Current location - Recipe Complete Network - Catering training - Seek a complete construction organization design and budget for residential or teaching buildings.
Seek a complete construction organization design and budget for residential or teaching buildings.
Engineering characteristics

1, general situation of buildings

(1) and * * middle schools have a building area of 4248m2.

(2) Building height

The building height of the teaching building is 22.2 meters, the ground floor height is 4.5 meters, and other floors are 3.6 meters.

(3) Floor

Toilet floor is ceramic tile bathroom floor, ceramic tiles are anti-slip and wear-resistant bricks, stair floor and steps are anti-slip and wear-resistant bricks with anti-slip strips, and other floors are anti-slip and wear-resistant bricks; The indoor floor of the stepped classroom is 100 thick concrete polished brick floor, and the overhead floor is 60 thick concrete terrazzo floor, which is divided into 1000× 1000 squares with three thick copper bars. The bathroom is 80 thick concrete ceramic floor tiles, and the bathroom should be waterproof.

(4), roof waterproof

20mm mortar leveling, three felt four oil waterproof! Roof plastering

(5), indoor metope

The bathroom wall is glazed tile with 200×300 white tiles to the top; The other is fangci paint, with a thickness of 18, and a lime mortar wall with a thickness of1:3,2, and then leveled twice.

(6), outdoor metope

The exterior wall is white and pink tiles, the door frame is cultural stone, and the roof is pink pottery tile.

(7), doors and windows

The gate is made of aluminum alloy glass door, others are ordinary wooden doors, and the balcony doors above the second floor are made of push-pull aluminum alloy. Uniformly installed by a special installation unit, and the windows are aluminum alloy windows.

2. Structural overview

(1), this project is subject to 7-degree seismic fortification, and the seismic grade is frame III.

(2) The fire resistance rating of this building is Grade II.

(4), masonry

Solid brick with strength grade of MU 10 is used for indoor masonry below the ground, and M5 cement mortar is used for masonry. Indoor masonry above the ground is built with small aerated concrete blocks with strength grade of MU7.5 and M5 mixed mortar. 120 thick brick wall is built with M5 concrete mortar of MU7.5 brick; 180 thick brick wall is built with MU7.5 brick M5 concrete mortar; The infilled wall of reinforced concrete frame structure is built with M5 mixed mortar of MU7.5 brick.

Chapter II Site Organization and Labor Allocation

I. Construction objectives

(1), quality objective-ensure that the first acceptance rate of this project is 100%, the first acceptance rate of this project is 85%, the quality reaches the excellent project and the lifelong quality responsibility system is implemented, and the system of regular return visits is implemented after the project is completed.

(2) Time limit for a project-According to the time limit for a project stipulated by the state and the bidding requirements, the time limit for this project is determined to be 200 days (calendar days).

(3) Safety construction goal-strengthen safety management and safety protection, ensure no serious injuries and accidents, and control the monthly frequency of minor injuries below 1‰.

(4) The goal of civilized construction is to maintain the surrounding environment. During the construction period, control the pollution and noise, coordinate the relationship with the surrounding units, and ensure to meet the standards of Zhuhai civilized construction model project.

(5) Service objective-timely, complete, accurate and friendly service to ensure the satisfaction of the owner (user) and implement the service commitment system.

Second, the construction organization and management

1, project management organization

The main persons in charge of this project site are as follows:

Project manager: engineer, first-class project manager.

Deputy project manager: engineer, first-class project manager.

Chief Engineer of the Project: Senior Engineer

3, on-site project management system

According to the provisions of our company's ISO900 1:2000: 2000 quality management system document and the characteristics of this project, the project management system is established to make the project management standardized, institutionalized and standardized. Management system and measures are as follows:

Fourth, the general layout of the construction site

1, basis for construction layout

(1), the original data of construction area;

(2), the location and scale of all the original and proposed projects;

(3), the construction scheme of all construction facilities;

(4), construction scheme, construction schedule and resource consumption plan;

(5) The construction unit can provide living facilities.

2, the construction layout principle

(1), the building layout should be compact and reasonable, and the construction land should be reduced as much as possible;

(2) Organize transportation reasonably, ensure smooth transportation roads on site, and minimize on-site transportation costs;

(3) Assembled construction facilities should be used as far as possible to reduce the loss of relocation and improve the installation speed of construction facilities;

(4) The layout of construction facilities should meet the requirements of convenient production, which is beneficial to life, fire safety, environmental protection and labor protection.

3. General plan

See the construction layout (attached figure 1) for details.

Chapter III Construction Machinery and Equipment

According to the characteristics of this project, construction methods, construction progress and the existing mechanical equipment of our unit, the main mechanical equipment to be put into this project construction is as follows:

1, earthwork excavation is equipped with two excavators and 10 bulk material transport vehicle;

2. The vertical transportation of the main structure of this bidding project is planned to set up 1 tower crane with an arm length of 55m;;

3. Set up four three-car steel derricks, two for the teaching building and two for the modern information center, so as to facilitate the vertical transportation of masonry and painting construction materials;

Chapter IV Overall Deployment of Construction

I. Overview

The teaching building project of Anhui * * middle school has a construction area of 4206m2, and the structure type adopts reinforced concrete cast-in-place frame structure, with the main body divided into six floors. This project has a heavy workload, and the total construction period is no more than 200 days. Therefore, in order to complete the construction task of this project with high quality and high efficiency, careful construction deployment must be carried out according to the characteristics of this project. After scheme optimization, it is planned to set the total construction period as 200 calendar days, formulate countermeasures and measures according to the key points and characteristics of the project, and take protective measures for the surrounding environment during the whole construction process.

1, technical input

Select excellent management personnel to form the project department of this project site, and implement the planning, organization, coordination, control, supervision and command functions for the project construction.

2. Ensure sufficient labor input.

In order to ensure sufficient labor input, our company's managers and workers are fully equipped. During the construction, the crossing process of carpentry, steel bar, concrete and bricklayer should be reasonable and compact in time and space to meet the construction needs.

3, turnover materials, construction machinery equipped to ensure the construction needs.

According to the requirements of the List of Construction Machinery and Turnover Materials, provide turnover materials and construction machinery in time. Tower crane, vertical steel derrick, mortar machine and other construction machinery should work normally, civil engineering should be coordinated with various professional projects, and the supply of materials used in the project should be timely and sufficient. By increasing the input of manpower, material resources and financial resources, the whole project will be completed with high quality, speed, safety and civilization.

4. Adopt dynamic management.

With the total construction period as the goal and the stage control plan as the guarantee, dynamic management is adopted in the construction to make the construction organization scientific and reasonable and ensure that the stage plan is completed on schedule or ahead of schedule. Carry out overall management, carefully prepare a feasible total project schedule, and use network planning technology and corresponding monthly, ten-day and weekly construction operation plans. Give each operation team a production plan, so that the construction and production can be coordinated from top to bottom, and the long-term and short-term plans can be connected.

The overall progress plan is controlled by microcomputer, and daily balance and weekly scheduling are adhered to to ensure the implementation of the monthly plan, thus ensuring the realization of the overall goal of the project.

Second, the division of construction period

The bidding project of the teaching building project in this middle school mainly includes the main building and an affiliated building. According to the characteristics of this project, it is planned to divide the project plane into two construction areas, with the main body as the first construction area and the annex building as the second construction area. During construction, the two construction areas are organized synchronously, and each construction area adopts parallel running water and three-dimensional intersection as a whole.

Third, the construction process and construction sequence

1, general construction principles

Follow the general construction principle of "underground first, above ground, structure first, enclosure first, main body first, decoration first, civil engineering first, installation and embedding first, and reservation should be synchronized with civil engineering construction".

5, the construction sequence of each stage

(1), preparation stage

On-site investigation → establishment of plane control network → inspection of elevation and leveling points → building positioning.

(2), foundation construction

Laying excavation sideline → earthwork excavation → trench inspection → independent foundation, strip foundation, ground beam, bricklaying → backfill soil.

(3), the main construction

Measuring elastic line → column rebar binding → beam-column template → column concrete → beam-slab template installation → beam-slab rebar binding → beam-slab concrete → maintenance → masonry.

(4) Interior decoration

Construction sequence of ceiling, wall and ground first.

(5), outdoor decoration

Exterior wall decoration begins after the completion of the main body and exterior wall construction, and the exterior wall decoration adopts the top-down construction sequence.

(6), installation project

Reserved and embedded → Installation → Debugging

(7), cleaning and acceptance

Comprehensive inspection → self-inspection, error correction and repair → arrangement of completion data → indoor and outdoor cleaning → completion acceptance.

Four. Description of construction general plan

1, general construction instructions

(1), construction survey

Use level to control elevation, theodolite to control axis, establish plane control network and elevation leveling points, and set control piles as needed.

(2), foundation construction

Earthwork is excavated mechanically, rammed by rammer and poured with commercial concrete.

(3), the main construction

The external scaffold adopts steel pipe scaffold, dense mesh safety net, the top frame adopts steel pipe top frame, the formwork adopts wooden formwork, and the commercial concrete is transported by concrete pump.

(4), indoor and outdoor decoration

Choose the indoor construction team with similar engineering construction experience and skilled technology for construction, and the outdoor coating project shall be constructed by the construction team designated by Party A. ..

(5), installation and indoor and outdoor water supply and drainage

For indoor installation, pre-embedded iron holes are reserved during main construction, mechanical excavation is adopted for outdoor pipeline excavation and drainage works, and manual excavation is adopted for water supply works.

(6), roof and bathroom, bathroom and other waterproof.

Select a team with waterproof engineering construction qualification and experience to carry out the construction to ensure the construction quality.

2. Key points of construction organization

(1), in the construction organization, the construction is arranged according to the principle of "overall arrangement, step-by-step implementation, balanced production and following the procedures". Arrange enough construction strength and mechanical equipment, and carry out multi-point and multi-surface construction in stages in each process to ensure the construction period.

(2) Prepare all the work of the construction project in advance, and make preparations for the decoration project during the main construction to ensure the close connection and coordination of each working procedure.

(3), the implementation of rainy days, typhoons and high temperature weather and climate construction measures, to ensure the progress and quality of the project.

(4), pays special attention to the coordination of each part, each time, each working procedure construction, reasonable organization construction, strive for the best production efficiency.

(5) Coordinate the relationship between all parties to ensure the orderly, sustained and coordinated development of the work.

(6) Strengthen the repair and maintenance of machinery on the construction site to ensure the normal operation of machinery and ensure the normal and orderly construction.

Chapter V Construction Preparation

A, the construction technology preparation

(1), investigating meteorology, topography, hydrogeology and material resources;

(2) Organize on-site construction personnel to be familiar with and review the construction drawings and related technical measures, and prepare relevant implementation plans. On the basis of construction disclosure, technical personnel will make detailed technical disclosure to all construction personnel on the general situation of the project, construction scheme, technical measures, construction points and matters needing attention in special parts, so as to carry out construction according to the designed construction drawings, specifications and construction scheme;

(3), study the construction drawings, in conjunction with the design institute, the construction unit, quality supervision unit and supervision unit, make records of the blue prints.the design as a basis for construction.

(4) Conduct self-examination, organize the construction management personnel of each type of work to review the relevant drawings of this type of work, and master and understand the details in the drawings;

(5) Organize professional construction teams to study construction drawings and agree on construction cooperation;

(6), organize the blue prints.the design, by the designer for disclosure, understand the design intent and construction quality standards, accurately grasp the details in the design drawings;

(7), plan disclosure to the team, list the project construction task list, make the team clear the task, quality, safety, progress, etc. ;

(8) Preparation for the working face: check whether the roads and horizontal transportation are unblocked, and the workplace should be cleaned;

(9) Clean up the quality, specifications and quantity of materials and components, and transport a considerable part to the designated job site;

(10), construction machinery in place and put into trial operation, do a good job of maintenance, to ensure the normal operation of construction mechanical energy.

(1 1), train construction personnel to master new technologies and new processes: important posts and special posts need training, and they can only take up their posts after passing the examination.

(12), according to the construction layout, set up temporary facilities, arrange construction machines and tools, do a good job in the construction road, keep the water and electricity unblocked, and do a good job in the maintenance of various construction machinery.

(13), pay special attention to the safety disclosure of construction technology. Through the safety technical disclosure, the construction personnel involved in this project can know fairly well the technical requirements and safety standards, which is convenient for scientific construction and operation according to reasonable technology.

(14), prepare the construction budget to provide reliable guidance for construction and production.

(15), strengthen raw material inspection, provide raw material test report and concrete mixture ratio report in time to ensure construction quality.

(16), according to the environmental conditions around the site, the comprehensive control measures for safe production and civilized construction were formulated.

Second, the site production preparation

1, site preparation

(1), in conjunction with the owner, Party A, and the supervision representative, recheck the red line point and carry out setting-out measurement. Use theodolite and level to establish construction control points and set plane control points, set permanent coordinates and horizontal foundation piles, and do a good job of protection and visa of survey control points.

(2), construction water, electricity, drainage, etc. Investigate, including water source, water quantity, water pressure, nozzle position, power supply capacity, line distance, drainage direction, etc. Prepare the construction plan for water and electricity consumption, arrange water and electricity according to the requirements of the plan, and complete the relevant procedures for sewage pipe connection.

(3) For the installation project, do a good job in verifying and processing the attachment data and drawings, and collect data according to the nature, installation essentials and technical requirements of the main equipment of the project; Collect requirements for joint debugging and prepare instruments and tools for debugging.

2. Temporary facilities

(1), laying construction drainage sewer pipe and sewage main pipe;

(2), laying temporary roads, temporary water supply and power supply lines;

(3), set up sporadic concrete mixer and mortar mixer.

Third, the construction personnel to prepare

(1), select high-quality construction teams from the labor market established by the company, and determine the labor demand at each stage according to the requirements of construction procedures and total construction schedule in the construction organization design;

(2) Do a good job in preparing the workers to enter the site, educate them in technology, safety, ideology and legal system, educate them to establish the correct idea of "quality first, safety first", and make them abide by the technical regulations on construction and safety and local public security laws and regulations;

(3), make good logistics arrangements, do a good job in the construction of temporary facilities, solve the problem of food, housing, medical care and work for the workers who enter the site, so that the workers who enter the site can quickly put into construction and fully mobilize their production enthusiasm.

Fourth, preparation of working conditions.

(1), plan disclosure and technical disclosure to the team, and issue the construction task list, so that the team can clearly define the requirements of tasks, quality, safety and progress.

(2) Preparation of working face: check whether roads and horizontal transportation are unblocked and clean up the job site.

(3) Check the quality specifications and quantity of materials and components, and send a considerable part to the designated job site.

(4), construction machinery in place and commissioning, do a good job of maintenance, etc. , to ensure the normal operation of construction machinery performance.

Verb (abbreviation of verb) Material planning

1, material management

(1). Preparation of material plan: According to the construction progress plan, calculate the ten-day and weekly consumption plans of materials and components, and submit them to the material procurement department for implementation one week in advance.

(2) Management of material consumption quota: Material accounting should be based on material construction quota, regularly check and analyze the implementation of consumption quota, focus on checking the differences between the quota materials and the actual materials, and continuously improve the level of material management.

(3) Inventory management of materials

1), strictly check the specifications, quantity and quality of incoming raw materials, find problems and distinguish responsibilities. Only when the quantity, quality and specifications meet the requirements of the procurement documents can the acceptance and warehousing procedures be completed.

2), warehousing materials should be recorded in the material account. Material certificate, certificate of approval and re-inspection report shall be stored by number. There are identification requirements, to do a good job of identification.

3) The storage capacity should be neat and the layout should be reasonable. Materials should be stored in clear specifications, old and new, and the quantity will be known at a glance. Materials stored in the open air should be padded up and down when necessary and neatly stacked. Articles stored in warehouses and sheds should be displayed in containers (racks) to prevent extrusion.

(4) Site management of materials

1), strengthen material management, prohibit defective and unqualified materials from entering the construction site, and strictly implement the "four inspections" system of variety inspection, specification inspection, quality inspection and quantity inspection for on-site materials.

2), to carry out production saving activities, according to the quota acquisition for each team, the day record, record at the end of the month, implement the system of saving prizes, make the material plan implemented.

2. Preparation of building materials

(1), according to the construction schedule and quantity analysis in the construction budget, prepare the material consumption plan required by the project as the basis for preparing materials, supplying materials, determining warehouses, stacking sites and organizing transportation.

(2), according to the material consumption plan, do a good job of material application and procurement, make the plan implemented.

(3) Organize the materials to enter the site as planned and keep them properly.

Six, construction machinery and equipment preparation

(1), according to the requirements, quantity and construction progress of mechanical equipment and construction machines and tools in the construction organization design, prepare the plan for the amount of construction machines and tools needed and the exit and entrance;

(2) After the mechanical equipment comes into play, it should be placed in the specified place and manner, and the corresponding maintenance and debugging should be carried out to ensure the normal operation of construction mechanical energy.

Chapter VI Project Construction Progress Plan

A, the principle of construction schedule planning

The preparation of the construction schedule of this project is based on the principle of meeting the requirements of the bidding documents for the construction period, and strives to complete the project tasks ahead of schedule on the premise of safety, high quality, high efficiency and rationality.

Second, the time limit for a project goal

According to the requirements of the tender documents, the total construction period of this project is 220 days. Our company will arrange the construction scientifically and reasonably in strict accordance with the requirements of the construction period to ensure the realization of the target construction period.

Three, the main partial project (process) plan control

The project name is planned construction period and planned construction time.

Construction preparation, measuring and setting out for 8 days 1~8 days.

Earthwork excavation of foundation pit takes 20 days and 9~29 days.

The main structure of the upper cover was constructed for 92 days, 26~ 1 18 days.

75 days for interior engineering and interior decoration engineering, the first 1 15~ 190 days.

Exterior wall decoration works for 55 days, 135~ 190 days.

Roofing and waterproofing works for 30 days 160~ 190 days

/kloc-dismantle the external wall grille in 0/0 day, 185~ 195 day.

Mechanical and electrical installation works 149 days 4 1~ 190 days

Fourth, schedule control and management.

1. This plan is a guiding plan. How to achieve better operability is formulated by the project manager and deepened by the technical director. The technical department of the company is responsible for supervision and tracking assistance.

2. The control point target of this plan must be completed on schedule.

3, in-depth planning and implementation plan should pay attention to the following points.

(1), the determination of working relationship is mainly based on the requirements of working procedure, technological process and working face, and the arrangement of labor force and turnover materials is secondary. The working relationship must be simple and the operability should be maximized. Even if the construction is abnormal, the working relationship basically does not need to be adjusted, and the planning network will not be broken.

(2), from the planning to ensure scientific and reasonable process schedule, ensure the smooth development of construction.

(3), make full use of the working face, to ensure the rhythm and rationality of construction, at the same time, can make all kinds of labor on the working face relatively independent construction.

(4) Try to ensure the balance of labor force in the construction process.

4. Make in-depth preparations for the next stage of planning five days in advance.

5. Check and adjust the plan once a day in the structural stage, and report it to the project manager for approval before implementation.

6, after the monthly plan to the professional builder, and key control points for disclosure.

7. The professional builder accurately calculates the demand plan and mobilization time of advocate materials and turnover materials according to the schedule, and submits it to the project manager for review. According to the reality of the balanced use of labor force, the quantity demand of labor force is planned and adjusted to properly solve the problems of workload, fullness and balanced use of labor force.

8. All data in the process of plan management shall be saved.

Five, the construction progress plan crossing diagram (see attached figure 2)

Chapter VII Time limit for a project guarantee system

Due to the short construction period of this project, in order to ensure the quality and quantity of this project to be completed on time, our company will plan to adopt the operation mode of large corps, increase the input of manpower and material resources, and provide strong guarantee from the aspects of construction scheme preparation, organization setting, resource allocation, construction plan, process arrangement, safety production, logistics supply working mechanism, construction period of various sub-projects and external environment.

Second, each division subdivisional work period guarantee measures

1, foundation engineering

1. The quality of time limit for the foundation project of this project directly affects the realization of the whole project construction progress. Therefore, in the construction, we must control the relationship between foundation pile construction and backfill construction to ensure that the foundation project can be completed as scheduled according to the construction schedule.

2, equipped with enough construction machinery, and often check the construction machinery, to ensure the normal operation of construction mechanical energy.

2, template engineering

1, the formwork adopts brand-new plywood, steel concrete formwork and special steel formwork, reasonably calculate the number and turnover times of formwork, and equip enough formwork.

2, reasonable arrangement of template in and out of time and quantity, to avoid the disconnect between processes caused by insufficient template quantity.

3, reasonable stacking in the process of use, careful maintenance, regular inspection, will be unqualified template eliminated in time.

4, the use of skilled carpentry, improve the template installation success rate at a time, so as to speed up the template installation and disassembly.

5. Before template installation, formulate a reasonable and feasible template support system to shorten the template installation time.

3, steel engineering

1, be familiar with the construction drawings carefully, do a good job of pumping and materials in time, and make full preparations for the on-site reinforcement processing.

2. Steel bars are processed on site in advance, and the processed steel bars are directly hoisted to the construction operation surface by tower crane to ensure the smooth installation of steel bars.

3. Arrange the processing and stacking positions of steel bars within the radius of gyration of the crane boom, so as to reduce the secondary transportation of steel bars at the site and shorten the transportation time.

4. Do a good job of sorting, stacking and marking on-site steel bars to avoid rework and repeated installation caused by misuse of steel bars.

5, equipped with enough steel processing, production, installation machines and tools, to ensure the smooth progress of steel installation.

6. Before installation, mark the number, model and setting-out of structural steel bars in the corresponding template position, and reasonably organize the installation sequence of steel bars in each part.

7, reinforced with tower crane transportation, reduce the labor intensity of workers, improve productivity.

8, in the process of steel bar safety, hold people carefully check, to ensure the safety and quality of steel bar, avoid rework.

4, concrete engineering

1, according to the strength grade of concrete used in this project, do a good job of concrete mixture ratio test in advance, so as to guide construction.

2, set up enough concrete machinery, and strengthen the daily inspection and maintenance of concrete construction machinery, to ensure the normal operation of machinery, so that concrete can be transported smoothly at the scene.

3. Reasonably arrange the overlapping relationship of concrete pouring time in each construction section to avoid the slowdown caused by simultaneous pouring in each section.

5, whitewashing operation project

1. Strictly select construction operators and select excellent construction teams for construction.

2, adhere to the technical disclosure, adhere to the principle of open circuit between examples, strictly monitor the team construction quality, avoid rework.

3. In terms of planning, our group will fully consider the relationship and influence of alternate construction of each working procedure on time limit for a project, quality and product protection, and reasonably arrange the overlapping of working procedures to ensure smooth and balanced paint construction and meet the requirements of time limit for a project.

4, painting workload is bigger, we must increase the investment of construction personnel, in order to speed up the construction progress, to ensure that the project can be completed and delivered in advance.

5, masonry, decoration engineering, etc. On the premise of not affecting the construction of the main structure, cooperate as soon as possible.

6, waterproof engineering

Chapter VIII Construction Scheme and Technical Measures

I. General situation of construction

Second, the earthwork

The steel bars are processed and shaped at the site according to the drawing design requirements, and then hoisted to the construction area by tower crane. Before steel binding, you should be familiar with the drawings and check whether the grade, diameter, shape, size and quantity of semi-finished steel bars are consistent with the material card. If there are any mistakes and omissions, they should be corrected and supplemented. Draw the positioning line of steel bar installation, and indicate the specification, shape, size and quantity of steel bar at the binding part, and brush the concrete surface at the position of construction joint with steel wire brush.

1, reinforcement connection mode

In order to ensure the construction quality, electroslag pressure welding is proposed for the vertical steel bar connection of columns with a diameter of 20 ㎜ and columns with a diameter of less than 20 mm, and binding lap joint is proposed for the vertical steel bar connection of beams with a diameter greater than or equal to18 mm. Flash butt welding or one-sided lap welding is proposed. The remaining steel bars with a diameter less than 18mm are to be bound and lapped.

Fourth, the template project

The first floor of the teaching building in this project is 4.2m high, and the height above the second floor is 3.6m.. Due to the high height of the first floor and dense steel bars, the construction is difficult, so we must pay enough attention to it during construction. Its formwork support scheme is not only the difficulty of formwork engineering, but also the difficulty of this project. We must determine the formwork support scheme through detailed calculation and report it to relevant departments for approval.

Five, concrete engineering

Due to the large amount of concrete used in this project, in order to meet the progress requirements of this project, all the concrete in this project adopts commercial concrete. During construction, the main body of the teaching building is constructed by flowing water with the corridor as the boundary. In this project, there are many concrete labels, including C 10, C25 and C30. Before pouring, the location and quantity of pouring must be clear. Concrete is transported to the pouring site by a fixed concrete pump.

Six, scaffolding engineering

According to the facade and structural characteristics of this project, the external scaffold of this project is planned to adopt the traditional floor-mounted steel pipe scaffold. Scaffolding for external walls is erected along the periphery of the building. Scaffolding must catch up with the requirements of construction progress, and at the same time, hang a dense mesh safety net, set up safety inclined baffles every three floors on the second floor and above, and set up safety platforms at the cage-falling mouth and main entrances and exits of buildings.

Seven, masonry engineering

MU 10 brick and M5 mortar are used for masonry below 0.00 in this project. During construction, -20mm 1:2 cement mortar mixed with 5% waterproof agent is defined as -0.06. M7.5 brick and M5 mortar shall be used for masonry above 0.00.

Eight, roofing waterproof engineering

SBS modified waterproof asphalt is used for flat roof waterproofing in this project, which is not suitable for people to enter the roof. Cement mortar leveling to find slope. The waterproof layer is 20MM 1:2.5 cement mortar protective layer. The sloping roof is an inaccessible roof, which is waterproof with inorganic aluminum salt waterproof mortar and decorated with corrugated tiles.

Nine, doors and windows engineering

There are many types of windows in this project, including aluminum alloy sliding window and hidden frame aluminum alloy window; Doors include aluminum alloy doors, plywood doors, stainless steel doors and sliding doors. The glass is 6mm white glass. Unless otherwise specified, doors and windows are made of dark brown frame materials. There are some glass curtain walls on the facade of the teaching building, which are made of white frame materials and painted with green glass. During the construction, they will be designed, manufactured and installed by professional companies.

External wall decoration engineering

The external walls of this project are mainly white and pink 95×45 tiles, and the sloping roof is pink pottery tiles. According to the drawing design requirements, the first floor, the fourth floor, the fifth floor and the protruding part of the roof are decorated with finished line corners. Waterproofing agent should be added to the leveling layer during construction to ensure the construction quality of the wall.

XI。 Building and ground engineering

In this project, except the terrace classroom floor is polished tiles and the overhead ground floor is terrazzo, the other floors are non-slip and wear-resistant floor tiles.