1. Gansu Lanzhou garbage power generation project: The first phase has a daily garbage treatment capacity of 2,000 tons, the second phase has a daily garbage treatment capacity of 4,000 tons, and the annual incineration treatment capacity is 6.5438+0.5 million tons.
2. Kunming garbage power generation project in Yunnan: the first phase will treat 700 tons of domestic garbage every day. After the second phase is completed, the daily treatment capacity will reach 1.050 tons, and the annual incineration treatment capacity will reach 390,000 tons.
3. Hubei Xianning Garbage Power Generation Project: The first phase will handle 600 tons of domestic garbage per day, the second phase will handle 900 tons of domestic garbage per day, and the annual incineration capacity will be 330,000 tons.