From February 2nd, the prevention and control of post-holiday resumption of work in Hangzhou's city-wide construction field strictly implemented the requirements of the Notice on Strengthening the Prevention and Control of Pneumonia Infected by novel coronavirus in Hangzhou's Construction Field (Hangzhou Construction Engineering Development [2121] No.33), focused on the important people, major projects and key links in the key nodes of post-holiday resumption of work, fully implemented all-round epidemic prevention measures, and compacted the main responsibilities of all parties involved in the construction according to the requirements of "one site, one plan". Strictly implement the "three strictness" of epidemic investigation and control, start the "five no's" of epidemic prevention and safety guarantee and the "two strictness, two prohibitions and two reductions" of internal environmental sanitation of the construction site to ensure that the epidemic prevention and control in the construction field is scientific, effective and in place.
how to prepare for returning to work after the holiday, and what are the precautions? 15 professional authorities answer you, look down.
1. When will the construction site resume work? Before 24 o'clock on February 9, the municipal housing construction site shall not be resumed or newly started. Before this time limit, no other personnel shall be allowed to enter the construction site and office area for work except the left-behind personnel and inspectors on duty.
2. What are the regulations for the return of construction site personnel? The main management personnel such as the project manager of the construction unit and the chief supervision engineer of the supervision unit should arrive at their posts before February 9, and prepare the employment plan according to the demand of returning to work for each project and report it to the local supervision institution. Other personnel will gradually return to Hangzhou in an orderly manner after February 9 in accordance with the principle that managers will return to their posts first and other personnel will be in place gradually; Employees and workers in Hubei, Wenzhou, Wenling, Taizhou, and huangyan district, Taizhou, require all enterprises to implement the main responsibility and actively advise them not to come to Hangzhou in the near future. No other personnel shall be allowed to enter the project except the left-behind personnel and inspectors on duty.
3. How to conduct on-site inspection for the returned personnel from the construction site? Establish a strict information screening system, comprehensively screen the situation of each returnee and establish a health card, and report the situation of returnees on the same day to the supervision institution every day. Strictly implement the "five unifications", that is, check and register all personnel stationed at the construction site and personnel and vehicles entering the construction site; The body temperature of all personnel entering the site shall be measured; Set up a relatively independent medical observation area, and observe people with a history of residence or travel in key epidemic areas and those who have had close contact with the above-mentioned people in isolation for 14 days; If there are suspected cases, the construction site will be shut down; Those who travel to key epidemic areas will be strictly controlled.
4. how to isolate the returnees from the construction site?
all personnel who return to the construction site from other places will be observed in isolation for 7 days, such as those from key epidemic areas such as Hubei, Wenzhou, Wenling, Taizhou and huangyan district, Taizhou, or newcomers with a history of residence and contact in the above areas and normal body temperature. They will be observed in isolation for 14 days, and the general contractor will be responsible for the implementation of the site. Once found to have fever symptoms, immediately report to the health and epidemic prevention departments and local streets for centralized treatment.
5. how to monitor the health of personnel during isolation?
pay attention to the physical condition of the isolated personnel, and take temperature tests at least twice a day and register them one by one. After the expiration of the isolation period, you can only work at your post if you are healthy.
6. What preparations should be made for the construction site to resume work after the holiday during the epidemic prevention and control period?
from February 11, all projects that have been declared for resumption of work must have the conditions for safe production, normal construction conditions and strict epidemic prevention and control measures. In addition to the complete preparation of machinery, personnel and materials, and the full implementation of the safety production management system, it is necessary to establish a special plan for the prevention and control of epidemic situation after the holiday in accordance with the "one site, one plan", and clarify the regional disinfection, return inspection, personnel protection, employment arrangement and management mechanism to ensure the safety of those who return to work.
7. What are the conditions for the project to resume production safety? Mainly whether the safety basic management meets the requirements; Whether the temporary electricity consumption meets the requirements; Whether the safety protection measures meet the requirements; Whether the lifting equipment and construction tools meet the conditions for safe production; Whether the dangerous projects such as deep foundation pits, scaffolding and formwork projects meet the conditions for safe production; For details, please refer to the Safety Checklist for Returning to Work after the Construction Festival
8. What conditions should the project have to ensure the normal construction of the project? The sources of raw materials such as concrete required for engineering construction have been implemented; The waste residue disposal site and waste residue transportation team for engineering construction have been put in place.
9. What epidemic prevention and control measures should be taken when the project resumes work? First, set up an epidemic prevention and control organization in charge of the project manager, and set up a special post; Second, the epidemic prevention articles are put in place, and the project prepares enough sanitary and epidemic prevention articles such as masks, thermometers and disinfectant (the reserves of masks and disinfectant are not less than one week); The third is to check the exchange history and contact history of the reserve personnel within two weeks. Fourth, according to the requirements of the construction site closed management, do a good job in life, office, work area disinfection; Fifth, a relatively independent medical observation area is set up on site as required, for people who need temporary isolation observation to live in a single room. For details, please refer to Hangzhou Construction Project Resumption Application Form.
11. What are the verification steps for returning to work after the holiday? Self-inspection by the construction unit → review by the supervision unit → review by the construction unit → approval by the territorial construction administrative department. After receiving the application for resumption of work, the construction administrative department shall verify the safe production conditions, ensure the normal construction conditions and epidemic prevention and control measures of the resumed project, and the supervisor shall review and sign for confirmation before resuming work.
11. What are the requirements for disinfection of construction sites, office areas and construction facilities and equipment? Focus on regular and fixed-point disinfection every day during the post-holiday resumption of work, assign special personnel to be responsible for disinfection of the above places and equipment twice in the morning and evening. No work can be resumed without disinfection and sterilization.
12, how to do a good job in daily prevention and control of environmental sanitation in construction sites? Earnestly achieve "two strictness, two prohibitions and two reductions". Strict management of food hygiene, personal hygiene and living hygiene on site to ensure the supply of hot water such as drinking and washing; Strictly do a good job in cleaning, ventilation, disinfection and sterilization of key parts such as dormitory and canteen. It is strictly forbidden to raise, slaughter and eat wild animals in the construction site area, buy food and materials through formal channels, and make every effort to ensure food safety; It is strictly forbidden to dump garbage, and do a good job in garbage storage and transportation, sewage treatment, ditches and sewers dredging. Minimize the access of personnel in the site area and minimize the contact between site personnel and the outside world.
13. How to publicize personnel protection during post-holiday work? Understand disease-related information through official authoritative channels, guide site personnel to improve their awareness and ability to prevent themselves, and do not spread unconfirmed news. Under the premise of not affecting the protection of epidemic prevention materials in local medical and health departments, strengthen the implementation of epidemic prevention materials at the construction site, and do a good job in providing materials such as disinfection materials, washing products, medical masks and infrared temperature measuring instruments to avoid the occurrence of unprotected construction operations.
14. how to manage the contractors during the post-holiday resumption of work? No gathering activities shall be organized before the epidemic situation is lifted. Epidemic prevention and safety education and training should be conducted by means of WeChat and radio. Advocate the adoption of network office and conference mode to reduce the number of people gathering. Suspected cases such as fever are immediately isolated and are not allowed to enter the construction area and office area.
15. What forms should be filled in during the project resumption? The Schedule of Site Employment in the Construction Field of Hangzhou City shall be filled in by the construction and supervision units respectively and then submitted to the territorial supervision institutions. The Construction Project Employee Health Status Declaration Card (Reference) shall be filled in by the personnel of the construction and supervision units respectively, and shall be kept by their respective project departments after being signed and approved by the project manager or director. The List of New (Returned) Hangzhou Personnel for Projects under Construction in Hangzhou shall be filled in by the project department of the construction unit, and then reported to the supervision unit for summary and verification, and reported to the local supervision institution every day. The Application Form for Resumption of Construction Project in Hangzhou shall be filled in by the construction unit, submitted to the construction unit or regional company for review and approval, and submitted to the local supervision institution for approval after review and approval by the supervision unit. The daily information is submitted before 16: 11 on the same day, and special circumstances are reported at any time.