Initial stage of construction
What I want to do is:
Apply for a decoration permit
Print a decoration notice and paste it in the
Unit door (notify neighbors)
Required information: ID card, house purchase contract and related information.
note:
It is suggested to install a list of activities in the decoration permit, and the decoration company can provide relevant information.
Hard loading stage
I. Demolition and transformation of the main body (7-8 days)
What should a decoration company do:
Shovel wall skin
sabotage
Build a wall
Glaze the balcony
Remove rubbish
Install central air conditioning
install underfloor heating
What I want to do is:
1. Contact the vehicle to clean up the construction waste.
Step 2 buy toilets and bathrooms
Buy central air conditioning
4. Confirm the floor heating laying mode
note:
Do a good job in floor drain protection to prevent construction waste sewer blockage. If you want to install (water purifier, water dispenser, garbage disposal, etc. ), make an appointment together; If there is floor heating, the fresh air shall coordinate with the construction party. If it is necessary to equip the whole house with intelligent equipment, it will only be constructed in the demolition stage.
Second, hydropower transformation stage (about 10 day)
What should a decoration company do:
Water and electricity disclosure
Circuit laying
Waterway laying
Reconstruction of wall drainage and launching
Embedded faucet
drill
Hydropower point inspection
Hydropower accounting
What I want to do is:
1. Buy whole house tiles.
2. Door stone and window stone
3. Have a preliminary understanding of whole house customization;
4. Let the master air-condition in the study.
note:
You can buy a floor drain online during the hydropower period, which will be cheaper.
The confirmation of hydropower stations requires the presence of the owner, designer and foreman.
Four, woodworking stage (about 25 days)
What should a decoration company do:
Woodworking base
Special modeling
Embedded lamp
Viewpoint embedding
Open position of lamp
Opening size of lamps and lanterns
Measuring gate
Woodworking acceptance
What I want to do is:
1. Confirm the shape, size and position of the front veneer, stone and partition!
2. Woodworking means: wood, tiles and oil. The principle is that whoever is dirty will go first,
3. Wooden door installation. In the meantime, install it! The hardware is ready
note:
Main keel spacing 1000mm, secondary keel spacing 400mm, lifting point spacing 1000mm, ceiling width greater than 700 mm. ..
The side keel is made of light steel keel, fixed with expansion screws, with a distance of 600 mm There are two rivets for the fixed side keel and the auxiliary keel, and the main keel should be in a straight line.
V. Oil production stage (about 35 days)
White decoration company to do:
Wall treatment
Determine the wall material
Grinding acceptance
Color mixing and painting
Paint completion acceptance
What I want to do is:
1. Choose the ending, furniture and appliances.
2. Customize double scales for the whole house.
3. Tuyere winding
Step 4 buy a switch panel
5. Hardware procurement
Step 6 buy tile sealant
note:
Be sure to scrape the putty 2-3 times, and then scrape it when it is dry.
Save a small jar and draw it later.
Installation stage of intransitive verbs (about 15 days)
keep sth clean
Panel installation of switch lamp
Hardware installation
Paint repair
Cabinet installation
Sanitary ware installation
Indoor wooden door installation
What I want to do is:
1. After installation, notify the decoration company to repair the wall.
2. Contact the wooden floor to make an appointment for installation after the hard installation is completed.
3. Excess materials should be returned.
4. Make an appointment for land reclamation and cleaning time
note:
Some decoration companies include the cost of cleaning and hardware installation, so you should consult the designer in advance.
Soft assembly stage
Six, furniture and household appliances into the arena (time)
In principle, enter the site in the order of big pieces first and then small pieces.
When buying furniture and home appliances, you can consider buying necessities first, and then slowly buying other things.
Seven, ventilation, formaldehyde
Number eight, report for duty