Plumbing renovation is a crucial link in home decoration, and its quality is closely related to the safety of the homeowner. Therefore, owners need to pay great attention during the renovation of water and electricity, and it is best to supervise the work on site. Beijing's "little girl" Lulu's family has also been busy decorating in the past few days, and they are also very cautious when it comes to water and electricity. But what is the result?
House information: 76_
Decoration style: American half package
Residing in the community: Beijing Tonghui Homestead
Decoration progress: demolition Renovation, water and electricity renovation
Decoration period: 15 days
March 16, 2015
Construction started today! My boyfriend and I arrived downstairs at our new home at around 9 a.m. and heard a thumping sound coming from upstairs. My boyfriend and I looked at each other blankly and said it couldn't be our home. When I went up to see it, it turned out to be true! The wall has been smashed and the whole house looks like an accident scene, but I am really happy that it has finally started! Great!
Then, we went to the property management company with Foreman Yang to complete the procedures. Foreman Yang was very skilled and said that he had worked here before and everything went smoothly. The property management fee was RMB 2,951, including a deposit of RMB 2,000, garbage removal freight of RMB 800, and decoration management fee. I've completed the task today, and I'm really looking forward to the results after the demolition is complete.
March 17, 2015
After get off work today, I ran to my new home with my boyfriend to take a look at it. The changes are amazing! The wall was beaten, the open kitchen took shape, half of the bathroom tiles were removed, and there were more than 20 bags of garbage alone! When I walked in, I thought it was cement, but it was actually garbage!
March 20, 2015
The wonderful weekend is coming! Today the responsible foreman called us specifically to meet us and made an appointment at noon tomorrow. Going for a run around the house every day has become a habit. Now that the walls have been removed and the house is very clean, I feel from the bottom of my heart that finding a reliable decoration company and a responsible foreman can really solve many problems during the decoration process! Everyone must keep their eyes open in the future, and even if it is slower, they must find a good one, otherwise problems will occur in the middle, which will waste time and cause more trouble.
March 24, 2015
On Monday and Tuesday, you can see that the master workers are still working diligently. At present, the location of the power supply at home has been basically determined, and the cement, yellow sand and stone slabs for the walls have all been put in place. I had always wanted to build an open kitchen, but I also had to block oil fumes. I thought of connecting the two walls with large glass to create a sense of transparency from top to bottom, and make an arc connection at the corners. As a result, the master worker said today that it is not possible because sockets cannot be placed in the flue and the sockets can only be placed on the wall. We also need to put a refrigerator in the corner. So no matter what, the wall must be built. I struggled for a long time this morning and finally decided to build a wall.
March 28, 2015
The windows are finally installed! The workers started installing the glass from 8 a.m. to 1 p.m. They bought environmentally friendly glass glue for 10 yuan per meter. The final result is: the three-layer glass is very soundproof, and the large windows have good transparency. I am very satisfied.
It has been a week since the water and electricity grooves were installed at home, and the PPR used for the water pipes is white and smooth. I didn't bother to check the brand of the wires, they were grounded. Recently, neighbors have frequently reported that the noise from our home decoration is too loud, which has disturbed the old man next door. We are going to come to apologize to the old man tomorrow and discuss the time of the water and electricity project with the foreman.
March 29, 2015
Today, Sunday, the dust was flying as soon as I entered the house, and the air was full of ash. Three workers and four chief processors were busy at work. It is worth mentioning that the wall was finally built today! The foreman specially showed us the insulation layer made for the balcony. He added insulation to the original wall, laid bricks, and added a layer of wire mesh outside the bricks to ensure it was strong. It was really done very carefully.
March 30, 2015
My boyfriend didn’t go to work all day today and was at the construction site troubleshooting the shifting of the kitchen water valve. We first went to the top floor to discuss with the owner about the time to turn off the water valve, and then asked the property management company to come over to do it. The property management company sent workers to move our home, and put up notices about water shutoffs throughout the building. Finally, it was replaced, which was quite a hassle. Tomorrow morning I have made an appointment with the foreman to discuss the water and electricity issues. The inspection will be completed on Thursday!
April 1, 2015
I took half a day off today to go to the construction site to watch the plumbers and electricians take measurements for me. The master is very kind, very conscientious and transparent in his work. He will tell you clearly how many meters each pipe will have. The writing on the wall will give you confidence. When settling the bill, there are two types: exposed tubes and hidden tubes. Hidden tubes are more expensive, while exposed tubes are cheaper. The circuits are divided into 2.5 square meters and 4 square meters. Large electricity consumers such as kitchens should try to use 4 square meters of wires. I have a small house of 76 square meters. It cost 13,686 to replace all the water pipes and circuits. It is really expensive!
April 02, 2015
Today is the big day for our home’s water and electricity acceptance! The supervisor is very responsible and good, and the inspections are also careful. Our foreman is also serious and responsible, especially punctual, which I particularly appreciate.
Yesterday, the foreman knew that the water pipes would be inspected today, so he pressed the water pipes to 0.6 in advance. Generally, the inspection requires the pressure to be 0.8. Everything seems to be normal now.
Today I saw that the brand used for my water pipes is Liansu. I asked Du Niang and she found that the brand is good. The electrical conduit is from Yuxing Hongyan. I asked Du Niang and it seems that it is not a big brand but it is enough for household use. The wires are all from Huiyuan, and the materials are not of inferior quality, which I am particularly satisfied with.
The current problem is that there is no tin foil protection at the intersection of the wires. The foreman said that it will be added tomorrow. Today I paid the water and electricity payment and another part of the decoration payment, totaling 18,006, and the card is dripping blood
Supervision on April 2, 2015
I received a task in the evening and will go to the construction site today for water and electricity acceptance. , confirm the specific acceptance time with the owner in a timely manner. We arrived at the construction site on time today. Let's take a look at the on-site acceptance status:
1. First, verify whether the brands of water pipes and wires on site are consistent with the quotation.
2. The grooves on the wall should be very horizontal and vertical, and the embedded wire pipe should be at least 1.5 meters away from the wall.
3. The bathroom floor drain was relocated and a tee was made to facilitate the drainage of the washing machine and washbasin drain. Pay attention to the slope of the water later.
4. The distance between hot and cold water pipes should be 150 in accordance with the standard, which is now the standard size of shower faucets.
5. It is recommended to use hoses to protect the ceiling light cords, and install lights later to avoid scratches on the exposed parts.
6. Try to position 1/3 of the water outlet in the wall. The plug should be just flush with the tiles after tiling to avoid installation problems.
7. To avoid signal interference at the intersection of strong and weak electricity on the ground, it is recommended to wrap it with aluminum foil and take isolation measures.
8. It is recommended that the water pipes in the bathroom be routed through the ceiling. In the future, whether it is maintenance or safety hazards, we will do our best.
9. It is recommended that all light sockets use 2.5MM wires. It is recommended that kitchen air conditioners or places with high power be equipped with 4MM wires to avoid short circuits caused by excessive power in the future.
10. Finally, use a hydraulic press to perform a pressure test on the water pipe. The pressure reaches 1.5 times the normal water pressure, which is 0.6-0.8MPA. The pressure must be stabilized for half an hour without losing pressure to pass the test.
Acceptance summary: This water and electricity acceptance was very smooth. All materials were verified to be correct according to the quotation. The slotted wiring of water pipes and wires were basically horizontal and vertical and met the acceptance requirements. I hope that the decoration company will continue to work hard in the future and grasp the construction site well. every detail part.
Wonderful reading recommendations:
It is difficult to choose materials for summer decoration. Here are some tips to learn from it
You need to do this in the face of summer decoration pollution
< p>Start from scratch Tang Xiaoguo’s happy decoration diaryFive pieces of furniture that say I love you and fill the house with romance
Decoration moves forward Xiao Xiaosu’s water and electricity decoration diary