Fifteenth the construction unit shall provide the following materials to apply for fire protection design audit:
(a) the construction project fire design audit declaration form;
(2) Legal identity documents such as the business license of the construction unit;
(three) the qualification certificate of the design unit;
(4) Fire protection design documents;
(5) Other materials as prescribed by laws and administrative regulations.
If it is necessary to apply for construction project planning permission according to law, it shall provide a certificate of construction project planning permission; Temporary buildings that need to be approved by the competent department of urban and rural planning according to law, which belong to crowded places, shall provide supporting documents approved by the competent department of urban and rural planning.
Seventeenth fire control institutions of public security organs shall issue written audit opinions within 20 days from the date of accepting the application for fire control design audit. But in accordance with the provisions of the need to organize expert review, expert review time is not included in the audit time.
Twenty-first construction units shall provide the following materials when applying for fire control acceptance:
(a) the construction project fire inspection declaration form;
(two) the project completion acceptance report and the completion drawings of fire control facilities;
(three) the quality certificate of fire protection products;
(four) the certification documents and factory certificates that the building components, building materials and decoration materials that meet the requirements of fire prevention performance meet the national standards or industry standards;
(five) fire facilities inspection documents;
(six) the legal identity certificate and qualification certificate of the construction, project supervision and testing unit;
Fifteenth before the public gathering place is put into use or business, the construction unit or the user unit shall apply to the fire department of the public security organ of the local people's government at or above the county level for fire safety inspection.
The fire control institution of the public security organ shall, within ten working days from the date of accepting the application, conduct fire safety inspection on the place according to the technical standards and management regulations on fire control. Without fire safety inspection or inspection does not meet the requirements of fire safety, it shall not be put into use or business.
Article 8 Before a public gathering place is put into use or business, the construction unit or the user unit shall apply to the fire department of the public security organ of the people's government at or above the county level where the place is located for fire safety inspection, and submit the following materials:
(a) fire safety inspection declaration form;
(two) a copy of the business license issued by the administrative department for Industry and commerce or a notice of pre-approval of the enterprise name;
(three) a copy of the legal documents obtained in accordance with the law for the fire inspection and acceptance of construction projects or the completion of fire inspection and acceptance for the record;
(four) fire safety system, fire fighting and emergency evacuation plan, site layout;
(5) Records of pre-job fire safety education and training for employees and copies of professional qualification certificates for special types of work in the fire protection industry obtained by operators of automatic fire protection systems;
(6) Other materials as prescribed by laws and administrative regulations.
In accordance with the Regulations on Supervision and Management of Fire Protection in Construction Projects, if a public gathering place that does not need to be put on record for fire protection completion acceptance applies for fire safety acceptance, it shall also submit the construction drawing of fire protection design for interior decoration of the place, the certificate of fire protection product quality, the certificate that the fire protection performance of decoration materials meets the fire protection technical standards and the factory certificate.
The application for fire safety inspection of fire control institutions of public security organs shall be accepted in accordance with the relevant provisions of administrative license.