1. First of all, it takes 20~25 days for hydropower and bricklayer, including 1~2 days for demolition and reconstruction project, 4~ 10 days for hydropower project, 3~7 days for waterproof project, 0/0 day for bricklayer, and 0/0 day for concealed project acceptance.
2. At the same time, cross construction shall be carried out for carpentry. It takes 15~20 days for woodworkers to make frames, and 5~ 10 days for facing and closing.
3. After that, it takes 10~ 15 days for oil workers to enter the site, including wood as primer, wood as topcoat, wall putty scraping and latex paint brushing;
4. It takes 4~6 days to finally install wooden doors, floors, cabinets, switches, sockets, lamps, sanitary wares and hardware.
Among them, wooden doors, cabinets and furniture are generally customized, and the production and transportation cycle is about 30 days, which needs to be set in advance and have a good quantity, so as not to delay the later progress.