Handling process of catering drainage certificate:
1. The applicant applies to the urban management window of the administrative service center;
2. On-site reconnaissance by the competent department and relevant units;
3. After the site survey is qualified, provide relevant information;
4. The municipal department will review and the drainage permit will be issued by the urban management window of the administrative service center;
5. If a drainage household discharges sewage into urban drainage facilities without obtaining a drainage permit, the competent department of urban drainage shall order it to stop the illegal act, take control measures within a time limit, and reissue the drainage permit, and may impose a fine of less than 511,111 yuan. Drainage households listed in the list of key pollutant discharge units may be fined between 311,111 yuan and 511,111 yuan.
The requirements that catering enterprises must meet:
1. The internal rain and sewage diversion has been completed and there is a fixed sewage outfalls;
2. Pretreatment facilities have been set up according to regulations and entrusted to professional operation and maintenance companies for maintenance;
3. It has been correctly connected to the municipal sewage pipe network;
4. The quality of discharged sewage meets relevant standards.
to sum up, the shopping malls, buildings, public construction units and construction sites of a single plot are separately certified; Residential shops are uniformly certified by residential properties; Special industries, such as medical care, catering, etc., or those that directly discharge water to public drainage facilities alone also need to obtain a separate permit.
Legal basis:
Article 7 of the Measures for the Administration of Urban Sewage Drainage Network Permit
To apply for a drainage permit, the following materials shall be submitted truthfully:
(1) Application form for drainage permit;
(2) drawings and descriptions of the drainage pipe network, special inspection wells, and the location and caliber of the rain sewage outfalls;
(3) relevant materials for the construction of sewage pretreatment facilities in accordance with relevant state regulations;
(4) a report on the completion of the concealed drainage project, or a written undertaking from the drainage households that the concealed drainage project is qualified and there is no mixed connection and wrong connection of rainwater and sewage pipe networks or mixed discharge of rainwater and sewage;
(5) a test report that the drainage water quality meets the relevant standards or a written undertaking that the drainage water quality meets the relevant standards;