Current location - Recipe Complete Network - Catering industry - Model construction project planning book
Model construction project planning book
Construction needs to be planned and implemented step by step as planned. If there is no complete plan to implement it, it is easy to have no direction like a headless fly. The following is a demonstration case of construction project planning book compiled by me for your reference only. You are welcome to read it.

Model essay on construction project planning book Case 1. Project overview

1. 1 project overview

Roof design requirements: fine stone concrete (internal reinforcement) (40.00mm)+ 1.3 cement mortar screed-coat (20.00mm)+ extruded polystyrene board (40.00mm)+APP modified asphalt waterproofing membrane (3.00 mm)+ 1.3 cement mortar screed-coat (40.00mm).

1.2 compilation basis

Design drawings and construction contracts of construction projects.

Second, the heat preservation construction preparation

2. 1 material requirements

2. 1. 1 extruded polystyrene board (40.00mm)

Flame-retardant extruded polystyrene board should be adopted, and the material should meet the specifications and design requirements.

2. 1.2 Extruded polystyrene board adhesive

Special adhesive for extruded polystyrene board produced by our company.

2.2 Preparation before construction

2.2. 1 organizational preparation

(1) Relevant personnel involved in construction management must be familiar with the construction drawings carefully, find the problems and summarize them, and put forward the modification scheme at the same time.

⑵ Check whether the construction equipment is in good condition and make preparations.

(3) Sign a good contract with material suppliers and establish a supply guarantee system.

Third, the roof insulation construction

1. base cleaning: during the construction of roof insulation, the base of insulation surface should be cleaned.

2. Laying of roof insulation board: After the waterproof layer is completed and confirmed to be normal through inspection, the extruded polystyrene board can be laid. The expansion of extruded polystyrene board itself is extremely low, and there is basically no need to leave expansion joints. In order to avoid the displacement of the extruded polystyrene board in the subsequent construction process and affect the overall construction, a fake joint can be made between the extruded polystyrene board and the waterproof layer with adhesive, and it is only necessary to paste or brush and paste it on the waterproof layer according to the size of the extruded polystyrene board, without comprehensive brushing. When the roof protrudes, the extruded polystyrene board should be cut and laid properly.

3. When laying insulation board, the gap between extruded polystyrene boards should not be greater than 2mm, and the horizontal joints between extruded polystyrene boards should be staggered; Extruded polystyrene board should be used to caulk around to ensure that the joints of the board are tight. During the construction of thermal insulation plane, broken wood boards shall not be used, and they shall be replaced immediately if any.

4. finished product protection. After the horizontal construction of insulation board is completed, the protection of finished products should be strengthened. Non-professional construction personnel are not allowed to enter to ensure that the insulation board will not be damaged in the next construction process.

Four, quality assurance measures and management system

(1) Establish and improve the quality assurance system, set up a quality inspection team headed by the project manager, conduct comprehensive individual inspections on a regular basis, and urge the operators to strictly control the quality.

(2) Before the construction of each working procedure, technical disclosure must be made, and the technical requirements, operation essentials and quality requirements should be implemented to each operator, so that everyone can know fairly well and construct correctly. ⑶ Strictly implement the "three inspections" system, that is, self-inspection, mutual inspection and handover inspection.

(4) The system of listing by sections shall be implemented, and the operation team leader, operators, construction date, construction site and forms shall be recorded, with clear rewards and punishments.

5] regularly patrol and check all aspects of quality, find problems and solve problems.

Five, construction safety, fire control guarantee measures

(1) set up a safety leading group, with the project manager as the team leader, to check anytime and anywhere, and establish a reward and punishment system.

⑵ Full-time security officers are set up to be responsible for the safety of the whole project.

(3) After the construction personnel enter the site, safety education should be conducted.

(4) Formulate targeted safety construction measures and implement them in time.

5] to do a good job of safety technical disclosure.

[6] Establish an acceptance system for mechanical and electrical equipment. Any mechanical and electrical equipment that has not been accepted shall not be used, and non-mechanical personnel shall not use mechanical and electrical equipment.

Once the scene should be set fire equipment, fire prevention measures.

Being exterior wall construction personnel to enter the site, must wear safety helmet, fasten your seat belt.

Levies are not allowed to work high above the ground after drinking.

⑽ Smoking is strictly prohibited in the construction site.

Case 2 of construction project planning book: Since the beginning of this year, under the leadership of the board of directors and through the efforts of all employees, all the work of the company has been carried out in an all-round way, and the xx brand has been initially recognized by the society. On the whole, the result is satisfactory. In order to make the company's work to a new level, the company will do a good job in one center, two creations, three adjustments, four enrichment and five implementation in the new year. Its work plan is as follows:

First, focus on the construction of xx project and earnestly complete the marketing task.

Xx project is a key project in provinces and cities. The municipal party Committee and the municipal government have placed ardent expectations on it. Because of the social benefits and potential economic benefits contained in the project, it must be built and cannot be screwed up; We can only move forward, not stagnate or even retreat. Therefore, the company plans to:

(a) to ensure that the xx project started in the first quarter, and strive to basically complete the first phase of construction tasks during the year.

The first phase of xx covers an area of 60 mu, with a total investment of 65.438+0.6 billion yuan and a construction area of 65.438+0.26 million square meters. The building is the skirt building of xx Commercial Plaza, the skirt building of xx Building and a logistics warehouse.

1, land acquisition and demolition work

Be sure to complete the land acquisition and demolition of the first phase of the project before and after the Spring Festival. 1 month completed a thorough investigation of land acquisition, and in February completed the demolition of unlicensed houses within the scope of land acquisition. In March, the demolition of certified houses within the scope of land acquisition and the expropriation of land and collective land in the land reserve center were completed. The coordination of the relationship between various departments is mainly based on the general manager's office, with the cooperation of the consultant's office and the specific operation of the engineering department. After the project enters the implementation stage, the engineering department should pay close attention to the land acquisition and demolition work in the second phase of the project and adjust the main attack direction in time.

2. Project Contract and Commencement

1 month signed the bidding agency contract, and the project entered the bidding stage. In February, it was determined that powerful construction enterprises would sign construction contracts in parallel; Ensure that supervision enterprises sign supervision contracts in parallel. The project officially started construction in March. In addition, the engineering department should strengthen the filing management of engineering contracts and various materials, and keep records by classification. Establish a complete project file.

3. Construction application work

The engineering department shall submit the project approval in time and follow up the drawing design. 1 month to complete the design of the scheme diagram; In February, the design of the extended diagram was completed. In the process of undertaking, the engineering department should be good at straightening out the relationship with relevant departments, and should not affect the start of the project because of the delay in applying for construction.

4. Engineering quality

Xx project is a key project in provinces and cities, and it is also the image project of xx brand. Therefore, it is particularly important to grasp the quality of the project. While assisting the engineering supervision company, the engineering department should gradually establish the company's engineering quality supervision system. Give priority to supervision, supplemented by self-construction, and strive to build xx project into a provincial excellent project.

5. Budget and final accounts work

Engineering department and finance department must strictly control the project budget and final accounts. Strictly implement the agreed quota standards, and shall not increase the quantity and settlement without authorization. Shall not exceed the budget to pay for the project.

(2) Earnestly complete the annual marketing task to ensure that the project schedule is not out of touch.

The annual sales task of pharmaceutical shops, property hotels and apartment buildings determined by the company in 20xx is 65.438+0.5 billion yuan. The completion of this task is directly related to the realization of the first phase of the project. So we must do a good job in marketing.

1, implement the task decomposition of house purchase, and ensure the performance of the planning agency contract.

In 20xx, the sales task of the company's buildings was 65.438+0.5 billion yuan, including 65.438+0.5 billion yuan in the first quarter, 45 million yuan in the second quarter, 45 million yuan in the third quarter and 45 million yuan in the fourth quarter. According to the agreement signed by xx, the carrier of this task is the planning organization. A new annual task contract was signed on 1 month through negotiation between both parties. In order to complete the annual marketing task, we suggest that the planning agency can implement the task decomposition of home ownership, which varies from person to person. Rather than relying solely on the activities of the investment promotion hall or center. We can adopt more flexible sales methods, complete the annual sales task in an all-round way, and fundamentally ensure the follow-up of project funds. In the form of marketing, we should improve the group purchase, center activity promotion, door-to-door promotion and other programs, and strive to create new marketing models and form self-marketing characteristics.

2. Rational use of advertising forms, brand building and marketing expansion.

In the new year, the company will further expand its advertising investment on the basis of 20xx. Its purpose is to shape xx brand and expand real estate marketing. In advertising marketing planning, xx should make great efforts in advertising category, data statistics, effect evaluation, cycle planning, novel design, layout creativity, tone processing and so on. , so as to avoid the same layout, invalid repetition, dull design and lack of creativity.

3. Cultivate the marketing team and gradually improve the incentive mechanism.

The real estate consultant of the planning organization and the marketing staff of the company's marketing department are an organic cooperative group. In the new year, the company will make full use of this part of resources. Planning agents should first do a good job in training the basic knowledge of marketers, so that marketers can become a team that can bear hardships, have skills and be good at promotion. Secondly, gradually improve the marketing incentive mechanism and establish marketing incentive measures in the system, and the specific incentive plan is drafted by the marketing department.

4. Broaden financing channels and tap social potential.

It is planned to broaden financing channels through bank credit financing, manufacturer financing, social financing, national debt financing and group financing. Expand the capital flow by means of share transfer and share expansion, and ensure that the construction funds of xx project are in place in time.

(three) to start the investment procedures in an all-round way, focusing on results.

Investment promotion is an important foundation for the operation after the completion of xx. Whether the work is carried out smoothly or not will directly affect the company's real estate sales. Therefore, in the new year, investment promotion should be carried out in a planned, targeted and timely manner.

1, combined with the current situation of the pharmaceutical market, formulate feasible investment policies.

According to the contract signed between the company and the planning agency, xx should publish the investment promotion plan and the investment promotion manual last year, but the work has lagged behind at present. The company requires the above two books to be compiled and published by the planning agency in the first quarter. In order to synthesize the pharmaceutical market, it is suggested that the investment promotion department should be responsible for drafting investment promotion measures, and the investment promotion department should be required to publish the first draft in 1 month.

2. Establish an investment team and operate in a virtuous circle.

From the analysis of the gains and losses of investment promotion in the past year, an important reason is the lack of investment promotion team and the shortage of personnel. In the new year, while introducing the competition mechanism, the investment promotion team will be equipped with qualified, professional and pioneering personnel, so as to enter a virtuous circle of investment promotion.

3, clear investment tasks, lay a good foundation for operation.

The first phase of xx project is scheduled to be completed by the end of this year and put into production next year 1 month. Therefore, the existence of manufacturers, general distributors and general agents is the basis of operation. We can't wait for the rice to be cooked. We have to wait for the army to arrive, and the food and grass will go first. This year, there are 300 enterprises, general distributors, general agents, pharmaceutical business agents and other tasks. By the planning agencies and investment promotion departments.

4. Prepare for logistics operation and make reasonable, effective and timely investment.

Medical logistics is different from traditional medical business, which requires medical logistics enterprises to be different from traditional medicine not only in the construction of medical trading platform, the improvement of transportation and distribution capacity and the configuration of medical logistics system, but also in the timely and rapid exchange of information functions. Therefore, in the new year, the company will cooperate with the Municipal Logistics Research Institute, sign a cooperation agreement, and perform its duties according to the contract. In order to make the company's operation market-oriented, the company plans to set up the logistics department, formulate the operation plan of xx pharmaceutical logistics system, and determine the composition of facilities and equipment, operation process and management mechanism. The work was carried out with the consent of the board of directors.

Second, take brand building as a long-term goal and gradually complete the two establishment.

Building xx brand is one of the company's strategic goals. The success of modern brand building must depend on the modern management mode of enterprises. In the new year, we will strive to establish a group company and a modern enterprise management system, and gradually build the company into a large private enterprise group.

1. Set up enterprise groups and continuously expand the company scale.

2. Establish a modern enterprise management system and implement work standards until people arrive at their posts.

Third, take the development of xx as a historical opportunity to speed up the three major internal adjustments.

The development of xx is the historical mission and the requirement of the market. We should adapt to the needs of this era, constantly improve ourselves, develop ourselves, adjust the mechanism, condense internal strength, give full play to the kinetic energy of employees, and let xx Group stand proudly in the forest of medicine.

1, personnel adjustment

The personnel adjustment work has been rolled out, and the principle followed by the company is to make the best use of people. Give full play to employees' innovative ability and fully affirm their pragmatic spirit.

2. Institutional adjustment

At present, institutional adjustment mainly refers to the internal institutional adjustment of xx Co., Ltd. At present, the established departments are: general manager's office, office, engineering department, marketing department, investment promotion department and finance department, that is, two rooms and four departments. With the xx project entering the construction stage, it is planned to add human resources department, logistics department, enterprise planning department and other departments to become the foundation of the group company. Four independent corporate companies, xx Real Estate, xx Pharmaceutical Commercial Company, xx Logistics Center and xx Property Management, have entered the preparatory period and will formally operate independently next year. Make the internal organization of the company become a unity with complete functional elements and reasonable division of labor.

3. Adjustment of the regular meeting system

The regular meeting system implemented in 20xx has played a very good role in summing up and perfecting the phased work and arranging the work in different periods. In the new year, while adhering to the regular meeting system, we will make the following adjustments:

First, the regular meeting time. It is held every Saturday morning.

The second is the meeting host. In addition to the work summary and work arrangement, each regular meeting will determine a work theme, which will be presided over by the general manager, deputy general manager and chief engineer in charge of the work respectively.

The third is to establish an inspection system for regular meeting arrangement, that is, the executive department should report the implementation of the previous meeting arrangement within a specified period of time, so as to sum up experience, improve methods and perfect them.

Fourth, on the premise of actively developing employees' potential, continuously enrich the foundation of enterprise development.

Xx's entrepreneurial spirit breeds everything, people-oriented; Harmonious and realistic, scientific and realistic determines the construction of xx brand, and the establishment of xx Group must enrich the basic work, all kinds of talents, corporate culture and comprehensive quality. In the new year, the company will carry out its work in four aspects.

1, enrich the basic work and improve the business environment.

Enriching basic work, the company mainly means that the work of all departments and positions should be in place, meticulous and in line with work standards. Do small things carefully, and do small things thoroughly. Pragmatic, not vain, really not grandiose. Standardize behavior and be meticulous. Improve the internal working environment and external business environment by doing basic work well. The main standards of this work are determined by the company's work manual formulated by the office, which requires employees to strictly abide by. In order to effectively supervise the quality of basic work carried out by various departments, the company office will undertake the compilation of xx work dynamics every half month in the new year.

2. Enrich all kinds of talents and improve personnel structure.

The competition of enterprises is, in the final analysis, the competition of talents. We should fully realize that there is a gap between the job suitability rate of company employees and modern standards.

In the year of 20xx, the company will formulate recruitment conditions and set up recruitment processes for all kinds of personnel according to the actual needs of enterprises, so as to attract all kinds of talents who are willing to serve xx, and accordingly establish a professional talent pool for xx to meet the needs of various positions of xx Group.

3. Enrich corporate culture and enhance humanistic spirit.

Thick corporate culture is also a manifestation of strong competitiveness. In the new year, xx planning organizations should take new measures to promote XX culture while carrying out marketing planning. External is the need of xx brand, and internal is the specific requirement of building a harmonious enterprise. Therefore, the formation, sublimation and sublation of xx culture should take xx enterprise spirit as the core and form a rich xx enterprise culture.

Case 3 1 model essay on construction project planning. Project overview

Construction unit: civil engineering development company of xx Co., Ltd.;

Design unit: Seventh Design and Research Institute of Nuclear Industry;

Supervision unit: xx Engineering Construction Supervision Co., Ltd.;

Contracting method: contracting for labor and materials;

Quality standard required by the tender: qualified;

The tender requires the commencement time to be 20xx, the completion time to be 20xx, and the total construction period to be 365 calendar days.

Second, the organization and job responsibilities

Overall construction progress plan:

A. Main structure: setting out of concrete wall → binding wall reinforcement → installing wall formwork → pouring wall concrete → installing roof formwork → binding roof reinforcement → pouring roof concrete → transferring to lower construction.

B, roofing engineering: insulation layer → leveling layer → leveling layer → waterproof layer → protective layer.

C interior decoration: copy and lay flat samples → secondary structure → installation of door and window frames → plastering and leveling of indoor walls → floor → installation of door and window sashes → installation of hydropower equipment.

D. Construction sequence of exterior wall decoration: follow the principle of "first up and then down", plaster the exterior wall and brush the exterior wall paint.

Third, the project construction planning

1, project management mode;

2, engineering subcontracting and labor organization

Labor organization preparation:

1) set up a project management department, implement the personnel of each post, formulate various management systems and functions, and take responsibility to people.

2) Organize the labor force to enter the site in batches, and make labor education and safety technical disclosure.

3. Supply of main materials and equipment

According to the budget (bill of quantities of main building materials for civil engineering, bill of materials for main plumbing equipment, bill of materials for electrical engineering), put forward the material and equipment supply plan; According to the construction arrangement, prepare the construction machinery use plan and material procurement plan. Summarize the application plan of engineering parts, materials and equipment and report it to the engineering department. Implement the mobilization time plan for major materials, equipment and semi-finished products.

Organize pre-procurement resource investigation, supplier selection evaluation and price determination, and organize bidding (invitation) procurement and leasing of materials and equipment according to materials and equipment procurement documents.

Case 4 of the construction project planning book is to thoroughly implement a series of arrangements made by the CPC Central Committee and the State Council on strengthening production safety, conscientiously implement the spirit of the 20xx national transportation work conference, strictly implement the relevant provisions of the Law on Production Safety and the Regulations on the Administration of Production Safety in Construction Projects, and earnestly strengthen the "two basics" (grass-roots and foundation) work of production safety in traffic construction. Efforts will be made to improve the safety supervision level and emergency support capability of the fourth bid section of the construction project from xx(xx boundary) to xx expressway, so as to promote the steady improvement of the safety production situation. Starting from this year, a two-year "Safe Site" construction activity will be carried out in xx(xx Boundary) to xx Section of the fourth bid section of expressway Construction Project. The relevant arrangements are as follows:

I. Guiding ideology and work objectives

Guiding ideology: under the guidance of Scientific Outlook on Development, carry out the policy of safety first, prevention first and comprehensive treatment, adhere to the principles of grasping the whole team, creating a demonstration team, grasping the construction site and grasping the key points, and vigorously promote the standardization of safety management of this project.

Work objective: Through the construction of "Safe Site", the laws, regulations and technical standards of safety production have been effectively implemented at the grassroots level, and the foundation of safety work has been fully consolidated, so that the safety protection on the construction site is standardized, the appearance on the site is standardized and the safety management is programmed. The responsibility for production safety of all construction units is in place, safety training and education are effective, and construction safety risks are effectively controlled. Achieve the goal of zero serious accidents, curb serious accidents, achieve "zero" casualty scene, and promote the overall improvement of safety management level.

Second, the activity time and scope of participation

The activity starts in 20xx and ends in 20xx for two years. The first year is the year of establishing demonstration, and the second year is the year of substandard promotion.

The project actively participates in various activities. The activity is led by the project department, implemented by each construction team, and participated by the prefabrication plant, bridge and yard.

Third, the implementation steps

First year: create a demonstration year

Each construction team should formulate the implementation plan of the "safe site" construction activities of the department according to the actual situation, and deploy the "safe site" construction activities to the team. According to the Regulations on Construction Safety Management, Technical Specifications for Construction Safety of Highway Engineering, Technical Specifications for Construction Safety Protection of Waterway Engineering and other relevant laws and regulations, the construction activities of "Safe Site" are carried out in the following six aspects.

1. Establishment of safety system and implementation of safety responsibility system

Each project office shall register the person in charge of project quality and safety of the construction unit, and check the safety management rules and regulations and various operating procedures of the construction unit. The safety management system formulated by the construction unit shall at least include the responsibility system for production safety of all kinds of personnel (including project manager, deputy manager, chief engineer, team leader of each operation, full-time safety officer, special personnel, etc.). ), the safety production responsibility system of each department (including engineering department, mechanical ministry of materials and equipment, laboratory, construction team, warehouse, prefabrication factory, subcontracting (cooperation) unit, etc. ), production safety inspection system, production safety fund management system, production safety education and training system. Safety production technical disclosure system, special construction scheme review system, special operation personnel holding certificates system, special equipment acceptance registration system, tunnel and other dangerous construction sites access registration system, safety production assessment reward and punishment management system, safety production accident emergency rescue system, safety production accident reporting system, major hazard source management system and dangerous goods management system.

2. Formulation, review and implementation of special projects with greater risks.

The project office should strengthen the safety inspection of dangerous projects to ensure that there are no major safety problems on the construction site. The construction unit shall formulate safety technical measures and temporary electricity utilization plans for the construction site in the construction organization design. In view of the potentially dangerous earthwork excavation, landslide and high slope treatment under adverse geological conditions; Dangerous projects such as pile foundation, retaining wall foundation, deep water foundation and cofferdam project, beam, arch, column construction in bridge project, concrete pouring, blasting project, erection and removal of large supports, templates and temporary bridges in temporary works should be prepared with safety inspection results, and implemented after being reviewed and signed by the technical director and supervision engineer of the construction unit, and supervised by full-time safety production management personnel on site. When necessary, the construction unit shall organize experts to demonstrate and review the special construction scheme of the project and report it to the construction unit for the record.

3. Employment registration and pre-job safety training and education.

The Project Office shall carefully supervise and inspect the safety production education and training of employees. The construction unit shall establish a dynamic management account of labor and employment, and conduct pre-job safety education and training for new construction personnel, especially those who have adopted new technologies and new processes for a long time. The project leader and full-time safety officer of the construction unit shall hold the certificate of "Class III Personnel", otherwise they shall not take up their posts. The construction unit shall regularly organize safety education and training for management personnel and construction personnel, and record the education and training in personal performance files. Personnel engaged in vertical transportation machinery, lifting equipment installation, climbing erection and other special operations shall hold the post certificate of special equipment operation, otherwise they shall not take up their posts. The safety management personnel of the construction unit shall disclose the safety technical measures and operation specifications to the frontline construction personnel before the commencement of each sub-project, and inform the operating procedures of dangerous posts and the hazards of illegal operations in writing.

4. Hidden dangers investigation and management

According to the characteristics of this project, each project office shall formulate a detailed construction safety hazard investigation plan, determine the detailed scope of safety hazard investigation, establish a safety hazard investigation and management account, specify the responsible person, formulate rectification measures, determine the rectification time, and review in time. Construction and supervision units shall strengthen the safety inspection on the construction site, and promptly stop or correct acts that violate the technical standards, norms and operating procedures of construction safety. In particular, the safety facilities for aerial work such as cast-in-place bridges and long-span bridges with high piers, the safety production scheme for the treatment of high slopes and landslides, the safety management of oil storage tanks, construction and domestic electricity consumption, etc. , should focus on hidden dangers, and take timely measures to eliminate the hidden dangers of safety accidents found. Supervision units should take various inspection forms such as standing by and patrolling to supervise the implementation of safety production and safety measures of construction units. For the problems found, the supervision unit shall require the construction unit to rectify immediately. If the problem is serious, the supervision unit shall request the construction unit to suspend the construction in writing and report to the construction unit.

5. The overall layout of the construction site, the construction of the construction site, and the safety protection standards for construction operations.

The construction unit shall strengthen the supervision and inspection of the overall layout of the construction site, the construction of the construction site and the safety protection measures for the construction operation. The construction unit shall provide the construction personnel with the production environment, living facilities, working conditions, mechanical equipment and safety protection appliances that meet the relevant national safety standards, and take corresponding safety construction measures at the construction site according to different construction stages and changes in the surrounding environment and climate. Special attention should be paid to all kinds of aerial work, pile foundation and pier construction, hydraulic limb protection, geological prediction and monitoring measurement of large-scale bridges and overpass bridges, whether the hardening safety setting of temporary access roads is strictly in accordance with the requirements of the specifications, whether the layout and site selection of temporary power lines, mixing yards and prefabricated yards are in compliance with relevant regulations, and whether the setting of various fall prevention facilities, life-saving fire prevention and lightning protection facilities is in compliance with relevant regulations.

6. The implementation and use of special safety expenses.

While the project department widely publicizes the construction activities, certain construction teams are identified as demonstration sites, and all departments should actively apply. After being confirmed by the project department, evaluate, sum up experience in time and organize observation and exchange.

Each construction team will submit a summary report to the project department in 20xx.

(2) The second year: the year of reaching the standard for promotion.

On the basis of summing up the demonstration experience of "Safe Site" construction, all construction units have formulated and issued the "Safe Site" standard in this region according to relevant laws, regulations and technical standards. All subordinate construction teams must carry out construction activities in strict accordance with the standards. The project department is responsible for the acceptance of "safe site" of each department. Unqualified acceptance shall be rectified immediately. Ensure the overall improvement of safety protection level and safety management level at the construction site of this bid section.

After the activity, the project department and all construction units shall timely summarize the "safe site" construction activities, consolidate the results of the activities, and commend the construction teams and departments that meet the standards. Institutionalize the "safe site" construction activities, constantly standardize the on-site safety management of this bid section, and commend the representative "zero casualties" departments emerging in the "safe site" construction activities.

Fourth, organization

The project department set up a leading group for "safe site" construction activities to guide the activities.

Leading group for "Safe Site" creation activities of the Project Department:

Group length: xxx

Deputy leader: xxx

Member: xxx

All departments should set up corresponding institutions to be responsible for the organization and promotion of activities.

Verb (abbreviation of verb) Job requirements and guarantee measures

(A) attach great importance to strengthening the heads of various departments to ensure that the "safe site" construction activities achieve practical results.

Building a "safe work site" is an important carrier to consolidate the foundation of safety work and strengthen the construction of grass-roots units of safety production, a direct and effective starting point to eliminate hidden dangers of accidents and build an accident prevention and control system, and a foothold to implement the concept of people-oriented and safe development. All departments should fully understand the importance and necessity of carrying out this activity, earnestly strengthen management, do a good job in implementation, and carry out work at all stages. Problems encountered in the activities should be solved in time to promote the solid and orderly development of construction activities. All departments of this project should strengthen the organization and arrangement of activities, make clear the objectives and achievements of activities, pay special attention to the demonstration construction team site, strictly meet the standards for acceptance, and effectively ensure that the special expenses for safety production are in place in full. All construction teams should conscientiously perform their main responsibilities, give full play to their own advantages, and actively carry out the creation activities. All departments, prefabrication plants, storage yards and other departments should be responsible for the division of labor and cooperate closely to ensure the actual results.

(2) Do a good job of "three combinations" to ensure that construction activities and safety production work are implemented simultaneously and promoted as a whole.

All construction teams and departments should combine the "safe site" construction activities with the implementation of safety production laws and regulations, improve various rules and regulations, and bring the safety behaviors of various departments into the track of institutionalized and standardized management; Strengthen the management of production safety and resolutely curb the occurrence of serious accidents; It is necessary to combine the construction of "safe construction site" with daily safety inspection, intensify the investigation of hidden dangers, continuously improve the safety production environment and conditions, and realize the overall improvement of safety management.

(3) Strengthen propaganda, mobilization and information communication to promote the smooth development of construction activities.

All departments should fully understand the current grim situation of building safety and the significance of "safe construction site" construction, and strengthen publicity and mobilization and information communication. By holding promotion meetings, hanging banners, holding training and distributing publicity materials, we will vigorously promote the "safe site" activities at all stages of construction projects and construction departments, mobilize employees to actively participate and supervise, and form a good public opinion atmosphere. According to the actual situation, formulate corresponding incentive policies for the participating teams identified as the demonstration construction team of this bid section; Departments that go through the motions in construction activities, lack of work measures, and chaotic management of the project site should be resolutely punished according to law, and those responsible for the accident should be severely investigated and punished. Take the construction of "safe construction site" as an opportunity to create more and better "safe projects" and make positive contributions to the goal of creating "safe industry". Before the end of the project, submit the summary report of "safety site" of the department.