Detailed analysis of the entry order of the main materials for decoration; Prepare the materials without delaying the construction period.

The renovation period is a concern of many owners. If you want the project not to be postponed, you must make preparations in advance to ensure that the materials can enter the site on time. But for the owners who decorate for the first time, there are so many decoration materials that it is difficult to control when to enter the market. Let's take a look at how to arrange the order of the main materials entering the venue.

1. Water and electricity pipelines enter the site:

Before the water and electricity transformation, the water and electricity transformation is the first project of the decoration project. Therefore, the materials needed for the water and electricity decoration must be determined before the construction starts, including water pipes, wires, threading pipes, etc. Note that the wires are available in 2.5 square meters and 4 square meters, and the water pipes are also divided into cold water pipes and hot water pipes. If the materials do not meet the requirements, the owner can only be responsible for the problems in the project. But if the decoration company is responsible for providing the main materials, then the owners only need to do a good job of acceptance. However, before the hydropower starts, the owner needs to set the kitchen cabinets, and make an appointment with the cabinet manufacturer and the hydropower master to discuss the route of the kitchen hydropower. Similarly, if you want to install a bathtub in the bathroom, you should also take into account the issue of water supply and discharge in the bathtub.

2. Tile mobilization: Before bricklayer's mobilization,

There are many kinds of decoration materials designed by bricklayer's engineering, so it is very necessary to arrange the mobilization order of each material. Usually, spot materials such as tiles and caulking agents are better, and some materials need to be booked, so they need to be prepared in advance. Bricklayer's decoration design involves a lot of stone installation, such as windowsill, floor, doorsill and skirting line. These stones need to be measured in advance and then customized, which takes about 3-4 days in advance. In addition, the floor drain can be bought in the bricklayer's stage, and can be installed together when the bricklayer lays the floor tiles.

Third, the wall decoration materials will enter the site: before the wall and ground foundation works are completed

After the bricklayer is finished, the painter should enter the site. Now the painter's basic job is to paint or wallpaper the wall. So buy the paint or wallpaper one or two days before the bricklayer finishes. To buy these materials, we must first measure the area that needs to be decorated, and then calculate the required amount. Avoid the second purchase, especially the wallpaper, which may be different from the batch and model of the wallpaper purchased for the first time, and the stitching marks will be obvious after pasting.

Fourth, kitchen and bathroom supplies enter the site: before the overall renovation, the foundation renovation is completed after the above three projects are finished, and the rest is the installation of various sanitary wares and lamps. So after painting the wall, you can install the faucet, toilet, basin, etc. These materials should be selected in advance and installed in the venue. General lamps can be bought now, and some lamps can also be ordered in advance.

V. Cleaning work: Before completion

After completion, cleaning work should be done well. If the floor is installed at home, you need to buy floor wax, stone wax and so on in advance. Cleaning staff also need to book in advance, usually 2-3 days in advance. At this stage, we need to buy curtains, and then hang them up after the cleaning is completed, so as not to get dirty during the renovation and cleaning. Curtains are generally measured by merchants on the spot, and the customization time takes about one month.

(The above answer was published on 29-11-2116, and the current relevant house purchase policy should be based on the actual situation)