Do you know the answer to the task book of construction organization course design-multi-storey brick-concrete office building? ! !
Construction organization course design task book

-Multi-storey brick-concrete office building

I. Design conditions

1, building overview

This project is the office building of XX company in a province, which is located on the side of XX road in the suburb of XX. The total plane or object surface is 6262㎡, and the simplest surface shape is L-shaped, with a length of 6 1.77m from north to south and 39.44m from east to west. Most of the building has five floors, with a height of18.95m, and some have six floors, with a height of 22.45m. The annex building (axis F ~ L) has a basement, axis ⑾ has a temperature joint, and axis F has a settlement joint ... See the attached drawings for its simplest surface, elevation and simplest surface.

The load-bearing structure of this project is brick-concrete structure except that the hall part is cast-in-place reinforced concrete semi-frame structure. The buried depth of toe foundation is 1.9 m, and the strip brick toe foundation is built on C 15 plain concrete cushion. The toe foundation is provided with cast-in-place reinforced concrete ring beams, which are supported by solid brick walls, and each floor is provided with cast-in-place reinforced concrete ring beams; Anti-seismic structural columns are set at the replacement position of the inner and outer walls and the corner of the outer wall; Toilets and bathrooms use cast-in-place floors, while other floors and roofs use prefabricated reinforced concrete perforated plates. Girders, stairs and overhangs are all cast-in-place reinforced concrete members.

In addition to the hall, corridor, laboratory, bathroom, back stairs, lifting steps, indoor floors are all cement mortar. White mortar spraying 106 coating is mainly used for interior decoration, and paint is mainly used for exterior decoration. The wall between windows is dry stone, and the waist line and window cover are decorative tiles. Aproll is a disposable facing for unreinforced concrete.

The roof is made of slag concrete, two felt and three oil waterproof layers and mung bean sand. The roof of the master was paved with concrete precast slabs.

Equipment installation and water, heating and electricity engineering are the same as civil engineering.

2. Geological and environmental conditions

According to the survey report, the soil is Grade I macroporous loess, the bearing capacity of natural foundation is 1.50 kn/m2, and the coordinates of spring water are 7 ~ 8m below the surface. The maximum freezing depth of soil in this area is 0.5m.

The south side of the construction site is the completed building, the west side of the north side is the wall of the company's property, and the east side is the XX highway. Do not occupy the sidewalk within 3 meters of the sidewalk, and do not damage the trees along the street. There are still high-voltage transmission lines and telephone lines passing above the sidewalk (see the simplest plan).

3, the construction period

Limit the total construction period to 10 months.

4, the scene image conditions

During the construction period, the dominant wind direction is easterly, the rainy season is September, and the winter is from 65438+February to 65438+ 10 and February of the following year.

5, construction technology and economic conditions

The construction task shall be undertaken by the municipal construction company, and assigned by the municipal construction company 1 the construction team shall be responsible. 20 masons, carpenters 16, and other auxiliary jobs 140, such as steel workers, mechanics, electricians, general workers, etc. According to the needs of construction, some migrant workers assist in the work. In the decoration stage, 70 people can be transferred from other construction teams to Plaster workers.

Construction electricity and water are introduced from urban power supply and water supply network. Building materials and prefabricated components can be transported to the site by car. The perforated plate is made by the prefabrication factory of urban construction corporation (transportation distance 10km), and the wooden doors and windows are made by the municipal wood processing factory (transportation distance is 7km).

Temporary works, in addition to the workers' dormitory can deceive the completed family apartment building, other necessary temporary measures should be built on the spot.

Cranes that can be used for construction include QT 1-6 tower crane and QT 1-2 tower crane. Besides Jiefang brand (5 tons), there are also Yellow River brand (8 tons) that can be used. Winches, all kinds of mixers, woodworking machinery, concrete vibrators, scaffolding and plates can be supplied according to the planned demand.

VI. Physical quantities of major projects (see table 1- 1)

7. Bill of quantities of main structures (see table 1-2)

8, engineering quota (see Annex "National Unified Construction Engineering Foundation Quota"); And refer to the quotas in relevant cases)

Second, the design content

1, the choice of construction scheme

(1) divide the construction section and determine the direction of construction flow;

⑵ Determine the construction points of special parts;

(3) Determine the construction sequence.

2, the planning degree of the construction process.

According to the determined construction sequence and available resources, the division of labor organizes the flow construction, and prepares the itemized plan of the unit project construction process. This includes the labor force curve.

Third, the design requirements

1. Some project construction schemes are reasonable and feasible.

2. The process arrangement is reasonable, the connection is proper, the process and organization requirements are met, and the construction period meets the requirements.

3. All the guarantee measures are feasible, economical and reasonable.

4. Design results:

(1) Construction organization design 1 copy (A4 paper)

(2) 1 process project plan crossplot (A4 or A3 paper)