EIA process:

1. Go to the Management Section of the Environmental Protection Bureau to get the Consultation Form for Environmental Protection Approval of Construction Projects.

2. Submit the application materials to the Management Section of the Environmental Protection Bureau: Consultation Form for Environmental Protection Approval of Proposed Projects in duplicate, a copy of the name approval notice, a geographical map of the surrounding area of the proposed location of the construction project and a copy of the house lease contract.

3. To make the EIA report, it is suggested that the EIA company recommended by the Environmental Protection Bureau issue the report, because they are familiar with each other, and they can coordinate the minor problems in the report themselves (pay attention to the amount of sewage in the EIA report. If the sewage is too large to build a septic tank, it is necessary to join the sewage pipe network or install sewage treatment equipment. If you need to build septic tanks, you need to sign a sewage cleaning agreement with the Municipal Fertilizer Management Office of the Environmental Sanitation Bureau, and report a copy of the agreement to the Environmental Protection Bureau).

4. Submit the EIA report (which is the responsibility of the EIA company).

5. After receiving the submitted EIA report, the management section of the Environmental Protection Bureau will go to the site for investigation (the workshop kitchen and canteen kitchen need to be equipped with oil fume treatment equipment).

6. Examination and approval of environmental impact assessment report

7. After the construction of supporting environmental protection facilities is completed or on the premise that relevant environmental protection measures have been implemented, it is suggested that the unit entrust a qualified environmental protection completion acceptance monitoring unit for acceptance monitoring (which will be carried out by the monitoring station of the Environmental Protection Bureau).

8. After the acceptance monitoring is qualified and the acceptance monitoring report is obtained, such materials as Application for Acceptance of Environmental Protection for Construction Project Completion, self-inspection report on environmental protection of construction project, environmental protection rules and regulations of the unit, and acceptance materials for standardized remediation of sewage outlets (except those that are unnecessary) shall be filled in. The electronic version of the above information will be sent to the mailbox of the Environmental Protection Bureau, and the official text will be printed after being verified by the Environmental Protection Bureau.

9. Prepare the Acceptance Monitoring Report, the Application for Environmental Protection Acceptance of Construction Project Completion, the Environmental Protection Self-inspection Report of Construction Project, the Environmental Protection Rules and Regulations of the Unit, and the Acceptance Materials for Standardized Renovation of Sewage Outlet (except unnecessary ones) and submit them to the Environmental Protection Bureau in triplicate, and the Environmental Protection Bureau will organize on-site acceptance.

11. After the on-site acceptance is qualified, the Environmental Protection Bureau will issue an acceptance opinion of the project.