3 model articles of construction report

construction means that the project is built as planned. Now I'm going to make a report on the construction. This article is a model construction report I compiled for you, for reference only.

model article 1 of construction report: project construction report

Dear leader:

This project is based on the design of Jiaxing Water Resources and Hydropower Exploration and Design Institute and the design and requirements of Haiyan Water Conservancy Bureau, Qinshan Street and Vineyard Owner. After signing the contract on August 31th, it will enter the site on September 7th and be accepted on October 6th, with a total time of * * * lasting 45 days, and all the contents of the project will be completed, specifically. Data acquisition of pressurized pump house in the first station, control and protection of water pump, valve reform; Installation of automatic fertilizer adding system, pipeline reconstruction and canopy construction; Optical fiber laying and welding of the whole system, laying of power line, video signal line and video control line of the whole system; Simple decoration of the control room of the control center, installation of network cabinet, installation of operation desk, configuration of software and hardware of automatic control system, etc.

I. Overview

This project is located next to the North Tuanshi Factory in Qinshan Town, and there is a pressurized pumping station and two 31KW pumps near the river, one for use and one for standby, with frequency conversion control and automatic manual control. The original intake vacuum drainage tank is equipped with two manual gate valves, which has no water shortage protection function. The vineyard * * * is about 351 mu, and there are 16 manual valve wells (the depth of the wells is slightly higher than the ground level). All the work must be manually operated by people at the site. In order to meet the requirements of modern agriculture and landscaping irrigation, and achieve the purposes of scientific water use, improving labor productivity and increasing production and income, a set of automatic drip irrigation fertilization system is specially built. In this automatic control system, all data are transmitted to the monitoring center by optical fiber communication.

II. Construction situation

1. Our company entered the site on September 7, and all products under the contract were delivered to the site and stationed in the office building of the original stone factory of Sanlian Bridge. According to the construction plan, all our personnel are stationed in the office building and start construction.

2. The site record of the specific construction situation is as follows:

9.3 Go to the Water Conservancy Bureau for a meeting, coordinate the project progress

9.11 go to the site, communicate the site construction situation with Chen Gong of the Water Conservancy Bureau, the secretary of the village committee and Ma Gong of the town committee, and reach an agreement on the plan. Prepare to arrive at the site before September 15 after all the goods are ready, and then reach an agreement with all parties before construction. During the construction period, we can live in the central control room on site to facilitate the work and supervise the equipment. Because I didn't notice the weekend when I made the plan, I will enter the venue on Monday, September 17. During this period, the company has made some relevant preparations.

at 16: 31 pm on September 7, all the goods will be transported to the central control room for construction. Buy quilts at night and live on the spot.

9.18 negotiation on renovation of Qing valve well, building, valve installation, video installation plan, etc. Negotiate the electrical transformation of the first station, and determine the nodes for collecting data (variable signal, manual automatic signal, frequency, pressure signal, fault signal, output signal, etc., where X1 is the automatic operation of No.1 pump and X1 is the automatic operation of No.2 pump); The gate valve is replaced by 2 check valves; Simple confirmation of wall painting and door replacement in the control center: replacing the security door, filling up three broken glasses, buying an operation console and installing the valve manhole cover; Purchasing daily necessities; Purchase engineering supplies such as wire pliers, electric drills, sandpaper, glass glue (guns), paint, auxiliary contacts, etc. Check the installation of the fertilizer feeder.

9.19 Sunny prepares to install the valve well by itself, buy bricks, cement, valves, pipes, etc., coordinate with the installer, and prepare to start construction on September 21; Install the control cabinet; Rust removal and painting of doors and windows in the central control room;

9.21 The pipeline preparation work, solenoid valve and pressure transmitter were rebuilt in the valve well. Pipes, elbows, tees and other pipe fittings are prepared and transported to the site; Complete the installation of a control cabinet.

9.21 wiring of four control cabinets in cloudy weather; Buy SYWV75-5 video cable 611 meters, RVVP2*1.1 signal cable 311 meters, power cable 2? 2.5 sheath line 611 meters; Buy plastic steel door 1711? 611, 4;

9.21 wiring of four control cabinets installed in cloudy weather is completed;

9.22 Rain plans to install optical fiber, valve installation and pipeline reconstruction; Failed to install due to rain; Control cabinet debugging; Perfect drawings; Collect and sort out product information (instructions, certificates, etc.); Video testing;

9.23 Fine fiber laying is completed; Installation of solenoid valve in valve well and pipeline reconstruction are completed; In the afternoon, the valve well house will be built; Software testing;

9.24 Fine valve well doors and shutters are transported to the site and installed in the valve well room; Video testing; Industrial computer test;

9.25 The check valve of Qingyi Initial Station goes to Haiyan and gets it back; Negotiate with Manager Tang about the installation of the fertilizer feeder, and initially discuss to build it at the first station; Four valve wells are built to a height of 1811mm to complete; Control cabinet channel test;

on September 26, the preliminary powder wall of the four valve wells was finished, and it was ready to cover the roof the next day; Make a video monitor installation bracket on the top of the valve well, and plan to fix it on the roof of the valve well the next day; Collect, control and debug all kinds of data, and make good preparations;

9.27 The top of the valve manhole cover was cleared. At 15: 31 pm, the leader of the Water Conservancy Bureau said that the valve well needed to be pointed, and the construction of the valve well was suspended.

9.28 sunny test control box communication at the last station; In the afternoon, I went to the Water Conservancy Bureau to communicate related matters, and the communication result: it was determined that the valve well top was still flat, and the construction continued on September 29; The fertilizer adding machine was installed at the first station, and it was not installed until the boss Zhang of 9.29 Vineyard came to the site for confirmation. Buy a security door; Buy a computer console.

9.29 Qing communicated with Boss Zhang about the installation of the fertilizer feeder; The welder handled the installation of the check valve and water flow switch in the first station, and the installation was completed.

install the fertilizer feeder at the main water outlet pipe of the first station on the sunny morning of 9.31, and return to Shanghai in the afternoon. Plan to return to Haiyan in April.

11.4 arrive at Haiyan at noon on a sunny day to buy paint, etc., and start painting the central control room at 1 pm. Buy materials for wiring preparation in the central control room.

11.5 Pipe wiring from valve wells M26 and 27 to valve wells M31 and 31; Central control room room coating; Contact anti-corrosion plastic-wood installation;

11.6 Pipe wiring from valve wells M28 and 29 to valve wells M32 and 33; Four valve wells are filled with paint; Central control room floor cleaning, cleaning.

11.7 Clear the pipe wiring from valve wells M31 and M31 to valve wells M32 and M33; Install the control cabinets of the first station, No.31, No.31 and No.32 and No.33 valve wells; Install the power inlet line of the control center.

install the control cabinets of the initial station, M26, 27 and M28, 29 valve wells in 11.8. Pipe piercing and sensor installation in the valve shaft room;

11.9 Pipe piercing and sensor installation are carried out in the shaft room of Qing valve; Complete the wiring of M26 and 27 valve wells, and the installation of anticorrosive plastic wood on the external wall

11.11 Clear, complete the wiring of each station, and complete the installation of anticorrosive plastic wood on the external wall of M31 and 31 valve wells;

11.11 Put cameras, sensors and other equipment in place for field test; Polishing the wall of the control room, making skirting lines and painting windows; The requirements have not been met, so we need to continue working on the evening of 12.

11.12 Make the grounding wire of each valve well, fill the vacuum drainage tank of the first station with water, and prepare for commissioning; Fix the pipeline of the fertilizer feeder and the fertilizer barrel; Test machine.

11.13 install DN251 main valve and make valve well; Debug the pressure, humidity and temperature signals of each valve well. The commissioning of the whole line is normal.

iii. quality control

during the construction, we strictly follow the relevant specifications and basis. Such as:

1, General Specification for Equipment Installation, Construction and Acceptance (GB51231-98

2, Specification for Welding Construction and Acceptance of Field Equipment Pipes (p> 3), Specification for Construction and Acceptance of Industrial Metal Pipes (GB51235-97

4), Specification for Construction and Acceptance of Electrical Equipment Installation (GB 51254). Code for Acceptance of Construction Quality of Building Electrical Engineering (GB51313-2112

) In order to ensure the project quality, the direct goal of our quality management is to pursue technical progress and scientific management, and provide customers with high-quality projects and satisfactory services. The organization in quality management, the cultivation and strengthening of employees' quality consciousness and the application of professional technology are not only the guarantee to improve the project quality, but also consistent with the purpose of improving economic benefits. Therefore, ensuring the construction quality of the project is the key to the construction organization of the project. According to the specific situation of this project, we have established a perfect project quality assurance system.

during the preparation of the project construction schedule, the characteristics of many projects, wide coverage and tight construction period are fully considered, and at the same time, the connection and cooperation with the civil main body and decoration projects are fully considered, and the working procedures of installation projects are reasonably arranged to ensure the efficient and orderly construction of the project.

iv. safety management

in this project, the safety management system was strictly implemented to prevent casualties, and it was realized? Zero accidents? Construction site.

doing a good job in safety production leadership is the key. Establish and improve the safety production management guarantee system headed by the manager. At the same time, establish and improve the safety management organization that specializes in line management and group management. The project manager is the first person responsible for production safety, and a safety management team is set up, with 1 full-time safety officers and the team leader as a part-time safety officer. Carry out? Safety first, prevention first? Safety production policy, to ensure that the accident does not happen.

V. Conclusion

According to the actual situation on site, our company completed all links of the whole project process in just 41 days. The monitoring center has the functions of display, storage, query, control, analysis and report. Display specific information of each site; Real-time data acquisition includes:

◆ Collecting the running frequency of water pump and the running pressure of pipe network.

collect the start-stop status of each water pump.

collect the fault status of each water pump.

collect the fault status of the inverter.

The start and stop of the water pump unit can be controlled remotely.

◆ realize the protection function of water shortage at the pump inlet.

collect fault alarm information, such as comprehensive fault, and all models that can be taken out of the original control cabinet can be uploaded.

◆ On-off state and control of valves at each station.

◆ video omni-directional monitoring.

◆ Reliable operation of the fertilizer adding device.

temperature and humidity collection and control of each plot.

the system has the characteristics of strong universality, perfect function, stable performance and reliable operation, and can provide decision-making basis for the operation and scheduling of pumping stations, realize optimal operation, thus reducing production costs, improving efficiency and management, which has positive significance.

Shanghai Dongfang Pump Industry (Group) Co., Ltd.

Model article 2 of construction report: construction summary report

Leaders:

Good afternoon! According to the requirements stipulated in Article 24.1 of the ministerial document "Regulations on the Management of Technical Documents for Municipal Infrastructure Engineering Construction", on behalf of * * * * Construction Engineering Co., Ltd., I will give you a summary report on the construction completion of the first phase of the supporting subsidiary II bid section of Chengnan Jiayuan undertaken by our unit.

I. General situation of the project

This project is located in Friendship Industrial Zone, Songling Town, * * District, * * City, and it is an outdoor auxiliary project of a new residential district. The contracting scope includes: residential roads, rainwater and sewage pipelines and integrated pipelines, landscape paving, street lamp installation, etc. Quality requirements: qualified. I. design overview

the residential area covers an area of 178262m2, and the main road is flexible. It is designed according to the Class III standard of urban secondary roads, with a design speed of 21km/h, a design life of 11 years and a seismic fortification intensity of 6 degrees. Outdoor rainwater and sewage are discharged separately into the municipal pipe networks of Nanliuhe and Binhe Road. The landscape pavement mainly uses granite plates, and the garden road is mainly paved with environmentally-friendly concrete permeable bricks. Nanli Electric High-pressure Cast Aluminum Middle Pole Lamp (courtyard lamp) and Philips energy-saving light source are selected as street lamps. The elevation control points are designed according to the indoor elevation (Wusong 4.811m) of the built single building, and the positioning control is marked with coordinates according to the design general plan. Second, the main structural form

1. Subgrade and pavement:

All subgrade is excavated. Pavement structure: the upper layer adopts 3cmSUP-13 (refer to 3.5%SBS) asphalt concrete surface layer; The lower layer adopts 5cm coarse-grained AC-21C asphalt concrete; The base is 31cm4% cement stabilized macadam, the subgrade is 71cm ballast, and the kerbs are C31 concrete precast flat stone and Wulianhua granite side stone.

2. Drainage pipes:

Outdoor rainwater and sewage pipes are all made of high-density polyethylene (HDPE) double-wall wound drainage pipes, which are connected by elastic flared sealing connectors, and the ring stiffness is not less than 8KN/m2. The design adopts sand and gravel cushion foundation, and the medium coarse sand is backfilled with full groove to 1.5 cm above the pipe top. Inspection wells are made of round bricks. The rainwater outlet adopts the general type B single grate rainwater outlet in Jiangsu Province.

second, the completion of the project

first, the construction period

this project started on April 11, 2113, and all the projects in the contract were completed on February 11, 2113. Second, the completion of the project (major quantities completed):

1. Large earthwork: subgrade excavation of 33,111m3, ballast filling of 23,111m3, trench excavation of 23,111m3, trench filling of 33,111m3, and disposal of the rest;

2. Road: 23,111m2 for 4% cement stabilized macadam base, 8,111m2 for 5+3 asphalt concrete surface and 4,111m for paving kerbs;

3. Drainage and comprehensive pipelines: 6,111 m rainwater and sewage pipelines, 2.4km weak current comprehensive pipelines and more than 2,311 inspection wells have been completed;

4. Landscape engineering: 3111m2 of granite block paving, 611m2 of washed Shiyuan Road, 651m2 of sidewalk paved with environmentally-friendly concrete seepage bricks, 29 flower and tree ponds of various shapes, and 15 sets of leisure seats;

5. Installation works: 415 sets of pole lights (SFT 6167), 111 sets of lawn lights (SFT 4189), 65 sets of floodlights (SFT 9118) and 12.7km of sheathed cables.

III. Quality control

1. Quality management

In order to facilitate the quality control in the construction process, according to the relevant technical standards and specifications and in combination with the actual situation of the project, this project is divided into sub-projects and inspection lots, and reported to the supervision unit for examination and approval.

according to the bidding documents and the contract, the project is divided into four divisions: roads, drainage and integrated pipelines, landscape paving and street lamp installation.

in the road section, * * * completed 9 sub-items and 37 inspection lots; Drainage and comprehensive pipeline * * * completed 5 disciplines and 45 inspection lots; Landscape part * * * Complete 4 disciplines and 3 inspection lots for each discipline; The installation part * * * completed 9 disciplines, with 2 inspection lots for each discipline. * * * There are 27 sub-items in 4 divisions.