1. Install from the nose, install the intermediate frames of each section in turn, and install the tailstock. Before installing the frame, the center line must be pulled on the whole length of the conveyor to ensure that the allowable error between the frame and the center line is within an acceptable range.
2. Install the driving device in a proper position, pay attention to make the transmission shaft perpendicular to the center line of the conveyor, make the width center of the driving roller coincide with the center line of the conveyor, and make the shaft of the reducer parallel to the transmission shaft. At the same time, all shafts and rollers should be horizontal.
3. Install the roller frame of the upper and lower rollers so that the transmission has a slowly changing arc. Fix the frame on the foundation or floor to ensure stability and reliability. After fixing, the feeding and discharging devices can be installed.