The project acceptance report can be divided into three parts. First, it can describe the scope of acceptance; Second, it can describe the standards of project acceptance; Third, the overall situation of acceptance can be described.
Article 1 of the model project acceptance report:
I. Overview of the Project
Building B5# of Dongheng Times Phase II is located in Shilibao, Chaoyang District, Beijing. The structure type is cast-in-place shear wall structure, raft foundation, basement 1, overground 2 1 floor, local 16 floor, building area 139 14 m2, and building height 16 floor 46m. 2 1 floor is 60m.
Employer: Beijing Fang Heng Real Estate Co., Ltd.
Project leader: Jiang Haitao.
Investigation unit: China Textile Industry Design Institute.
Project leader: Cyndi Luo.
Designer: Huatong Design Consulting Engineering Co., Ltd.
Project leader: Guo Chun.
Construction unit: Beijing Hanjian Group Co., Ltd.
Project leader: Li Hechun
Supervision unit: Beijing Fangcheng Acer Engineering Supervision Co., Ltd.
Project leader: Wang Shizeng.
This project was approved by the beijing municipal commission of development and reform and Beijing Municipal Construction Committees on June 5438+1October 65438+July 2002 (J.J.T.H. [2002] No.581), and the construction permit number of the construction project was [2007] Shi (Chao) Jian Zi. 0 130; The construction project planning permit number is: 2006 G (Z) ZiNo.. 0 123. According to the Regulations on Quality Management of Construction Projects, it was reported to Beijing Chaoyang District Construction Project Quality Supervision Station for registration, and the supervision registration number was: J.J.Zi. No.03 13-8.
Second, the construction drawing design document review
On July 24th, 2006, the Architectural Design and Research Institute of the General Logistics Department reviewed the revised design documents. The original design unit has revised the construction drawing design documents of this project according to the review opinions. The construction drawing design documents of this project meet the requirements of mandatory standards for engineering construction, the foundation and main structure are safe, and the technical review of the construction drawing design documents is qualified.
Three, the construction unit archives engineering data sorting
Entrusted by the construction unit, the supervision unit reviewed the completion files submitted by the construction unit. The construction technical data files, construction management data, main building materials, components and equipment test and inspection reports of the construction unit were complete and effective, which met the filing requirements.
Four, the unit engineering safety and function inspection is completed
The safety and functions of the building and structure, water supply and drainage, heating, electricity and ventilation of this project all meet the design requirements, and have the conditions for testing and testing. After testing and testing, the functions meet the requirements.
5. The project of this unit has completed all the contents stipulated in the contract and construction drawing design documents, and there is no rejection. Quality defects are common faults in general construction quality, and the rectification is completed under the witness of the supervisor, which meets the acceptance requirements.
Six, other related to the construction project acceptance.
1, passed the acceptance of fire protection project in April 2008; In April, 2009, it passed the acceptance of the fire protection project of the Municipal Fire Bureau, and obtained the fire protection acceptance opinion of the building project.
2. On March 24th, 2009, we entrusted a unit with environmental testing qualification to conduct indoor environmental quality sampling, and obtained the indoor environmental quality testing report.
3. In April 2009, we passed the planning acceptance of Chaoyang District Planning Bureau, and obtained the notice of planning acceptance.
Dongheng Times Phase II Project
4. In April 2009, the urban construction archives were submitted to the Municipal Urban Construction Archives for review, and the pre-acceptance letter of urban construction archives issued by the urban construction archives management department was obtained.
Seven. final acceptance of construction
1. Completion acceptance time: On April 20, 2009, the construction unit will organize the survey, design, construction and supervision units to complete the acceptance of the project of this unit.
2, to participate in the acceptance unit personnel
Employer: Beijing Fang Heng Real Estate Co., Ltd.
Project Leader: Jiang Haitao Project Technical Leader: Hou Mingbo.
Civil engineer: HVAC engineer: Zhang.
Electrical Engineer: Zhang Xuan
Investigation unit: China Textile Industry Design Institute.
Project leader: Cyndi Luo.
Designer: Huatong Design Consulting Engineering Co., Ltd.
Project leader: Guo Chun.
Construction unit: Beijing Hanjian Group Co., Ltd.
Project Manager: Zhao Jianyong.
Project technical director: Li Jinping.
Supervision unit: Beijing Fangcheng Acer Engineering Supervision Co., Ltd.
Project leader: Fan Yongyi
HVAC Supervision: Liu Qiang Electrical Supervision: Wu Yunhua
3. Acceptance members have corresponding qualifications.
4. The main problems raised by the design and supervision units during the acceptance are all written rectification plans, witnessed by the supervision in the implementation process, and re-examined by the four parties, which meet the acceptance requirements.
Eight, the overall evaluation of the project, the overall opinion.
The engineering quality of B4# building in Dongheng Times Phase II complies with relevant laws and regulations and mandatory standards for engineering design, and meets the requirements of design documents and contracts. Sub-projects such as foundation, main structure, architectural decoration, building roof, building water supply and drainage, heating installation and electrical installation have passed the quality acceptance, and the quality control data are complete. The engineering safety and main use function testing data of main sub-projects are complete. The sampling results of main functional projects meet the requirements of relevant professional quality acceptance specifications, and the visual quality meets the requirements, and the comprehensive quality meets the acceptance standards.
Beijing Fang Heng Real Estate Co., Ltd.
Project leader (signature):
20__ _ _ _ _ _ _ _
Article 2 of the model project acceptance report:
I. Overview of the Project
Construction unit:
Design unit:
Investigation unit:
Supervision unit:
General contractor:
Quality supervision unit:
The location, construction area, structural type, number of floors and height of the building project mainly include those sub-projects, with emphasis on some design points of sub-projects and important conditions of the project construction;
Second, the project construction basis
1, construction drawings, minutes of the blue prints.the design, contact list of design changes, contract and mandatory provisions of engineering construction.
2.GB50300-200 1 Unified Standard for Acceptance of Construction Quality of Building Engineering
3.GB50202-2002 Code for Acceptance of Construction Quality of Building Foundation Engineering
4.GB50204-2002 Code for Acceptance of Construction Quality of Concrete Structure Engineering (version 20 1 1).
5.GB50203-20 1 1 Code for Acceptance of Construction Quality of Masonry Structure Engineering
6.GB50207-20 12 Code for Quality Acceptance of Roof Engineering
7.GB50209-20 10 Code for Acceptance of Construction Quality of Building Ground Engineering
8.GB502 10-200 1 Code for Quality Acceptance of Building Decoration Engineering
9.GBJ 107-20 10 Concrete Strength Inspection and Evaluation Standard
10, GB50208-20 1 1 Code for quality acceptance of underground waterproofing works
1 1, GB504 1 1-2007 Code for acceptance of construction quality of building energy-saving projects.
12, gb50164-2011"concrete quality control standard"
13, JGJ52-2006 "Standard for Quality and Inspection Methods of Sandstone for Ordinary Concrete"
14, JGJ33-20 12 technical specification for safe use of construction machinery 15, JGJ 18-2003 specification for welding and acceptance of steel bars.
16 and GB50303-2002 Code for Acceptance of Construction Quality of Building Electrical Engineering
17, GB50 168-2006 code for construction and acceptance of cable lines in electrical equipment installation engineering 18, GB50 166-2007 code for construction and acceptance of automatic fire alarm system 19, gb5007.
Note: If the above specifications are not used in this project, don't write them down. If the above specifications are already in the acceptance report of foundation and main structure, don't write them down repeatedly.
Three. Construction process and quality control
Reports on the commencement time of the project (subject to the test pile), the construction time and end time of relevant important parts, the sub-projects and special acceptance time of the foundation and foundation, the main structure, the quality situation and treatment situation in the construction process should be highlighted;
Fourth, the quality self-evaluation of divisional projects.
Write in the form of the following table. If there is none in that division (sub-division) project, don't write it, but fill it in according to the actual division (sub-division) project of the project;
Verification of verb (verb's abbreviation) quality control data
Full-time librarians are responsible for this project data, and they are collected, sorted and filed in strict accordance with the data submission procedures and data sorting required by the supervision unit. All quality assurance materials and inspection lots have been verified by the supervision unit, and the materials are complete and meet the requirements. See table G.0. 1-2 for verification records (table 2).
Six, engineering safety and functional inspection data verification
1, unit engineering safety and function inspection data verification and main function spot check records meet the requirements, and table 3 (g.0.1-3);
2. Observation of inclination and settlement: Several settlement points are arranged around the building in this project, and several measurements have been made. The first observation time is a certain year, a certain month and a certain day, and the last observation time is a certain year, a certain month and a certain day, the maximum and minimum settlement points, the maximum and minimum settlement amount and the maximum settlement difference between two adjacent points; Maximum and minimum tilt points, maximum and minimum tilt amount and direction; (See attached table for details)
Seven. Self-evaluation of engineering visual quality
The comprehensive evaluation of the engineering visual quality of this unit is average or good; See attached table 4 (g.0.1-4) for details;
Eight, safe production and civilized construction
In the process of engineering construction, we should attach importance to safety management, adhere to the policy of "safety first, prevention first", always implement the management system of "safety is for production, and production must be safe", hold regular safety meetings, give three-level education to all employees involved in the construction of this project, and make safety technical disclosure to all sub-projects. The team leader is responsible for the safety work of his team, so that safety work can run through the whole construction process and achieve safe production and civilized construction in time.
Nine, the project pre-acceptance:
The project was pre-accepted on a certain day in a certain year. During the pre-acceptance, all units pointed out that there were still some problems in the construction. In view of the above problems, the project department actively organized relevant construction personnel to carry out rectification, which has been completed within the specified time, verified by the supervision unit and the construction unit, and now meets the requirements of the completion acceptance conditions. (The rectification report is attached)
To sum up, according to the Unified Standard for Construction Quality Acceptance of Building Engineering, the quality acceptance of the sub-projects contained in the unit project is qualified, the quality control data are complete, the safety and function testing data of the sub-projects contained in the unit project are complete, the spot check results of the main functional projects meet the requirements of relevant professional quality acceptance specifications, and the visual quality meets the requirements. The company self-rated the project as qualified. Now please review and approve the relevant units, and humbly accept the valuable opinions put forward by the leaders, experts and colleagues attending the meeting, and we will rectify them in time!
Article 3 of the model project acceptance report:
Application report for project completion acceptance
To Shaanxi Guanzhong Tool Manufacturing Co., Ltd.: Baoji Dingyi Construction Project Management Co., Ltd.
The shantytown renovation project 10# building of Guanzhong Tool Company undertaken by our unit was inspected by the project department and verified by the company, and it was considered that it had the conditions for completion acceptance. Now you are applying for completion acceptance, please organize relevant units to check and verify.
Project manager:
Technical director of the unit:
Construction unit: Baoji No.1 Construction Engineering Co., Ltd.
20__ _ _ _ _ _ _ _
The above is what Bian Xiao shared today, and I hope it will help everyone.