Can the hg plot in Baishi Village, Yantai be started in July?
I can't. The first-phase reconstruction project of Baishi Village in Zhifu District (G and H plots) is the key project of the municipal and district governments. The collection began on August 20 13. However, due to the inability to contact nearly 200 indigenous residents, the cancellation procedures of the original land certificate and the original real estate license were delayed, which led to the suspension of the first phase of Baishi Reconstruction Project for 7 years. To this end, the district party committee and the district government held coordination and promotion meetings for many times, requesting the Baishi Sub-district Office to find and contact the indigenous people as soon as possible, but by July 5, 2022, the street (neighborhood committee) had exhausted all means and still could not contact all relevant parties. So we still can't start work in July.