Interim Measures of Xining Municipality on the Administration of Urban Housing Demolition
Article 1 In order to strengthen and standardize the management behavior of urban house demolition, ensure the safe, civilized and orderly operation of the house demolition site, and ensure the smooth progress of construction projects, these Measures are formulated in accordance with the State Council's "Regulations on the Administration of Urban House Demolition" and other laws and regulations, combined with the actual situation of this Municipality. ? Article 2 These Measures shall be observed in the implementation, supervision and management of the demolition of urban houses and their ancillary facilities within the municipal area of this Municipality. ?

These Measures are not applicable to the demolition management of temporary houses, military facilities, churches, temples, cultural relics and houses occupied by villagers outside construction projects. ? Third city housing demolition management department is the competent department of urban housing demolition in this city, responsible for the supervision and management of urban housing demolition within the administrative area of this city, and implement the annual assessment system for housing demolition construction units.

The district construction administrative department is responsible for the daily supervision and management of the urban housing demolition site within its administrative area. ?

Urban management, safety supervision, public security and other administrative departments should do a good job in the management of urban housing demolition operations according to the division of responsibilities. ? Fourth urban housing demolition responsibility system. ?

Demolition in the process of "housing demolition permit", it should be with the housing location of the district construction administrative departments signed a letter of responsibility for housing demolition safety construction, environmental sanitation, dust pollution control. The responsibility book shall be uniformly formulated by the municipal housing demolition management department. Fifth urban housing demolition construction units shall have the corresponding qualifications, and construction units that do not have the qualifications for housing demolition construction shall not carry out housing demolition. ?

City housing demolition construction units shall meet the following conditions:

(a) with three or more construction qualification certificates; ?

(two) the implementation of blasting operations must be carried out by blasting enterprises with corresponding qualifications. ? Article 6 The demolisher shall contract the house demolition project to a house demolition construction unit with corresponding qualification grade through bidding or agreement. Seventh demolition should sign a house demolition contract with the house demolition construction unit, and submit the following materials to the district construction administrative department for the record within 5 days before the house demolition construction:

(a) the qualification certificate of the housing demolition construction unit; ?

(two) the "house demolition contract" signed with the house demolition construction unit; ?

(three) the responsibility of safe construction, environmental sanitation and dust pollution control of house demolition; ?

(four) a statement that the demolished house and its ancillary facilities may endanger the adjacent buildings; ?

(five) the demolition of construction organization plan, safety operation procedures and accident emergency treatment plan, as well as dust and noise reduction measures; ?

The implementation of blasting operations shall comply with the provisions of the state on the management of civil explosives. ?

The district construction administrative department shall, after receiving the filing materials specified in the preceding paragraph, conduct a review within 2 days. To meet the conditions, should be issued to the "city housing demolition project notice"; Do not meet the conditions, should give a written reply, and put forward rectification opinions within a time limit. ?

The district construction administrative department shall, after receiving the materials for the record of the demolition, file a record with the municipal housing demolition administrative department in writing within 10 days. Article 8 A house demolition contract shall include the following main contents:

(a) the names and addresses of the legal entities of both parties, and the names, genders, ages and addresses of the legal representatives; ?

(two) the structure, construction area and construction age of the demolished house; ?

(three) housing demolition costs, settlement methods and performance period; ?

(four) the intention to dismantle the old materials; ?

(5) Site management and safety measures for house demolition; ?

(six) the rights and obligations of both parties; ?

(seven) the liability for breach of contract and the settlement of contract disputes; ?

(8) others. ? Ninth urban housing demolition construction units in the "urban housing demolition project announcement" issued after the implementation of housing demolition. ? Tenth urban housing demolition construction units to implement the overall responsibility system for safe demolition construction. The following safety measures should be taken to dismantle the construction site:

(a) before the demolition of construction work, it shall conduct on-the-spot investigation on the demolished houses and their appendages, and formulate corresponding construction operation plans and preventive measures according to the operation means adopted; ?

(two) the demolition of the construction site shall set up signs, indicating the name of the demolition construction unit, the name of the person in charge of the unit, the name of the person in charge of the construction operation, and the name of the safety supervisor, and accept social supervision; ?

(3) Dismantle the temporary fence not less than 1.80m on the construction site, and implement closed operation; ?

(four) the person in charge of the construction site and the main technical person in charge shall be present to direct, and the construction personnel must wear safety helmets; ?

(5) When an accident occurs in the process of house demolition, it must be reported to the administrative department of house demolition in the city or county and the local safety supervision and construction department in time, and emergency measures shall be taken to minimize casualties and accidents. ? Eleventh urban housing demolition construction units should strengthen the legal education and training of demolition staff. Before entering a new post or a new construction site, the house demolition construction personnel shall receive safety education, and those who have not received education and training or failed the education and training examination shall not be allowed to work at their posts. ?