Planning and latest progress of Wuhan wildlife kingdom
Wuhan Wildlife Kingdom is divided into three phases, of which the first phase mainly includes parks such as wildlife world, fairy tale forest, bird paradise and parking facilities. Let's take a look at the planning and latest progress of these projects.

I. Planning and Latest Progress of Wuhan Wildlife Kingdom

The first phase investment of Wuhan Wildlife Kingdom Project is about 500 million yuan. The planning and construction contents include: parking lot, comprehensive service area, bosom friend valley, falcon valley, fairy tale forest, bird paradise, wildlife world and supporting facilities.

The parking lot includes parking spots for foreign vehicles and main transfer points for traffic battery cars. The total planned parking space of the ecological parking lot is 1339.

The construction of the comprehensive service area includes squares, gates, ticketing centers, etc. At present, 90% of the project progress has been completed;

Yin Zhigu's construction contents include Yin Zhi Square, high mountains and flowing water, colorful parrot steel structure net, etc. At present, 60% of the landscape flow has been completed, and Cai Yinggu is carrying out Skynet and infrastructure construction.

The construction of Eagle Hunting Valley includes the eagle-themed animal viewing area, the secret cabin in the forest and the plank road. , has been completed at present;

The main animals in the fairy tale forest are cute pets such as giant pandas, zebras and giraffes. At present, giraffe, zebra pavilion, ostrich and camel cage have been built, and racetrack venues and stables are under construction.

The construction of bird paradise, including high-altitude plank road, bird breeding center and bird watching platform, has been completed at present;

The contents of wildlife world construction include wild animal stocking areas such as Brown Bear Pavilion, Tiger Pavilion and Lion Pavilion, grazing animals free-range areas and related supporting facilities. The cage construction in the wildlife area has been completed, and the purse seine construction is currently underway.

Among the supporting facilities, 2 sewage treatment stations have been built and are under construction 1. The construction of post station, quarantine yard and veterinary hospital was completed, and the greening was steadily promoted.