Current location - Recipe Complete Network - Complete cookbook - Planning Route of Jin 'an Avenue in Changsha County
Planning Route of Jin 'an Avenue in Changsha County
The total investment of Jin 'an Avenue Project is 790 million yuan. The whole project is east-west. It starts at the intersection of Xiangdi North Road and Logistics Avenue, crosses Niulanpo from west to east, crosses Laodao River in Daijia Old House, continues eastward to Huilong Village South, and finally reaches the north extension line of Huangxing Avenue, with a total length of 2.895 kilometers. 2 bridges, 8 culverts, passage 1, 2 interchanges and 8 plane crossings. The project is divided into two phases. In the first stage, the Laodaohe Bridge (including ramp bridge and pedestrian walkway) will be built first. In the second stage, after the adjustment of basic farmland, the auxiliary road under the bridge and other subgrade sections, as well as the Yuchangxia Railway Bridge, will be built.