1, determine the location of the greenhouse installation, according to the land area and the current situation, to determine the number and length of the greenhouse;
2, after determining the location of the fixed line, sprinkle lime;
3, in the lime line in accordance with the pre-determined spacing of the skeleton punch holes on both sides of the punch holes in the greenhouse tubes;
4, with the top of the roof connection Pipe to connect the two sides of the trellis tube together;
5, with a spring card card on the top of the longitudinal rod, some for the three longitudinal rods;
6, with a three-piece hardware card card on the film card slot;
7, installed on the trellis reinforcing rod, and after the installation of trellis ends of the reinforcing pipe;
8, cover the film, tighten the film pressure line, a vegetable greenhouse is built successfully.
Note: When installing, the spacing between the trellis tubes should be parallel and consistent, and the width of the trellis door should be appropriate to be able to open into the micro-tiller.