of nature, the use of a three-dimensional space based on the theory of effective division of bubbles. The structure of "Water Cube" follows the most common structural composition form in nature, and adopts a new type of space structure based on the theory of effective division of three-dimensional space bubbles, which forms the uniqueness of the structure of the National Swimming Center, and it is a challenging work from analysis, design to construction, and it also puts forward a lot of new topics for the development and research of space structure.

(B) Super-large-area ETFE Membrane Structure

The building envelope of the "Water Cube" design program adopts a new type of ETFE inflatable pillow, with a surface coverage area of 100,000 square meters, which is the largest ETFE application project in the world at present.The ETFE facade assembly system has the advantages of material, material, and structure, compared with the traditional building envelope. ETFE fa?ade assembly system compared with the traditional building envelope, has a small material weight, flame retardant, beautiful building appearance, good light transmission and many other advantages.

(C) the key technology of indoor environment system

As the ETFE material inflatable pillow and the traditional building materials in the physical properties are completely different, and the National Aquatics Center on the indoor environment and have very strict requirements, so figure out this special enclosure sound, light, heat characteristics of the indoor environment, and put forward performance improvement measures to ensure that the National Aquatics Center It is very important to ensure that the indoor environmental requirements of the National Aquatics Center are met.

Some of the above problems have been solved, and some are being overcome through relevant tests.

Fourth, the progress of the project construction

December 24, 2003 was successfully held in the National Aquatics Center groundbreaking ceremony, the central government and the Beijing Municipal leaders attended the ceremony, marking the National Aquatics Center officially entered the construction stage.

As of February 2005, the earth excavation, foundation piles and waterproofing of the floor slab have all been completed, including about 400,000 square meters of earth excavation, 4,366 foundation piles, and about 40,000 square meters of waterproofing of the floor slab.

The concrete pouring construction of the base slab started in October 2004, and the concrete construction of the underground part of the structure and the backfilling of the fertilizer tanks are now underway, and some sections have reached plus or minus zero. At present **** completed underground structural concrete 40,000 cubic meters, 8,000 tons of steel reinforcement system, respectively, accounting for 56% and 61% of the total.

V. Engineering Construction Arrangement

April 2005 to complete the underground structure of concrete construction;

June 2005 to complete the above-ground structure of concrete construction;

2005 the end of the year to complete the installation of the steel structure;

August 2006 to complete the installation of the membrane structure;

the end of 2006 to complete the equipment Installation, and on-line debugging;

October 2007 all completed, and complete acceptance.

National Aquatics Center post-game operation concept

National Aquatics Center project to meet the Olympic Games competition requirements at the same time, in the design of the post-game operation for the maximum consideration, the existing design of the National Aquatics Center will be used to maximize the use of the post-game, the competition and entertainment organically integrated.

Currently in the design of the National Aquatics Center will be divided into seven main operating divisions, namely: the main competition hall (including competition pools, diving pools), warm-up pool hall (warm-up pools), splash hall (splash park), multi-purpose hall (ice rink), the South Building, the North Building, Commercial Street.

I. Competition Hall

Its function is to carry out temporary, planned, group and training courses of water sports training. Under normal operating conditions, the auxiliary facilities of the main competition hall include:

Patron changing rooms

Pool equipment storage rooms

Technical, announcement and audio visual control rooms

Swimming pool management and staff areas, including changing rooms

Pavilion medical center access

Swimming club meeting rooms and club management areas.

II. Warm-up Pool Hall

In normal operation, the warm-up pool hall provides ancillary facilities including:

Customer changing rooms, including family changing rooms

Access to medical facilities

Pool equipment storage

III. Splash Hall

The main function of the hall is indoor splashing, aimed at children, families and adventurers. The main function of the hall is indoor splashing, mainly for children, families and adventurers. Under normal operating conditions, the Splash Hall provides the following facilities:

Changing rooms, including a family changing area

Catering facilities, including food and drink

Control room for the ride-based entertainment facilities

IV. Post-Games North Building (Private Club)

The functions of the North Building include: the first floor as a catering and bar area, and the second to fourth floors as a club area, lounge and catering area. The second to fourth floors are used for clubhouse and lounge dining, etc. Under normal operating conditions, the private club offers the following facilities:

Changing rooms

Spa, sauna and steam room

Terrace and relaxation area with sun loungers

Private swimming club pool to be installed after the 2008 Olympics and Paralympics

V. Post-race South Building

Its functions are: the first floor is a commercial building, the second to fourth floors are for clubs and lounge dining. The first floor is for commercial use, and the second to fourth floors are for fitness and office use. Under normal operating conditions, the main facilities provided in the Post Race South Small Building are:

Open office space (which can be used for other purposes)

Activity and fitness space (basketball, badminton, bowling, etc., as required by the operator)

Food and beverage service area

VI.Commercial Street

Its functions are catering, commerce, restaurants, beauty salons, massage, etc. Shopping, sightseeing and rest. Under normal operating conditions, the commercial street provides the following facilities:

East-west internal pedestrian circulation and evacuation routes (with a view of the splash park)

Catering, service facilities

Shopping malls, shopping

Drinking places

VII.Multi-purpose hall

Its functions are: as an ice skating rink and ice hockey rink. Under normal operating conditions, the multi-purpose hall provides the following facilities: