Changchun City Engineering Planning Permit Handling Process

The process of handling the project planning permit in Changchun:

1. On every working day, the construction unit will report to the window of the Planning Bureau with relevant materials;

2. When the window staff check and accept the application materials, if they find any mistakes that can be corrected on the spot, they shall allow the applicant to correct them on the spot; If it is found that the materials are incomplete or do not meet the requirements, it shall inform the applicant of all the contents that need to be corrected on the spot;

3. When receiving the application materials, the window staff should register the project construction report and indicate the content and date of receipt;

4. After the application materials are checked by the window staff, they will be transferred to the project manager;

5. After receiving the application materials transferred from the window, the project manager thinks that relevant documents need to be corrected after examination, and informs the applicant in writing that all the contents that need to be corrected should be transferred to the window at one time, and informs the applicant to re-declare after correcting the materials;

6. After the audited application materials are qualified, the project manager will conduct on-site inspection. For the projects that meet the planning requirements, the project manager will complete the countersigning work and transfer it to the Design Department to issue the Construction Land Planning Permit, which will be sent to the project unit through the window; After research does not meet the planning requirements, the project manager will fill in the "Notice of Return" and reply to the construction unit through the window;

7. If it is found that the construction project is directly related to the major interests of others during the process of handling the Construction Land Planning Permit, the applicant and interested parties shall be informed in writing; Applicants and interested parties have the right to make statements and defend themselves;

8. If the applicant or interested party requests a hearing, a hearing procedure shall be held according to the Provisions of Changchun Planning Bureau on the Hearing of Planning Administrative License;

9. if the applicant requests to change the contents of the construction land planning permit, he shall reapply and renew the construction land planning permit according to the prescribed procedures.

The materials required for the construction project planning permit are as follows:

1. Apply for the civil air defense review first and obtain the civil air defense review opinions;

2. The application form for Construction Project Planning Permit is stamped with the official seal of the applicant, the official seal of the designer and the official seal of the civil air defense department;

3. Approval from the planning department;

4. Approval Letter for Construction Land and Red Line Map of Land Use or Land Use Right Certificate;

5. the "construction project planning monitoring report" of the survey institute;

6. Review report issued by the construction drawing review agency;

7. Construction drawings stamped by the construction drawing review agency;

8. The design unit shall provide the stamped building layered area table and functional classification area accounting table;

9. "Summary of Joint Review of Architectural Scheme Design" or "Review Opinion of Architectural Scheme Design", which is the initial design reply;

11. handle the power of attorney of the construction unit and the copy of the ID card of the entrusted agent.

to sum up, many places are under construction now, which generally involves construction projects, and construction projects usually have construction permits.

Legal basis:

Article 41 of the Urban and Rural Planning Law of the People's Republic of China

Where buildings, structures, roads, pipelines and other projects are built in urban and town planning areas, the construction unit or individual shall apply to the competent department of urban and rural planning of the people's government of a city or county or the people's government of a town determined by the people's government of a province, autonomous region or municipality directly under the Central Government for a construction project planning permit.

to apply for a planning permit for a construction project, relevant certification documents for land use, construction project design scheme and other materials shall be submitted. For a construction project that requires the construction unit to prepare a detailed construction plan, it shall also submit a detailed construction plan. For those who meet the regulatory detailed planning and planning conditions, the competent department of urban and rural planning of the people's government of a city or county or the people's government of a town determined by the people's government of a province, autonomous region or municipality directly under the Central Government shall issue a planning permit for the construction project.

the competent department of urban and rural planning of the people's government of a city or county or the people's government of a town determined by the people's government of a province, autonomous region or municipality directly under the central government shall publish the general plan of the approved detailed planning and design scheme of the construction project according to law.