Fan Wen:
Because the construction of this project was suspended during the Spring Festival, now the Spring Festival has passed, the temperature is rising, all the management personnel of the project department have arrived at their posts, and the construction team of the project has basically arrived. The conditions for returning to work are as follows:
1, site management personnel and workers in place.
* * Project Manager 10 person for this project. By February 20th, 20xx, all project department managers were on duty.
2. Safety education and system inspection.
After inspection, the safety inspection system has been established and the safety account has been collected. The emergency plan is complete, the operation procedures are in good condition, and the inspection records of mechanical equipment, temporary electricity consumption and fire fighting equipment are complete. Participate in every working procedure and mechanical operation. All special operations personnel hold relevant certificates, and have made an application report for inspection and resumption of work as required.
In March, our project department conducted safety education and safety technical disclosure for employees who returned to work after the Spring Festival, and signed a safety responsibility letter with the team leader. After the holiday, the statistics of new special operations personnel have basically ended, and the declaration procedures for special operations personnel are being handled.
3. Safe production.
The project department inspected the safety production in the site and office, and the situation was good. The project department re-erected some temporary power lines dismantled before the Spring Festival, inspected the three-level distribution box and the two-level leakage protection switch, and dismantled some random connections. On-site temporary electricity consumption basically meets the specification requirements. The mouth of the cave, limb protection in place.
4. Civilized construction.
The project department set up a civilized construction team to be responsible for the maintenance and replacement of the on-site enclosure, daily cleaning and damaged enclosure.
5. Operation of construction machinery and equipment.
At present, all the machinery and equipment on the construction site have passed the debugging. After inspection and rectification, our project department is ready to resume work after the Spring Festival and has the conditions to resume work. It is planned to start construction on March 6th, 20xx.