Fire record publicity query fire record publicity
What is the fire recording process and cost?

Handling fire protection filing process:

Prepare relevant information on fire protection requirements and go to the fire protection window of the administrative examination and approval center for handling.

A, building fire record materials:

(a) the construction project submitted for approval shall provide the following information:

1, declaration form for fire prevention audit of building fire protection design;

2, the automatic fire facilities design fire audit declaration form;

3, the Planning Commission, planning, land and other departments in charge of the project approval and other relevant documents (land ownership certificate or lease agreement and its copy, meeting minutes, leadership approval, etc. ...

There is no charge for fire records.

There is no charge for filing fire protection design and project completion in public security fire control institutions. However, you should prepare the corresponding information. Such as official drawings, personnel qualification of design and construction units, witness sampling inspection of decoration materials, etc. The public security fire brigade does not charge fees for fire fighting, fire design review and acceptance, filing, fire safety inspection permit, fire supervision and inspection, fire accident investigation, etc.

What should I report to the fire department before fire control construction?

Before the fire fighting construction, the fire fighting design scheme should be declared to the fire fighting department, which generally refers to the fire fighting water supply system, fire fighting smoke control system, fire fighting external wall insulation materials, fire fighting water tank installation equipment, etc. It is also necessary to report fire zones, fire escape routes, corridors, etc. To the fire department, after the completion of the project, the fire department for fire acceptance.

What is the spot check system for fire inspection records?

The system of fire inspection record and spot check is another important measure of China municipal government to reform the fire inspection system. Since the fire inspection was handed over from the fire department to the housing and urban-rural construction department, the fire inspection procedures have been simplified. General buildings with a building height of less than 50 meters and residential buildings with a building height of 54 meters have been declared online, and a commitment system has been signed. Check the fire acceptance during the publicity period, which requires on-site acceptance; if it is not checked, it will pass the fire acceptance.

What do you mean the fire record is not drawn?

Most construction projects need to report the fire protection design to the Ministry of Housing and Urban-Rural Development for the record before construction, and the completion acceptance should be reported to the Ministry of Housing and Urban-Rural Development for the record before completion. After the record was passed, the legal fire control procedures of the construction project were obtained. If the filing is not selected, that is, when the number is selected for filing, the selected number can be directly constructed or put into use without filing review or completion acceptance, which saves the time and energy of the construction unit and is a convenience measure.

What is the fire protection filing process in Jinan?

I feel invited. The fire protection filing process in Jinan area is relatively standardized and clear, and the specific filing process is as follows:

First, prepare information.

The construction unit shall submit the following materials when applying for fire inspection and acceptance for the record:

1 fire acceptance record

2, the project completion acceptance report

3, involving fire construction project completion drawings

Second, online declaration.

Log in to the management system of fire control audit and acceptance system of construction projects in the province, and fill in and submit relevant materials as required.

Third, window processing.

After the system is approved, take the uploaded paper materials and offline materials to the fire window of the local government service center for handling. Offline information includes: product certificate and inspection report, third-party inspection report, construction engineering information (inspection, debugging, concealment, acceptance, etc. ), CD drawings, power of attorney and a copy of the licensee's ID card. If it is not accepted, the information provided is generally incomplete and it is necessary to start online declaration again.

Fourth, record the lottery

Draw lots: draw lots to draw the record certificate of this project and hand it over to the quality safety station for inspection. The probability of being drawn is generally not less than 50%. Not selected: A record certificate shall be issued for the unselected items.

Five, fire inspection

Fire inspection opinions shall be issued within 15 days after the data of the selected project is audited and inspected on site, and the inspection opinions shall be issued within 7 working days after the project is audited. After the notice is issued, it will be issued after being approved by the fire window of the government service center.

Qualified, issued a notice of conformity, fire engineering data for the record; Unqualified, unqualified notice issued, after the completion of the rectification, the construction unit to apply for re-inspection. At this time, you need to re-apply online. Review the project does not participate in the lottery for the record, and the window will be directly handed over to the quality safety station for inspection after acceptance.